83 Fed. Cl. 594 | Fed. Cl. | 2008
OPINION
Pending before the court are the motion for partial summary judgment by the plaintiffs, Wallace Oenga, et al. (“plaintiffs” or “the Oenga heirs”),
The plaintiffs’ complaint sets forth three claims, each in the alternative. In their first claim (“claim one”), the plaintiffs allege that they were entitled under various statutes and regulations to receive a royalty on the value of oil and gas produced on the allotment and that the government breached its fiduciary responsibilities and trust obligations when it failed to require or collect royalty payments from the lessee.
In their third claim (“claim three”), the plaintiffs allege that the lease and its amendments were intended to extend only to oil and gas development and production from the Niakuk oil field, and therefore the oil companies’ use of the plaintiffs’ allotment to develop and produce oil and gas from the West Niakuk and Lisburne areas constituted breaches of the lease and trespasses. The plaintiffs argue that the government, in turn, breached its duties as set forth in 25 U.S.C. §§ 162.617-162.623 (2001) to send notices and take other actions against these alleged breaches of lease and trespasses, when the plaintiffs made demands to that effect after learning of the use of the allotment for oil and gas development and production from beyond the Niakuk area. The plaintiffs also argue that the facility sharing agreement between BPX, ARCO, and Exxon violated both the lease, as amended, and regulations regarding subleases and assignments of allotted lands.
The government asserts that claims one and two are barred by the six-year statute of limitations set forth in 28 U.S.C. § 2501 (2004).
With regard to claim three, the government and the intervenors do not raise a statute of limitations defense, arguing instead that both the use of the allotment by ARCO and Exxon and the oil and gas development and production from the West Niakuk and Lisburne areas were authorized un
For the reasons set forth below, the court finds that the plaintiffs’ first and second claims are time-barred under the six-year statute of limitations set forth in 28 U.S.C. § 2501, because those claims challenge the mismanagement of trust assets, rather than trust funds, and as such they are not covered by the ITAS. With regard to the plaintiffs’ third claim, the court finds that the development and production of oil and gas from the Lisburne Participating Area (“PA”) through the plaintiffs’ allotment exceeded the scope of the lease and that the plaintiffs have stated a claim that the government breached its money-mandating duty to investigate and take action against such a violation. However, the court finds that disputed issues of fact remain as to whether the scope of the lease, and particularly the “Niakuk Project,” in-eluded development and production of oil and gas from the West Niakuk area. Thus, the question of whether the activities in the West Niakuk area constituted a lease violation giving rise to a money-mandating duty on the part of the government to take action cannot be resolved on summary judgment.
I. BACKGROUND FACTS
The following facts are taken from the parties’ cross-motions for summary judgment, proposed findings of uncontroverted facts,
A. Negotiation of the Original Lease
In 1971, Andrew Oenga (“Mr.Oenga”), an Inupiat Alaska Native, applied for and received an Alaska Native Allotment at Heald Point
Lease negotiations involving BPX, the BIA, and Mr. Oenga and his relatives ensued later in 1988. BPX developed a draft lease, with input from the BIA, using a lease from another allotment as an example. DA 46; see DA 5. BIA Superintendent Michael Staneampiano noted in a July 14, 1988 letter to BPX’s Steven Taylor that, by law, “[n]o lease can be approved for less than fair annual rental ... unless it can be shown to be in the best interest of the landowner.” DA 6.
On September 26, 1988, BIA Realty Specialist Kathleen Dickinson met with Mr. Oenga, his interpreter Rex Okakok,
According to Ms. Dickinson, the “initial purpose” behind the Niakuk Project was “to construct a causeway out to Niakuk island where [BPX’s] drilling facility was to be placed.” DA 21; see also DA 42 (Stipulation
B. Terms of the 1989 Lease
Mr. Oenga signed the final lease on January 19, 1989.
The lease provided for two phases. During the first phase, the land would be let on a year-to-year basis for a maximum of ten years, during which time the lessee would “attempt to obtain required permits for the Niakuk Project.”
The lease provided for an annual payment of $1,600 per acre ($16,000 per year for the initial ten-acre area) for each of the first five years, plus a $25,000 signing bonus. DA 13 ¶¶ 3, 4. BPX would pay the rental amount to the BIA, which would then credit the funds to Mr. Oenga’s Indian Individual Money Account. Id. at ¶ 4. The rental rate could be “increased at successive five-year intervals beginning in the sixth year after rental payments have begun[,] ... based upon either the fair market undeveloped rental value for
The lease’s reappraisal term stated:
[BIA] review for the purposes of establishing the fair rental value of the premises shall be based on the highest and best use of the premises as raw, unimproved vacant lot at the time of the appraisal and shall not be based on the cost or value of improvements or developments made by the Lessee or any income the Lessee derives from the leased premises.
DA 13 ¶ 9 (emphasis added). Thus, the rental payments would not be based on the value of the use of the land for an oil pipeline, a facility to produce oil, or any of the other activities permitted under the lease.
In addition, though the lease initially provided for use of a minimum of ten acres, the lease permitted BPX to amend the lease to “increase or decrease the size of the leased premises at any time at Lessee’s sole discretion,” provided a proportionate increase or decrease in the rental payments was also made. DA 13 ¶ 11. Because BPX had the option to rent the full tract, and because it was permitted to use the unleased premises for activities supporting its operations on the leased premises, Mr. Oenga was effectively unable to enter into other leasing arrangements on the unleased premises. See, e.g., DA 46 ¶ 9 (the BIA refused to allow ARCO to lease part of Parcel B, as discussed below); see also DA 30 (Realty Officer Diane Stevens of Arctic Slope Native Association (“ASNA”) noted that, because of BPX’s option to expand and the impact of the development on the entire parcel, “the entire 40 acres were effectively at the disposal of BPCX]-”)-
Attached to the lease as Exhibit A were two maps, both dated September 21, 1988, entitled “Niakuk Project Location Map” and “Niakuk Onshore Access Road and Pipelines.”
Mr. Oenga died on April 16, 1990, and interest in the allotment was divided among his several heirs in accordance with his last will and testament. DA 14,15.
C. Adjustments and Amendments to the Lease
1. The July 29, 1993 Letter
When BPX was “unable to secure the necessary permits for the causeway,”
On July 29, 1993, BPX formally exercised its option to proceed with the second phase of the lease in a letter from Mr. Hirsh to BIA Superintendent Samuel Demientieff, giving written notice to the BIA “that the first phase of the Niakuk Development Project has been approved and that development will procede [sic]....” DA 20. The letter described the 1989 lease as “provid[ing] authorization for BP[X] to construct production facilities to support development of, and production from, our Niakuk oil accumulation.” Id. (emphasis added). Mr. Hirsh indicated that “an armored production pad will be constructed at the tip of Heald Point” and that “[w]e have also redesigned and relocated our pipelines to the east side of the access road.” Id. The letter further stated that, pursuant to the 1989 lease, “the Lease is converted from a year-to-year basis to a fixed twenty-five year term,” and “BP[X] hereby requests that the Lease be amended so as to increase the size of the Leased Premises from 10 acres to 20 acres effective August 1, 1993,” with a corresponding increase in rent for the “enlarged Leased Premises.” Id.
In the July 29,1993 letter, BPX requested that BIA Superintendent Demientieff “indicate [his] approval of this amendment by signing in the space provided below____” Id. The letter included a signature line for Mr. Demientieff, beneath the statement “The within Lease Amendment is hereby approved____” Id. Mr. Demientieff signed the statement provided by BPX on August 3, 1993. DA 20.
Construction of the “Niakuk production pad” on the plaintiffs’ allotment began in August 1993, with portions of the pad “being constructed on submerged lands owned by the State of Alaska” adjacent to the plaintiffs’ allotment. DA 42.
2. The 1993 Appraisal
On June 15, 1993, the BIA requested a real estate appraisal of the plaintiffs’ Heald Point allotment. DA 18, 21, 23. BIA Staff Appraiser, John R. Cress, inspected the property on June 17, 1993 and prepared an Appraisal Report on August 6, 1993. DA 19. After comparing the property to other leases in the area, Mr. Cress estimated the market rent for the original ten acres to be $16,000 per year, unchanged from the rate set in 1989. DA 19. Mr. Cress’ report noted that the land “remain[ed] undeveloped,” but that “[t]he highest and best use” of the land would be “Industrial—oil or natural gas related development or production site.” DA 19. Ms. Stevens at ASNA informed Leroy Oenga that the 1993 appraisal was taking place via letter dated July 30, 1993. DA 23.
3. The 1994 Amendments
On July 2, 1993, ARCO contacted the BIA about the possibility of leasing part of Parcel B. DA 46 ¶ 9; Pls.’ Attach. (“PLA”) 1 at 11. However, “[b]ecause the 1989 lease to [BPX] gave the lessee the unilateral right to increase the acreage under lease,” Ms. Dickinson of the BIA “reasoned that the allotment owners could not enter into a new lease or sale without getting a release of part of the Parcel B acreage from BP[X]’s rental option.” DA 46 ¶ 9. In her January 20, 2008 declaration, Ms. Dickinson stated, “I am pretty confident that ... the Oenga heirs were made aware of the ARCO feeler shortly after it was received.” Id.
On August 30, 1993, Leroy Oenga sent a letter to Ms. Stevens at ASNA requesting a meeting with BPX in order to “work at a better lease agreement” with the goal of “a lump sum to be paid to the heirs of Andrew Oenga.” DA 27. On October 21, 1993, the Oenga heirs and Ms. Stevens met with representatives of BPX. DA 28. On November 10, 1993, Ms. Stevens sent a letter to BPX proposing various amendments to the lease and identifying areas of conflict. DA 28, 30.
On November 30, 1993, Mr. Hirsh of BPX responded to Ms. Stevens’ letter, agreeing to amend the lease to increase the leased premises to include the entire forty acres of Parcel B, but not agreeing to pay rent for the entire forty acres any earlier than the date that ARCO was denied an opportunity to lease part of the allotment, nor to include a provision requiring mutual consent before decreasing the acreage.
[t]he most likely scenario for third party involvement on Heald Point would be for one or more of the following to occur: 1.) BP[X] assigns an interest in its Niakuk oil and gas leases to a third party; 2.) the Niakuk Participating Area34 is expanded to include oil and gas leases owned by parties other than BP[X] and their leases are developed from Heald Point or 3.) BP[X] enters into a production facility sharing arrangement with one or more third parties.
Id.
Finally, on January 20,1994, the lease was amended to increase the annual rent to $80,640 (reflecting both the increase to forty acres
At the time they signed the amendments in January 1994, each of the Oenga heirs signed a counseling record prepared by ASNA. DA 33, 34. The counseling records stated as follows:
I understand that the lease signed by Andrew Oenga legally allows BP Exploration to develop and manage this Native allotment____ I understand that the original lease is still in effect except for those parts changed by the amendment signed in August by BIA and those parts changed by these amendments____ I understand that*604 this lease amendment increases the acres being leased to BP[X] from 20 acres to 40 acres.... I understand that by agreeing to end the negotiation now, it may not be possible for ASNA Limited to reopen negotiations on the lease____
I understand that BP[X] may enter into any arrangement with ARCO to develop this property. I understand that I will not receive any changes in payment because BP[X] has full legal right to develop the property and enter into any agreements with ARCO.... 7 understand that I will not receive any changes in payments except for a possible change every four years because raw land values may go up or because the [CPI] may go up ____ I understand and agree with the lease amendments and so I am signing the amendment of my own free will.
DA 33 (emphasis added).
4. The ARCO/Exxon Facility Sharing Agreement
Shortly after the 1994 amendments were executed, on January 27, 1994, BPX entered into a facility sharing agreement providing ARCO and Exxon with a drilling and manifold slot at the Heald Point drillsite “to test the prospectivity of their lease(s) at the western limit of the BPX Niakuk Field.” IE J (redacted “LETTER AGREEMENT— ARCO/Exxon Access to Niakuk Facilities and Integration of Niakuk Interests”). In return, if the tests resulted in commercial production, ARCO and Exxon agreed to pay BPX a thruput for access to the BPX facilities on the Oenga allotment. Id. Pursuant to this facility sharing agreement, “shared use of the leased premises by BPX, ARCO ... and Exxon ... continued until BPX became the sole operator of the Prudhoe Bay Unit Area [(‘PBUA)] in 2000.” IPFUF ¶ 13 (citing IE K (Aaska DNR decision approving BPX as sole operator of PBUA, June 27, 2000)).
It is undisputed that BPX did not give the plaintiffs notice of the facility sharing agreement at the time. Leroy Oenga asserts that “[t]he first I or any member of the family learned of this LETTER AGREEMENT was in 2005 after our attorney met with BP[X].” PLA 1 ¶ 8. The government and intervernors assert that no such notice was required under the terms of the 1994 lease amendments which expressly excluded facility sharing agreements from the notice requirement for subleases. DIMFD ¶ 5.e; IP-FUF ¶ 30.
5. The 1995 Amendments
After signing the 1994 amendments, the Oenga heirs continued to explore their options for increasing the payments under the lease. On December 20, 1994, BPX offered to purchase the allotment for $600,000 cash. DA 38 (Doc. 42-5 at 44). The family verbally accepted the offer, but the sale was not completed. DA 40, 42. In January 1995, the Oenga heirs entered negotiations with BP to obtain a lump sum payment of $240,000 and annual (as opposed to biennial) payments for the remaining value of the lease, in exchange for no direct communication by the lessees with BPX and no requests for further amendments of the lease by ASNA and the BIA, except as a result of a change in circumstances affecting the leasehold. DA 40. BPX rejected this proposal on February 2, 1995, though negotiations continued. Id.
On May 11, 1995, the lease was amended again. DA 41. The 1995 amendments changed the payments from biennial back to annual, required that payments be made to a bank where some of the heirs had taken out loans, modified the first possible cancellation date to coincide with the term of those loans (January 1, 2001), and “appoint[ed] the BIA, acting by and through ASNA, to be [the] sole contact with [BPX] for any and all matters arising out of this Lease Agreement or any amendment thereto.”
6. The 1997 Appraisal
Consistent with the terms of the 1994 amendments, reappraisals were done in 1997 (for purposes of the 1998 rental adjustment)
D. Production Via the Plaintiffs’ Allotment
1. Oil and Gas Lease Areas Involved
Beginning in February 1993, BPX applied to Alaska DNE to approve the formation of the Niakuk PA within the PBU, and DNE granted the application, thereby forming the Niakuk PA, on March 2, 1994.
On November 17, 1997, Alaska DNE approved the “interim application” by the Greater Niakuk Area (“GNA”) Owners— BPX, AECO, and Exxon—to (1) expand the PBU and the Niakuk PA and (2) form a new PA, the West Niakuk PA, within the PBU. IE M. Alaska DNE indicated that the areas would encompass lands overlying the Kuparuk Eiver Formation reservoirs
As noted above, Alaska DNR approved BPX’s application to become the sole unit operator for the entire PBUA on June 27, 2000.
2. Production by the Oil Companies
With regard to the original Niakuk PA, to date, BPX has used the premises leased from the plaintiffs to “facilitate the production of oil and gas from” nine sections of land pursuant to four Aaska DNR leases of which BPX is the lessee. IPFUF ¶ 14(a); IE L at 122. With regard to the expanded Niakuk PA, to date, BPX has used the premises leased from the plaintiffs to “facilitate the production of oil and gas from” twelve sections of land pursuant to the same four Aaska DNR leases.
From the execution of the facility sharing agreement in 1994 until BPX became the sole operator of the PBUA in June 2000, ARCO and Exxon used the premises leased from the plaintiffs to “facilitate the production of oil and gas from the lands included in the West Niakuk [PA]” via five sections of land pursuant to two Aaska DNR leases, and “from certain lands included in the Lisburne [PA]” via three sections of land pursuant to two Aaska DNR leases. IPFUF ¶¶ 16-17. In June 2000, when BPX became the sole operator within the PBUA, BPX took over the ARCO/Exxon leases in the West Niakuk and Lisburne PAs and began using the leased premises to facilitate the production of oil and gas from those lands in addition to those in the Niakuk PA, and this use continues to date. IPFUF ¶ 18. From 1995 through 2001, oil production through the plaintiffs’ allotment from the West Niakuk PA was 16,722,387 bbls, amounting to approximately 24% of the total oil production from the Heald Point facility during those years. PLA 2. In addition, from 1994 through 2001, oil production through the plaintiffs’ allotment from the Lisburne PA was 3,180,979 bbls, or approximately 5% of the total oil production from the Heald Point facility during those years. Id.
Thus, the total volume of oil produced through Heald Point between 1994 and 2001 was 67,800,452 bbls. Id. The plaintiffs’ undisputed estimate, based on the United States Department of Energy’s annualized price per barrel of oil, is that the oil produced through Heald Point during those years was worth roughly $1,139,363,899. Id.
E. The Plaintiffs’ Requests for Accountings and Demands
In 2003, the plaintiffs made an informal, oral request of the BIA’s realty contractor, the Inupiat Community of the Actic Slope (“ICAS”) (a successor contractor to ASNA which now possesses the ASNA files, Def.’s
On December 1, 2005, the plaintiffs demanded in a letter to the DOI, the BIA, and ICAS that the government give notice and take action regarding alleged breaches of the lease by BPX, including “Unauthorized and unreasonable use of the property by utilizing [it] to produce oil from the West Niakuk Lease.” PLA 1 at 21. On December 23, 2005, the plaintiffs demanded that the government give notice and take action to halt the alleged trespasses by the lessees of the West Niakuk Oil Lease—listed as BPX, ConoeoPhillips, Chevron, Exxon, Forest Oil, and Foreenergy Inc. Id. at 23.
Also in December 2005, the plaintiffs, the government, and BPX entered into a tolling agreement for the period between December 20, 2005 and June 30, 2006, inclusive. Second Am. Compl. ¶ 6. Under the terms of the tolling agreement, the plaintiffs’ claims dating back to December 20, 1999 were to be considered timely. On the final day of that period, June 30, 2006, the present suit was filed. On September 25, 2006, BPX, Chevron, ConocoPhillips, Exxon, and Forest Oil filed a motion to intervene as defendants, which was granted on December 22, 2006.
The plaintiffs maintain that it was not until 2007 during discovery in the present case that they learned of the production of Lisburne PA oil and gas through the facility on the plaintiffs’ allotment. Second Am. Compl. ¶ 64; PLA 1 at 26. Accordingly, on June 4, 2007, the plaintiffs demanded in a letter to the BIA that the government give notice and take action regarding the alleged breaches of lease and trespasses arising from the production of Lisburne PA oil and gas. PLA 1 at 26; PPFUF ¶ B.4.b.
F. Proceedings to Date
As noted above, the plaintiffs allege that the government has breached its fiduciary responsibility and trust obligation by failing to collect royalties (claim one) or, in the alternative, a fair annual rental (claim two) from BPX, or in the alternative, by failing to take action to halt the alleged breaches of lease by BPX and alleged trespasses by ARCO and Exxon as requested by the plaintiffs in 2005 with regard to the West Niakuk PA and 2007 with regard to the Lisburne PA (claim three).
On May 14, 2007, the government filed a motion to dismiss, or, in the alternative, for summary judgment, alleging that claims one and two should be dismissed for lack of jurisdiction under Rule 12(b)(1) of the Rules of the United States Court of Federal Claims (“RCFC”), because they are barred by the six-year statute of limitations set forth in 28 U.S.C. § 2501. The government further argued that claims one, two, and three should be dismissed under RCFC 12(b)(6) because they are not claims upon which relief may be granted, on the grounds that none of the claims are money-mandating. On June 25, 2007, the intervenors filed a motion for partial summary judgment with regard to claim three, arguing that all of the activities complained of were within the scope of the activities permitted by the lease, and therefore no breach of lease or trespass occurred.
On January 3, 2008, the plaintiffs filed their own motion for partial summary judgment, seeking a determination that claims one, two, and three were timely filed -within six years of accrual, and that money-mandating duties exist and were breached by the government for all three claims. Briefing on the motions was completed on March 10, 2008, and oral argument was heard on August 13, 2008.
A. Standard of Review
In passing on a motion to dismiss, whether for lack of subject matter jurisdiction under RCFC 12(b)(1) or for failure to state a claim upon which relief may be granted under RCFC 12(b)(6), “[f]actual allegations must be enough to raise a right to relief above the speculative level, on the assumption that all the allegations in the complaint are true (even if doubtful in fact).” Bell Atl. Corp. v. Twombly, 550 U.S. 544, 127 S.Ct. 1955, 1965, 167 L.Ed.2d 929 (2007) (internal citations omitted); Holley v. United States, 124 F.3d 1462, 1465 (Fed.Cir.1997). In considering a motion under RCFC 12(b)(6), “[t]he court must determine whether the claimant is entitled to offer evidence to support the claims, not whether the claimant will ultimately prevail.” Chapman Law Firm Co. v. Greenleaf Const. Co., 490 F.3d 934, 938 (Fed.Cir.2007) (internal quotation omitted).
Under RCFC 56(c), by contrast, summary judgment is appropriate “if the pleadings, depositions, answers to the interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.” RCFC 56(c); see also Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 249-50, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986). Summary judgment will not be granted if the “dispute about a material fact is ‘genuine,’ that is, if the evidence is such that a reasonable [trier of fact] could return a verdict for the nonmoving party.” Anderson, 477 U.S. at 248, 106 S.Ct. 2505. Contract interpretation is a question of law that is generally resolvable by summary judgment. Varilease Tech. Group, Inc. v. United States, 289 F.3d 795, 798 (Fed.Cir.2002). Where, however, the contract language is ambiguous, disputed issues of fact may arise as to the intent of the parties. Perry-McCall Constr., Inc. v. United States, 46 Fed.Cl. 664, 672 (2000).
The United States Court of Federal Claims is a court of limited jurisdiction, Jentoft v. United States, 450 F.3d 1342, 1349 (Fed.Cir.2006), and under the Tucker Act, 28 U.S.C. § 1491 (2000), it may “render judgment upon any claim against the United States founded either upon the Constitution, or any Act of Congress or any regulation of an executive department, or upon any express or implied contract with the United States, or for liquidated or unliquidated damages in cases not sounding in tort.” 28 U.S.C. § 1491(a)(1). However, under 28 U.S.C. § 2501, “[e]very claim of which the United States Court of Federal Claims has jurisdiction shall be barred unless the petition thereon is filed within six years after such claim first accrues.” “The six-year statute of limitations set forth in [28 U.S.C. § ] 2501 is a jurisdictional requirement for a suit in the Court of Federal Claims.” John R. Sand & Gravel Co. v. United States, 457 F.3d 1345, 1354 (Fed.Cir.2006), aff'd — U.S. -, 128 S.Ct. 750, 169 L.Ed.2d 591 (2008).
Moreover, the Tucker Act simply confers jurisdiction on this court; a plaintiff must also identify a separate money-mandating statute upon which to base a claim for damages. In re United States, 463 F.3d 1328, 1333 (Fed.Cir.2006) (“[A] Tucker Act plaintiff must assert a claim under a separate money-mandating constitutional provision, statute, or regulation, the violation of which supports a claim for damages against the United States.” (citing Todd v. United States, 386 F.3d 1091, 1094 (Fed.Cir.2004))). “[A] statute creates a right capable of grounding a claim within the waiver of sovereign immunity if, but only if, it can fairly be interpreted as mandating compensation by the Federal Government for the damage sustained.” United States v. White Mountain Apache Tribe, 537 U.S. 465, 472, 123 S.Ct. 1126, 155 L.Ed.2d 40 (2003) (internal quotation omitted).
B. The ITAS Does Not Apply to Plaintiffs’ Claims One and Two.
The plaintiffs have moved this court to find that their first claim, seeking compensation for the government’s failure to collect proper royalties on the oil and gas produced through the facility on Heald Point, and their second claim, in the alternative, seeking compensation for the government’s failure to collect “present fair annual rental” taking into ae
Claims by individual Indians or tribes for breach of trust are subject to the same six-year statute of limitations under 28 U.S.C. § 2501 that applies to other litigation against the United States under the Tucker Act. Hopland Band of Pomo Indians v. United States, 855 F.2d 1573, 1576 (Fed.Cir.1988) (“[Statutes of limitations are to be applied against the claims of Indian tribes in the same manner as against any other litigant seeking legal redress or relief from the government.” (citing Capoeman v. United States, 194 Ct.Cl. 664, 440 F.2d 1002, 1007-08 (1971) (applying the same rule to an individual Indian))). 28 U.S.C. § 2501 requires that claims be “filed within six years after such claim first accrues.” (emphasis added). According to the Federal Circuit, “[a] cause of action for breach of trust traditionally accrues when the trustee ‘repudiates’ the trust and the beneficiary has knowledge of that repudiation.” Shoshone I, 364 F.3d at 1348 (citing Hopland Band, 855 F.2d at 1573). However, as noted above, the ITAS provides:
[Notwithstanding any other provision of law, the statute of limitations shall not commence to run on any claim ... concerning losses to or mismanagement of trust funds, until the affected tribe or individual Indian has been furnished with an accounting of such funds from which the beneficiary can determine whether there has been a loss[.]
119 Stat. at 519. For “claims falling within [the] ambit” of the ITAS, therefore, the statute of limitations does not begin to run— meaning the claims do not accrue—until the plaintiffs receive a meaningful accounting.
As to what claims are within the ambit of the ITAS,
The Shoshone I court rejected the trial court’s “overly expansive” view that “ ‘mismanagement of trust funds’ plainly covers a breach of fiduciary duty in the management of money already received in the trust” whereas “ ‘losses to ... trust funds’ ... corresponded] to the Government’s mismanagement of trust assets and the breach of its trust duty to ‘make the trust property productive.’ ” Id. at 1348-49. Accordingly, the Federal Circuit rejected the trial court’s view that the ITAS could be extended to “claims that the Government did not receive the best possible price for the leases negotiated,” reasoning that, “[w]hile it is true that a failure to obtain a maximum benefit from a mineral asset is an example of an action that will result in a loss to the trust, the [ITAS’] language does not on its face apply to claims involving trust assets.” Id. at 1349-50 (emphasis in original).
However, the Federal Circuit also rejected the government’s “narrow reading” of the ITAS, at the opposite extreme. Id. at 1349. The government had argued that “the [ITAS] applies only to claims for the mismanagement or loss of tribal funds that were actually collected and deposited into the tribal trusts by the Government,” reasoning that the phrase “mismanagement of trust funds” connoted “active misconduct relating to the tribal funds,” while the phrase “losses to ... trust funds” connoted “ ‘purely passive behavior’ resulting in a decrease in the trust funds.” Id. at 1349. In other words, “[u]nder the Government’s theory of liability, the [ITAS] would not apply to losses that the Tribes alleged occurred because of the Government’s failure to collect rents or to collect rents in a timely manner or to timely deposit such rents into the tribal trust accounts.” Id. The Federal Circuit found that such a “narrow reading” would render the term “losses to” redundant, because “mismanagement of trust funds after their collection necessarily results in a loss to such funds.” Id. (emphasis added).
Instead, the Shoshone I court found that, “[i]n the context of the [ITAS], ‘losses to ... trust funds’ may be understood to cover losses resulting from the Government’s failure to timely collect amounts due and owing to the Tribes under its ... contracts.” Id. at 1350. Importantly, the Shoshone I court went on to explain what was meant by “failure to collect amounts due and owing ... under its ... contracts,” concluding: “We therefore interpret the phrase ‘losses to ... trust funds’ to mean losses resulting from the Government’s failure or delay in (1) collecting payments under the ... contracts, (2) depositing the collected monies into the Tribes’ interest-bearing trust accounts, or (3) assessing penalties for late payment.”
Here, the plaintiffs argue that the determination of the amount required as a matter of law to be collected under the lease
The court is not persuaded by the plaintiffs’ arguments. In light of the guidance from the Federal Circuit in Shoshone I, laid out above, the plaintiffs’ reliance on Shoshone I for the assertion that the ITAS applies to their royalty and rent claims as “failure[s] to collect amounts due and owing” is misplaced. Id. As an initial matter, the repeated references in Shoshone I to amounts due and owing “under [the] contracts,” see, e.g., id. at 1342, 1350, 1351, 1355, suggest that, according to the Federal Circuit, the ITAS extends only to cases where money was lost to the trust fund by virtue of the government’s failure to collect the amount stipulated in a given contract or lease, as opposed to its failure to include the legally-required terms in the contract or lease to begin with. This reading is particularly prohibitive of the plaintiffs’ claim one for royalties, which were not provided for in any version of the lease or its amendments, before or after the change in use to oil and gas production.
However, the plaintiffs have argued that the “under [the] contracts” language in Shoshone I nonetheless allows for claims alleging violations of the statutes and regulations governing collection under leases such as the one in this case, insisting that the ITAS contemplates such claims. Accordingly, a deeper investigation must be made into the meaning of the phrase “collecting] amounts due and owing ... under [the] contracts” to address this subtler argument by the plaintiffs. Where, as here, the plaintiffs are not alleging that trust funds were mismanaged after collection, the Federal Circuit has indicated, as set forth above, that the ITAS is limited to claims of failure or delay in activities such as “(1) collecting payments under the ... contracts, (2) depositing the collected monies into the Tribes’ interest-bearing trust accounts, or (3) assessing penalties for late payment.” Shoshone I, 364 F.3d at 1350-51. The plaintiffs here have not alleged failure or delay in depositing collected monies into their accounts or in assessing penalties for late payments. However, those two examples are instructive in deciphering what is meant by the first, “collecting payments under the ... contracts” example. Failure and delay in “depositing” and “assessing penalties” on payments do not suggest claims relating to breach of a substantive trust obligation; rather, those examples suggest claims relating to errors in the transmission and calculation of funds. Likewise, as a series, (1) collecting payments, (2) depositing the monies, and (3) assessing late penalties connote errors in acquiring, moving, and measuring amounts of money, prior to those amounts becoming part of the pool of money in the trust fund, not errors in determining what is required as a matter of substantive Indian leasing law—errors of the latter type pertain instead to the management of the asset, the leased allotment.
As part of its duties, a trustee must keep clear and accurate accounts, showing what he has received, what he has expended, what gains have accrued, and what losses have resulted. An accounting alone will not reveal the mismanagement of tribal assets.... In contrast, the comparison of pertinent ... contracts with the results of an accounting will reveal what income was required to be received by the Government but was either not received or was received late.
Shoshone I, 364 F.3d at 1351 (emphasis added) (internal citations omitted). Thus, as emphasized previously, the Federal Circuit has signaled that, for trust fund issues, the contract itself is the relevant source of information regarding what was required of the government. Moreover, losses to trust funds, as opposed to trust assets, are losses that are detectable by comparing the contract to the accounting. In this case, a comparison of the lease with the results of an accounting would not reveal what income was (allegedly) required to be received, and therefore claims one and two raise trust asset issues, not trust fund issues covered by the ITAS.
A closer look at the plaintiffs’ specific claims further illustrates this contrast. For example, in the case of claim one for royalties, what is required of the government would be revealed not by comparing the lease to the accounting, which would yield equivalent results, but by comparing the lease or its amendments, which contained no provisions for such royalties, with the applicable statutes and regulations, to determine whether such royalties were required under the law. The plaintiffs have not set forth any reason why they could not have undertaken such a comparison of the lease documents with the applicable laws during the six years after those documents were executed with provisions for oil production but not for royalties, or, at the latest, after the property began to be used for such production.
Likewise, in the case of claim two for a “fair annual rental” accounting for the value of the lease for oil production, a comparison of the lease with the results of an accounting would not reveal whether a larger annual rental was required by law. The lease itself stated that rental adjustments would be “based upon ... the fair market undeveloped rental value,” “based on the ... use of the premises as raw, unimproved vacant land,” and “not ... based on the cost or value of improvements or developments made by the Lessee or any income the Lessee derive[d] from the leased premises.” DA 13 ¶¶ 5, 9. The appraised market values reflected in the “accountings” did just that. Thus, only a comparison of the lease with the applicable laws would reveal whether a “fair annual rental” taking into account the value of the land for oil production was required. Again, the plaintiffs have not set forth any reason why such a comparison of the lease and the applicable laws could not have been made within the six years after the use of the land changed with no corresponding change in the lease terms.
C. The Plaintiffs’ Claims One and Two Are Barred by 28 U.S.C. § 2501.
Having determined, as discussed above, that the ITAS does not apply to delay the accrual of the plaintiffs’ claim one for failure to collect royalties and claim two for failure to collect “present fair annual rental,” the court now turns to the timeliness of these claims under 28 U.S.C. § 2501 based on traditional rules of accrual.
The government responds that even the 2000 and 2001 claims are time-barred because they accrued when the plaintiffs were chargeable with knowledge of what payments they would receive and how they would be calculated. Specifically, the government contends that claim one accrued in 1989, when the lease was executed without any royalty provision. In the alternative, the government contends that, at the latest, claim one accrued in 1993, when the first rental adjustment occurred, since the method of determining the compensation should have been clear to the Oenga heirs at that point, or in 1994, when the lessee began to use the property for oil and gas production but still no royalties were received. By that time, the government argues, the plaintiffs had enough information to bring their claim against the government for the failure to collect royalties. Similarly, the government argues that the alleged failures to collect payments based on a “fair annual rental” in claim two accrued in 1993 and 1997, when the appraisals and rental adjustments occurred, setting the rent for the subsequent periods, with no changes in payment allowed under the lease until the next adjustment. The government claims that, while the plaintiffs may not all have had copies of the appraisals, the plaintiffs had contemporaneous knowledge of the conclusions therein, and they participated in extensive lease negotiations during that time, giving them sufficient knowledge of the return they were receiving to bring claim two within six years of the allegedly improper rental adjustments.
As noted above, “[a] cause of action for breach of trust traditionally accrues when the trustee ‘repudiates’ the trust and the beneficiary has knowledge of that repudiation.” Shoshone I, 364 F.3d at 1348. Thus, the accrual standard for breach of trust has two components: (1) when was the trust repudiated, and (2) when did the beneficiary “learn[ ] that the trustee ... failed to fulfill his responsibilities.” Id. As to the first component, “[a] trustee may repudiate the trust by express words or by taking actions inconsistent with his responsibilities as trustee.” Id. In this case, the plaintiffs allege that the government’s repudiation occurred each year, including 2000 and 2001, at the time of the annual collection of the rent by the government, while the government contends the alleged repudiation occurred, at the latest, at the time the government calculated the rental adjustments to be collected—no later than 1997.
The court agrees with the government that even the portions of the plaintiffs’ claims one and two pertaining to 2000 and 2001 are time-barred under 28 U.S.C. § 2501. The actions of the government that the plaintiffs allege in claims one and two were inconsistent with its responsibilities as trustee were set in motion by the execution of the lease, approved by the BIA, with no provision for royalties (despite listing oil production as an allowable use of the site) and provisions for annual rental rates that were not to be “based on the cost or value of the improvements or developments made by [BPX] or any income [BPX] derive[d] from the leased premises.” See DA 13 ¶ 9. The alleged failures to fulfill the responsibilities to collect royalties and “fair annual rental” were then cemented by the perpetuation of those lease terms in each subsequent amendment of the lease, and by each of the government’s rental adjustments according to those terms, all of which failed to add a royalty provision or change the way the annual rent was calculated even after the site began to be used for oil production in 1994.
Nor can the plaintiffs’ argument that the government had a duty to correct its course every year that it collected payments be characterized as a “continuing duty” claim. In continuing duty cases, “any ongoing breach of the continuing duty [creates] a series of individual actionable wrongs.” Mitchell v. United States, 10 Cl.Ct. 787, 788-89 (Cl.Ct.1986). Where such a duty exists, those individual wrongdoings “which arose within the six-year limitations period may be sued upon.” Id. This approach has been applied in certain pay cases, on the grounds that each failure to pay the proper amount gave rise to a new claim. See, e.g., Friedman v. United States, 159 Ct.Cl. 1, 310 F.2d 381, 384-85 (1962).
The Federal Circuit has held that, “[i]n order for the continuing claim doctrine to apply, the plaintiffs claim must be inherently susceptible to being broken down into a series of independent and distinct events or wrongs, each having its own associated damages.” Brown Park Estates-Fairfield Dev. Co. v. United States, 127 F.3d 1449, 1458 (Fed.Cir.1997). In Brown Park, the plaintiffs alleged that the Department of Housing and Urban Development (“HUD”) had failed to properly set the maximum rent for low-income housing based on the fair market value of the rental property for the local area, because required rental adjustments were not made during a period outside the six year statute of limitations, and “on account of HUD’s breaches outside the period of the statute of limitations, HUD started from the wrong base when making rent adjustments during the six years prior to the filing of suit.” Id. at 1457-58. “Thus, the alleged improper base for these latter years relates directly to, and is completely dependent on, whether HUD failed to make rent adjustments in earlier years____” Id. at 1458.
In response to the government’s statute of limitations defense, the plaintiffs in Brown Park argued that theirs was a continuing claim. Id. at 1454. However, the Federal Circuit held that the claims accrued at the time of the earlier failure to make proper rent adjustments, at which time the statute of limitations began to run. Id. at 1455.
Here, the plaintiffs’ claims one and two are barred because the lease amendments in 1994 and 1995 and the rental adjustments in 1993 and 1997 were each distinct events that allegedly caused continuing ill effects to the plaintiffs in the intervening years. The lease amendments in 1994 and 1995 set off a “series of deleterious effects” allegedly suffered by the plaintiffs, but once each amendment was in place, the payments in later years did not give rise to independent damages—the damages were directly tied to the terms of the earlier lease amendment. See Boling, 220 F.3d at 1373. Likewise, the harm incurred in the years between rental adjustments (in 1998, 1999, 2000, and 2001, for example), was directly tied to the preceding adjustment in which the allegedly incorrect rates were set; the rent collections in each of those intervening years did not have “its own associated damages.” See Brown Park, 127 F.3d at 1458. Thus, when the BIA allegedly failed to collect the proper royalties or rent in 2000 and 2001, it was adhering to the terms to which it had bound itself in the formation of the lease, the subsequent amendments, and the rental adjustments under the lease, and it was not committing any new, independent wrongs.
D. Production from the Lisburne PA Was Outside the Scope of the Lease, and the Plaintiffs Have Established a Money-Mandating Claim of Breach of Trust for the Activities There; However, Disputed Issues of Material Fact Preclude Summary Judgment as to Whether Production from the West Niakuk PA Was Within the Scope of the Lease.
In their third claim, the plaintiffs allege that the government breached its fiduciary obligation and trust responsibility by failing to take appropriate actions against the alleged breaches of the lease and trespasses caused by the production of oil and gas from locations other than the Niakuk area through the plaintiffs’ allotment—specifically the Lisburne and West Niakuk PAs.
Under this reading of the lease, the plaintiffs argue that BPX breached the lease when it allowed the production of oil and gas from the Lisburne and West Niakuk PAs through its facilities on the plaintiffs’ allotment, first by way of the facility sharing agreement with ARCO and Exxon, and later by producing the oil and gas from those areas itself. In addition, the plaintiffs argue that ARCO and Exxon trespassed on the plaintiffs’ allotment when they used BPX’s facilities to produce oil and gas from Lisburne and West Niakuk.
In response, the defendant and intervenors argue that the terms of the lease were sufficiently broad to include the development and production of oil and gas without regard to where such oil and gas was located, as the lease did not place geographical or geological restrictions on the use of the leased premises. They point to the language of ¶ 10 of the lease, which states, as noted above, that “[t]he Lessee may use the leased premises for any and all oil field exploration, development, construction, facilities, production and support purposes and for any other uses and purposes reasonably or conveniently related thereto.” DA 13 ¶ 10. The intervenors claim that, notwithstanding the references to the “Niakuk Project” in the lease, no effort was made to define the geographic boundaries of the oil exploration and production because at the time the lease was entered into, the location of the oil and gas was not yet completely understood, and that in fact, the “Niakuk PA” as such was not formed until March 2, 1994, more than five years after the lease was executed.
Thus, the central question in claim three is one of lease interpretation, particularly interpreting the meaning of the “Niakuk Project.” It is well-established that “[ejontract interpretation begins with the language of the written agreement.” NVT Techs., Inc. v. United States, 370 F.3d 1153, 1159 (Fed.Cir.2004) (citing Foley Co. v. United States, 11 F.3d 1032, 1034 (Fed.Cir.1993)). “When interpreting the contract, the document must be considered as a whole and interpreted so as to harmonize and give reasonable meaning to all of its parts.” Id. (citing McAbee Constr., Inc. v. United States, 97 F.3d 1431, 1434-35 (Fed.Cir.1996)). Meaning should be given to all parts of the contract to avoid “leav[ing] a portion of the contract useless, inexplicable, void, or superfluous.” Id. (citing Gould, Inc. v. United States, 935 F.2d 1271, 1274 (Fed.Cir.1991)). The court must determine the correct interpretation of the lease provisions “consistent with the parties’ intent at the time of [lease] execution.” Cities of Burbank, Glendale, and Pasadena v. Bodman, 464 F.3d 1280, 1284 (Fed.Cir.2006) (citing Winstar Corp. v. United States, 64 F.3d 1531, 1540 (Fed.Cir.1995)). In addition, when interpreting a contract, “the language of [the] contract must be given that meaning that would be derived from the contract by a reasonably intelligent person acquainted with the contemporaneous circumstances.” TegParadigm Environmental, Inc. v. United States, 465 F.3d 1329, 1338 (Fed.Cir.2006) (internal quotation omitted).
1. The Lease Did Not Encompass the Lisburne PA.
The court agrees with the plaintiffs that, tested by the above standards of contract interpretation, the scope of the lease, while broad, did not encompass oil and gas development and production from the Lisbume PA, which had been formed in December 1986, more than two years before the signing of the January 1989 lease. Though the term “Niakuk Project” is not defined in either the lease or the later amendments, the repeated references to it may not be read out of the lease. See NVT Techs., 370 F.3d at 1159 (A contract interpretation should not “leave[] a portion of the contract useless, inexplicable, void, or superfluous.”). In this
Given the fact that the Lisburne PA was a defined area prior to the execution of the lease, the lack of any reference to that area in the lease (despite the repeated references to Niakuk) indicates that the lease was not intended to encompass activities in the Lisburne PA.
2. Disputed Issues of Fact Preclude Summary Judgment as to the Activities in the West Niakuk PA.
In contrast to the Lisburne PA, the court finds that disputed issues of fact re-
3. A Money-Mandating Duty to Take Action Against the Lease Violations Exists, and the Government Breached That Duty with Regard to the Lisburne PA.
Having determined that the oil and gas development and production from the
The plaintiffs argue that, under 25 U.S.C. § 415(a) and 25 C.F.R. § 162, the government has specific duties to send notice and remedy breaches of lease and trespasses arising in relation to commercial leases on Indian allotments such as the one at issue in this case. The plaintiffs point to Brown v. United States, 86 F.3d 1554, 1563 (Fed.Cir.1996), in which the Federal Circuit agreed with an Indian landowner that “by virtue of the control they place in the hands of the Secretary [of Interior], [25 U.S.C. § ] 415(a) and the implementing regulations of [25 C.F.R. § ] 162 impose upon the government a fiduciary duty in the commercial leasing context.” (quoting United States v. Mitchell, 463 U.S. 206, 226, 103 S.Ct. 2961, 77 L.Ed.2d 580 (1983) (“Given the existence of a trust relationship, it naturally follows that the Government should be liable in damages for the breach of its fiduciary duties.”)). In Brown, the Federal Circuit agreed with the Indian landowner that “it is the assumption of ‘control or supervision’ over tribal money or property by the government that gives rise to the imposition of trust standards, and ‘control or supervision’ perfectly describes the Secretary’s role with respect to commercial leasing of allotted lands.” Id. (quoting Mitchell, 463 U.S. at 225, 103 S.Ct. 2961) (additional internal quotation omitted). The Federal Circuit cautioned, however, that “where no specific statutory requirement or regulation is alleged to have been breached by the Secretary, the money claim against the government must fail.” Id. In this case, the specific regulatory requirements alleged to have been breached by the BIA include 25 C.F.R. §§ 162.617-162.623.
The government concedes that, if the circumstances complained of by the plaintiffs are found to fit within the scope of 25 C.F.R. § 162, a money-mandating duty exists. Tr. of Oral Arg. 86:11-25. However, the government counters that the plaintiffs’ circumstances do not fit within that scope. Id. Specifically, the government argues that “plaintiffs conveniently ignore the fact that [25 C.F.R. § ] 162.618 only requires the BIA to send notice of breach of a lease only after the BIA has determined that a breach oc
The court finds that the clear guidance of Brown dictates that where, as here, the plaintiffs have alleged specific breaches of the regulations under 25 C.F.R. § 162, a trust responsibility exists and the claim of breach of that trust is money-mandating. Brown, 86 F.3d at 1563. As an initial matter, the plaintiffs have correctly noted that the government’s strained reading of the duties contained in 25 C.F.R. §§ 162.617-162.623 would mean that “simply by failing to acknowledge that a breach or trespass occurred,” the government could avoid triggering its responsibilities under the regulatory scheme. Pis.’ Reply at 22. The government’s reading of the regulatory requirements does not comport with the plain language of the regulations. Specifically, under 25 C.F.R. § 162.617, the regulations state that “[i]f an Indian landowner notifies [BIA] that a specific lease violation has occurred, [BIA] will initiate the appropriate investigation within five business days of that notification.” Then, under 25 C.F.R. § 162.618, “[i]f [BIA] determine^] that a lease has been violated, [BIA] will send the tenant ... a notice of violation within five business days.”
Here, the plaintiffs sent letters in 2005 and 2007 notifying the BIA that the lease was being violated as a result of the unauthorized use of the property to produce oil from the West Niakuk and Lisburne PAs. PLA 1 at 21, 26. The government does not assert that the “appropriate investigation” required under 25 C.F.R. § 162.617 was undertaken by the BIA upon receiving this notice of specific lease violations by the Indian landowners. Instead, the government argues that it is immune from liability because it incorrectly determined that the lease allowed oil and gas
III. CONCLUSION
In light of the foregoing, the court GRANTS the government’s motion to dismiss plaintiffs’ claims one and two for lack of subject matter jurisdiction because they were not filed within six years of accrual as set forth in 28 U.S.C. § 2501. Accordingly, the plaintiffs’ motion for partial summary judgment with regard to the timeliness of claims one and two is DENIED. In addition, the court GRANTS-IN-PART the plaintiffs’ motion for partial summary judgment with regard to the Lisburne PA portion of claim three, and the case shall proceed to trial regarding the damages arising from the Lisburne area development and production. However, the court DENIES-IN-PART the plaintiffs’ motion for partial summary judgment with regard to the West Niakuk PA portion of claim three, because disputed issues of material fact preclude a finding with regard to the scope of the lease; the case shall proceed to a trial regarding liability and, if appropriate, damages with regard to the West Niakuk area claim. Accordingly, the defendant’s and intervenors’ motions to dismiss and for partial summary judgment on claim three are DENIED.
The parties shall submit a joint status report on or before Friday, October 17, 2008, proposing a schedule for the next steps in the litigation.
IT IS SO ORDERED.
. The plaintiffs are the heirs of the original lessor, Andrew Oenga, and include his son Wallace Oenga, his daughter Georgene Shugluk, his grandsons Leroy Oenga, Sr., Michael Deha, Tony Delia, and Joseph Delia, his granddaughter Jennie Miller, and his great-granddaughter Trinity Delia. Second Am. Compl. ¶ 7.
. The other defendant-intervenors, ConocoPhillips Alaska, Inc. ("ConocoPhillips”) (formerly ARCO Alaska, Inc. ("ARCO”) and PHILLIPS Alaska, Inc.), Exxon Mobil Alaska, Inc. ("Exxon”), Chevron U.S.A., Inc. ("Chevron”), and Forest Oil Corporation ("Forest Oil"), are "Working Interest Owner” oil companies which "reimburse BPX for costs incurred by BPX as Unit Operator” for certain oil and gas leases, including the ones at issue in this case, in exchange for which "BPX delivers to each Working Interest Owner its proportionate share of all oil and gas produced from [the] leases.” Mot. to Intervene at 4; Intervenors’ Proposed Findings of Uncontroverted Fact ("IPFUF") ¶ 12.
. At the time the lease was entered into, BPX was called Standard Alaska Production Company. Standard Alaska changed its name to BPX effective January 31, 1989. Intervenors’ Mot. at 7. To avoid confusion, this opinion will refer to the company as BPX throughout.
. In addition, as discussed infra, in January 1994, ARCO and Exxon entered into a facility sharing agreement with BPX, under which BPX provided ARCO and Exxon with a drilling slot and access to the BPX facilities on the plaintiffs’ allotment in exchange for a thruput (an amount paid per barrel produced). Sealed Decl. of Edward Morse ¶ 7, Attach.; see also Intervenors’ Ex. ("IE”) J.
. The plaintiffs list 25 U.S.C. §§ 396, 396c-396e, 396g (1955), 30 U.S.C. §§ 1701-57 (1996), 25 C.F.R. § 212 (1987, 1996), 30 C.F.R. § 206 (1993), and 43 C.F.R. § 3160 (1993) as giving rise to a money-mandating duty for the government to collect such royalties. Pls.’ Mot. at 23-24.
. As part of their third claim, the plaintiffs originally argued that the government also breached its duty to disclose to the plaintiffs its knowledge of ARCO's interest in leasing the allotment to develop its offshore state oil leases. However, this "second part” of claim three has since been withdrawn by the plaintiffs in light of contradictory evidence submitted by the government. Tr. of Oral Arg. at 74:4-24. Accordingly, the court will not address the "duly to disclose” portion of claim three in this opinion.
. 28 U.S.C. § 2501 provides, in relevant part: "Every claim of which the United States Court of Federal Claims has jurisdiction shall be barred unless the petition thereon is filed within six years after such claim first accrues.”
. The ITAS provides:
[Njotwithstanding any other provision of law, the statute of limitations shall not commence to run on any claim ... concerning losses to or mismanagement of trust funds, until the affected tribe or individual Indian has been furnished with an accounting of such funds from which the beneficiary can determine whether there has been a loss[.j
119 Stat. at 519.
. Likewise, the intervenors argue that "since the undisputed facts establish that the actions of Intervenors on the leased premises have been at all times within scope of the grant made by the lease, claim three fails as a matter of law.” Intervenors' Mot. at 7.
. The government filed a "Statement of Genuine Issues of Material Fact in Dispute” ("DIMFD”) in response to the plaintiffs' Proposed Findings of Uncontroverted Facts ("PPFUF”).
. In addition, the facts set forth infra are consistent with the "Stipulation of Lease History” entered into by the Oenga heirs, BPX, and the BIA in May 1995. Def.’s Attach. ("DA”) 42.
. Heald Point is located on Alaska's North Slope, on the northeast edge of Prudhoe Bay. See DA 19. Mr. Oenga’s allotment covers the entire end of the Point, which is a long, narrow finger of land bounded by water on three sides. See DA 13 Ex. A at 1.
. Pursuant to 43 U.S.C. §§ 270-1 to 270-3 (1970), repealed with a savings provision by 43 U.S.C. § 1617(a) (2000), Mr. Oenga was eligible, due to his status as an Alaska Native, to receive title to a plot of land from the United States government for use as a homestead by him and his heirs in perpetuity. DA 2, 3.
. Mr. Oenga also secured a 120-acre "Parcel A,” not at issue here, as part of Allotment F-14632. See DA 1.
. The defendant contends that, because of this clause, the Oenga heirs are Indian surface owners only under the definitions set forth in 25 C.F.R. § 212.3 (2008) and are therefore not entitled to a royalty payment. Because the court finds, as discussed infra, that the plaintiffs’ claim for a royalty is time-barred, the court does not reach the merits of the defendant’s argument regarding the applicability of this regulation to the plaintiffs' lease.
. The document quoted by both the plaintiffs and the government for the terms of the allotment is, in fact, Native Allotment Certificate (Patent) No. 50-2005-0580, dated September 27, 2005, which formally transferred "Lot 1” of Parcel B—an area “[c]ontaining 22.21 acres”—to Mr. Oenga's heirs. DA 2. As to the remaining 17.79 acres of Parcel B, "the allotment has not yet been conveyed because all of the lands in [the township in which the acres are situated] were
. According to the Alaska Department of Natural Resources ("DNR”), ”[a]n oil and gas ‘unit’ is comprised of a group of leases which cover all or part of one or more potential or known reservoirs and which are subject to a ‘unit agreement’ ... which is typically executed by those with an interest in the leases." IE L at 1.
. The intervenors submitted two sets of exhibits, both referenced alphabetically. The court denotes those attached to their corrected motion for partial summary judgment (Doc. 62) with a single letter (i.e., "B”) and those attached to their reply (Doc. 87) with a double letter (i.e., "BB”).
. According to Alaska DNR, a "participating area,” in turn,
is usually limited to that part of the unit area which has been shown to be productive of oil or gas in 'paying quantities.' ... [A] separate PA must generally be established for each delineated reservoir____The boundaries of PAs can be continually revised as more wells are drilled and more data are obtained.
IE L at 1.
. Mr. Oenga "spoke and read little or no English.” PPFUF ¶ A.2.a.
. The memos describing the September 26, 1988 meeting do not mention any discussion of royalties. DA 11; IE PP.
. The effective date stated in the lease is January 1, 1989. DA 13.
. In addition, the lease itself stated that it was "made and entered into ... in accordance with the provisions of existing law and regulations at [25 CFR 162 (1987)], which by reference are made a part hereof.” DA 13 (brackets in original).
. Some of the permits for the causeway to an offshore drilling pad had already been denied by October 1988, before the lease was entered into in January 1989. DA 12, 42, 46 ¶ 7.
. Such uses of the unleased areas were to be allowed "without cost to lessee [BPX],” and Mr. Oenga could not "require separate or additional permits” for such activities. DA 13 ¶ 10.
. The phrase "Niakuk Project” is not defined in the lease.
. In the first phase of the project, BPX “ha[d] the option to cancel this Lease Agreement at any time,” provided notice was given to both the BIA and Mr. Oenga. DA 13 ¶ 1. In the second phase of the lease, BPX also had the option to cancel the lease "for any reason,” but only at the end of each five year period. DA 13 ¶ 15.
. This method of “using whichever method gave the highest adjustment" was included by Ms. Dickinson as a way to obtain greater compensation for Mr. Oenga. DA 12.
. These maps were incorporated into the lease by a reference in the granting paragraph stating that “[t]he allotment and leased premises are shown on the attached Exhibit A.” DA 13.
. As noted supra, some of the permits for the causeway to an offshore drilling pad had been denied by October 1988, before the execution of the lease in January 1989. DA 12, 46 ¶ 7. The maps in Exhibit A of the lease, dated September 21, 1988, apparently predate that development.
. The Stipulation of Lease History indicates that eventually, "only the North Slope Borough approve[d] the causeway permits. The State of Alaska and the Corps of Engineers rejected] the permits.” DA 42.
. In a letter to Leroy Oenga, dated July 30, 1993, Ms. Stevens of ASNA indicated, “As you know, BP will be constructing a pad at the point.” DA 23.
During this time, the BIA transferred “day-today lease administration duties from the Fairbanks Agency of the [BIA] to [ASNA], which contracted to perform such administrative responsibilities____” Def.’s Mot. at 7-8; DA 24.
. This letter also mentions the "Niakuk Project” in relation to the 1989 lease, as follows: "A more precise description of the leased premises was not available at the time the lease was executed because the Niakuk Project was in the permitting process and a final location of the right-of-way had not been surveyed.” DA 31.
. As noted supra, the Niakuk PA was located within the PBU, which also encompassed the Lisbume PA. The creation and expansion of the various PAs relevant to this case are described in more detail, infra.
. This increase in the size of the leased premises was “deemed effective on July 1, 1993 for purposes of calculating rental payments.” DA 35.
. At the same time as the 1995 amendments were executed, the Oenga heirs, BPX, and the BIA executed the “Stipulation of Lease History” setting forth some of the facts and circumstances surrounding the lease and its amendments up to that point. DA 42.
. Claims stemming from the 2001 and 2005 reappraisals and rental adjustments are not before this court. Those claims are pending before the DOI Board of Indian Appeals.
. It is apparently disputed whether the rent payment for 1998 remained at $80,640 or increased to $88,997.34, the amount collected each year from 1999-2001 (a difference of $8,357.34). Compare PLA 2; Second Am. Compl. ¶ 29 with DIMFD ¶ 8.a (citing DA 44; Ans. ¶ 29). The total rent collected is therefore disputed and is either $670,191 by the plaintiffs’ calculation or $678,549.40 by the defendant’s calculation (a difference of $8,358.40). Id.
To the extent that the plaintiffs claim that they did not receive in 1998 the $8,357.34 increase computed in 1997, their claim is for mismanagement of trust funds and may therefore be timely under the ITAS. See Shoshone Indian Tribe of the Wind River Reservation v. United States ("Shoshone I"), 364 F.3d 1339, 1350 (Fed.Cir.2004). However, as noted supra, the record contains a letter to Leroy Oenga informing him of the increased payment amount in October 1997. DA 44. It is not clear when the plaintiffs allege they received a "proper accounting” of this disputed amount. Accordingly, the court defers ruling on the timeliness of this portion of the plaintiffs’ claim.
. According to Alaska DNR, ARCO had objected to BPX’s proposed plan, hoping to include in the original Niakuk PA the two ARCO/Exxon leases (34626 and 34629) of which portions were later included in the West Niakuk PA, but they were denied. IE L; cf. IE M.
. Alaska DNR had approved the formation of the Lisburne PA for the Lisburne Reservoir within the PBU on December 4, 1986. IE O.
. Alaska DNR indicated that "the Kuparuk River Formation reservoir is stratigraphically and structurally complex and contains multiple compartments,” and that
[t]he proposed PA boundaries do not conform with the known compartmentalization of the reservoir. For example, ... data indicate that the Kuparuk reservoir is in communication between the proposed W[est] N[iakuk] PA and the current N[iakuk] PA. The boundaries for the Wfest] Nfiakuk] PA and the expanded Nfiakuk] PA ... are based on geography and lessee interests rather than the known geology of the reservoir.
IE M (emphasis added).
. Alaska DNR also noted that “[t]he GNA Owners have negotiated agreements among themselves to share the existing production capacity of the Lisburne facilities, the Heald Point facilities, and the PBU infrastructure.” Id.
. Prior to that, BPX had been the unit operator for the Western Operating Area of the PBU and ARCO (under its new name, Phillips Alaska, Inc.) had been the unit operator for the Eastern Operating Area of the PBU. IE K.
. On December 21, 2007, the formation of the Combined Niakuk PA, encompassing much of both the former expanded Niakuk PA and the former West Niakuk PA, was approved by Alaska DNR. IE II; Intervenors’ Reply at 24.
. The production from the expanded Niakuk PA has "[a]lmost all ... come from the Niakuk accumulation in and under” the PA, though two of the wells there have produced “some oil from the deeper Raven accumulation.” IPFUF ¶ 15. The “Raven Participating Area” was established in December 2007 encompassing this Raven accumulation—the Raven PA is "situated wholly within the area of the Combined Niakuk Participating Area”—the Combined Niakuk PA, also established in December 2007, now encompasses both the former Niakuk PA and the former West Niakuk PA. IE II, JJ. Claims relating to the Raven and Combined Niakuk PAs are outside the scope of this litigation.
. Shoshone I discussed a 2003 version of the ITAS provision, called the “[DOI] and Related Agencies Appropriations Act,” Pub.L. No. 108-7 (2003), which contained the same language as the ITAS provision at issue in this case. Shoshone I, 364 F.3d at 1343.
. As noted supra, the government also contends that its responses in 2003 and 2006 to the plaintiffs’ requests for accountings were not "accountings” under the meaning of the ITAS, and that therefore they have no effect on the running of the statute of limitations under 28 U.S.C. § 2501. Because the court finds, as discussed infra, that the ITAS does not apply to the plaintiffs’ claims, the court does not reach the question of whether the government’s responses constituted “accountings.”
. As the Shoshone I court explained, “This is simple logic-how can a beneficiary be aware of any claims unless and until an accounting has been rendered?” 364 F.3d at 1347. Along those lines, the "meaningful accounting” standard has been found to require more than simple notice, in that the information in the accounting must be sufficient to raise suspicion of possible losses. Chippewa Cree Tribe of the Rocky Boy’s Reservation v. United States, 69 Fed.Cl. 639, 664 (2006). Accordingly, the ITAS comports with the "lesser duty to discover malfeasance" on the part of trust beneficiaries. Shoshone I, 364 F.3d at 1347 ("Beneficiaries of a trust are permitted to rely on the good faith and expertise of their trustees.”).
. The plaintiffs argue that the "notwithstanding any other provision of law" phrase in the ITAS means that an objective accrual standard— "when was the accounting received?"—has replaced the previous, subjective standard of "what did the Indians know and when did they know it?” It is not disputed that, if the ITAS applies, the accrual date is fixed as the date an accounting is received. However, the “notwithstanding any other provision of law” phrase adds nothing
. The plaintiffs' claims in Shoshone I pertained to sand and gravel contracts. Id. at 1341.
. The court noted that "[fliduciary breaches such as” those listed result in the type of "losses to trust funds that are separate and distinct from the mismanagement of trust funds once collected.” Id.
. To hold otherwise would open the ITAS to delaying the accrual of any and all money-man
. Indeed, this reading is also consistent with the legislative history of the ITAS. In the House Report accompanying the 1993 renewal of the appropriations bill in which the provision is located, the committee noted that it intended to "extend[] the Statute of Limitations with relation to Indian trust fund management, to protect the rights of tribes and individuals until the reconciliation and audit of their accounts has been completed." H.R.Rep. No. 103-158, at 57 (1993) (emphasis added). In other words, the ITAS was intended to provide an opportunity to reconcile the Indians' accounts, balancing the books by comparing what was owed under the arrangement entered into with what was received, as evidenced by the accounting.
By the same token, the numerous and fact-intensive Cobell cases which prompted the passage of the ITAS involved "mismanagement of Individual Indian Money (IIM) trust accounts." See, e.g., Cobell v. Babbitt, 30 F.Supp.2d 24, 27-28 (D.D.C.1998) (Under the IIM trust account system, "the United States acts as trustee of accounts that hold money on behalf of individual Indian beneficiaries.”). The Cobell claims, like the ITAS, were concerned with the management of the trust funds, rather than with whether the government complied with the applicable laws in
. As noted supra, the dispute over the correct payment of rent in 1998 does fit within the ambit of the ITAS, as the amount was owed to the plaintiffs under the lease. In fact, the alleged failure to collect the $8,357.34 calculated under the lease to be owed to the plaintiffs in 1998 is a perfect illustration of the kind of claim of "failure to timely collect amounts due and owing ... under [the] contracts” considered to be a claim involving trust funds under Shoshone I, 364 F.3d at 1350. For example, a comparison of the lease documents with an accounting would reveal the discrepancy over that amount. As such, as noted supra, the claim may be timely, depending on when the proper accounting (causing the statute of limitations to begin running on that claim under the ITAS) was received.
. The plaintiffs support their reading of Shoshone I by relying on the decisions of several members of this court who have interpreted the ITAS to include: plaintiffs who were owed royalties under other leases, Osage Tribe of Indians of Oklahoma v. United States, 68 Fed.Cl. 322 (2005), plaintiffs who had been awarded judgment funds by the Indian Claims Commission but were not paid, Chippewa Cree Tribe, 69 Fed.Cl. at 639, and plaintiffs who were owed royalties under existing leases, Shoshone Indian Tribe of the Wind River Reservation v. United States ("Shoshone II”), 71 Fed.Cl. 172 (2006). Those cases involved challenges to what was owed under the terms of a lease or judgment, rather than what should have been included in the lease or judgment in the first instance, and as such they are distinguishable from the plaintiffs’ claims one and two.
The plaintiffs also list Simmons v. United States, 71 Fed.Cl. 188, 193 (2006), a case in which the ITAS was found to be inapplicable to a damage claim for mismanagement of timber assets on a reservation allotment, without explaining why that case should be distinguished from their own. In fact, Simmons, in which the plaintiff demanded compensation for timber allegedly improperly harvested from his land, is strongly analogous to the present case, and the court in that case dismissed the claim on Shoshone I grounds. Simmons, 71 Fed.Cl. at 193.
. As noted supra, a tolling agreement between the plaintiffs, the defendant, and BPX provided that the statute of limitations would not run between December 20, 2005 and June 30, 2006. The complaint in this court was filed on June 30, 2006. Thus, the parties do not dispute that any claims accruing after December 20, 1999 (six years prior to December 20, 2005) may be considered timely under 28 U.S.C. § 2501. The court notes, however, that the Supreme Court’s recent holding in John R. Sand & Gravel Co. v. United States that "a court a court must raise on its own the timeliness of a lawsuit filed in the Court of Federal Claims, despite the Government’s waiver of the issue,”— U.S. -, 128 S.Ct. 750, 752, 169 L.Ed.2d 591 (2008) (emphasis added), calls the validity of such tolling agreements into question. Because the analyses of the timeliness of the plaintiffs’ claims are not affected by the six-month window of time subject to the tolling agreement, the court does not reach the question of the validity of the tolling agreement at this time.
. As noted supra, the plaintiffs’ claims stemming from the rental adjustment done in 2001 (and applied to the years 2002-2005) are pending before the DOI Board of Indian Appeals.
. In fact, the 1994 amendments specifically provided that "Lessors shall make no additional claims, requests or demands of Lessee for Lease rental payments, rental payment adjustments or rental payment advances except as set forth in [the Lease Rental Adjustment provision].” DA 35.
. The plaintiffs' emphasis on the government’s duties regarding "collection” of such rental is misplaced. With regard to claim two, the court
Accordingly, the court focuses on the government’s actions related to approval and granting of the lease and its amendments as the relevant duties for "repudiation” purposes. The court need not decide whether the rental adjustments should be included in these “lease approval and granting” duties, however, as the last such adjustment occurred in 1997 and any claim arising from it is therefore time-barred in any event.
. The plaintiffs assert that they were not given copies of the actual 1993 and 1997 appraisals in this case until they received the "accounting responses” in 2003 and 2007. See, e.g., PLA 1 ¶ 7. However, the plaintiffs have not set forth any evidence that documents pertaining to the lease, including the appraisals, were withheld or otherwise not available to them upon request. Cf., e.g., DA 46 (Ms. Dickinson’s declaration stating “If [the heirs] had asked, the copies [of the appraisals] would have been provided.”). Accordingly, the court finds that it is sufficient for purposes of knowledge of repudiation that they were made aware of the existence and contents of such documents at the time. See, e.g., DA 23 (July 30, 1993 letter to Leroy Oenga from ASNA informing him that the 1993 appraisal had occurred and that ”[a]s you know, BP[X] will be constructing a pad at the point.”); DA 33 (counseling records signed by each heir in January 1994, indicating that they understood that they would "not receive any changes in payment because BPIXi has the full right to develop the property and enter into any agreements with ARCO.”); DA 42 ("Stipulation of Lease History” signed by the parties to the May 1995 amendments, indicating the change to building a production pad on the allotment in 1993); DA 44 (October 8, 1997 letter to Leroy Oenga from Ms. Dickinson indicating that the 1997 appraisal had occurred and that the CPI adjustment would be used instead, as it was greater).
. This is consistent with the characterization of the claims for failure to collect proper rents and royalties as mismanagement of the trust assets, since such mismanagement could occur only as a single event at the setting of the rent, after which the BIA lacked the power under the terms of the lease to unilaterally alter the contract, in contrast to mismanagement of trust funds, which could occur as a series of individual accounting-type errors, each giving rise to new harm.
. Because claim two is entirely time-barred, the court does not reach the question of whether the plaintiffs have alleged a money-mandating duly in claim two.
. As noted supra, the government and the intervenors have not raised a statute of limitations defense to claim three. However, the plaintiffs have moved for summary judgment with regard to the timeliness of claim three, arguing that it accrued when the government failed to take action as requested via demand letters by the plaintiffs—in 2005 with regard to West Niakuk and the use of the allotment by ARCO and Exxon, and in 2007 with regard to Lisburne. Pis.’ Mot. at 17-18. Alternatively, the plaintiffs point to the dates when they learned of the production of oil from West Niakuk and Lisburne through the facility on their allotment—in 2003 for West Niakuk (via a requested accounting), and in 2007 with regard to Lisburne (via discovery in the present litigation)—as accrual dates. Id.
Though neither the government nor the intervenors has challenged the timeliness of claim three, the court has an independent duty to determine whether the claim falls within the six-year statute of limitations set forth in 28 U.S.C. § 2501. John R. Sand & Gravel, 128 S.Ct. at 752 ("[A] court must raise on its own the timeliness of a lawsuit filed [under 28 U.S.C. § 2501] in the Court of Federal Claims, despite the Government’s waiver of the issue.”).
As discussed supra, a breach of trust claim traditionally accrues "when the trustee 'repudiates’ the trust and the beneficiaiy has knowledge of that repudiation.” Shoshone I, 364 F.3d at 1348. In this case, it is undisputed that the plaintiffs did not have knowledge of the development and production from West Niakuk and Lisburne until 2003 and 2007, respectively. More
. For example, the plaintiffs quote the language of ¶ 1 of the lease, to the effect that:
[t]he first ten years of the lease shall constitute a period within which the Lessee shall attempt to obtain required permits for the Niakuk Project .... [Djuring the initial ten (10) year period, Lessee must notify the Lessor and the Superintendent [of the BIA] of the status of the permitting process and/or of the Niakuk Project ____Such notice is required within ninety (90) days of the date that the Niakuk Project is either fully permitted or the project is can-celled or delayed.... If Lessee serves written notice that it intends to procede [sic] with the Niakuk Project, then this lease will be deemed to have been taken for consecutive five (5) year periods....
DA 13 ¶ 1 (emphasis added). As a further example, the plaintiffs point to the two maps attached to the lease as Exhibit A, entitled "Niakuk Project Location Map” and “Niakuk Onshore Access Road and Pipelines.” Id. at Ex. A (emphasis added). As described in detail supra, these maps depict a causeway extending offshore to a "Proposed Niakuk Production Island Addition.” Id. (emphasis added).
. The plaintiffs also argue that the facility sharing agreement between BPX and ARCO and Exxon was an "assignment,” and that notice of and consent to the arrangement were therefore required, under both the 1994 amendments to the lease, which required notice to the Oenga heirs and ASNA "if the leased premises are subleased” but excluded "facility sharing agreements or other transactions which do not convey an interest in real property," DA 35 ¶ 13, and the regulations governing leases of allotted lands, particularly 25 C.F.R. § 162.610, which states that "a sublease, assignment, amendment or encumbrance of any lease or permit issued under this part may be made only with the approval of the Secretary and the written consent of all parties to such lease or permit,” except that, “[w]ith the consent of the Secretary, the lease may contain a provision authorizing the lessee to sublease the premises, in whole or in part, without further approval.” 25 C.F.R. § 162.610(a)-(b) (2001). The plaintiffs define "assignment” as "the transfer of rights or property." Black’s Law Dictionary (8th ed.2004); see also id. (defining "partial assignment” as "[t]he immediate transfer of part but not all of the assignor’s right.”).
The intervenors respond that, though an assignment would have required notice and consent under the lease and the regulations cited by the plaintiffs, the facility sharing agreement in this case is not an assignment. The intervenors define “assignment” as a transfer of possessory rights, under which the “entire interest” in leased premises is transferred with no reversionary interest, as opposed to a “sublease,” which involves transfer of all or a portion of the leased premises for "less than the balance of the term.” Intervenors’ Reply at 28 (citing Restatement (Second) of Property § 15.1 cmt. i (1977); see also Rest. (2d) of Prop. § 15.1 cmt. i (defining a “partial assignment” as transfer of an undivided share or specific portion of the leased property "for the balance of the term of the lease ” (emphasis added))).
The court agrees with the government that the facility sharing agreement in this case was not an assignment. The agreement allowed ARCO and Exxon to use a drilling and manifold slot at the Heald Point drillsite to test the prospectivity of their leases. IE J. It did not convey all or part of BPX’s interest in the leased premises for the balance of the lease term. In fact, the interest conveyed by the agreement was recouped by BPX before the end of the lease when, in 2000, BPX took over ARCO and Exxon's leases and BPX itself began producing the oil therefrom through Heald Point. The court notes that the definition of assignment in Black’s Law Dictionary, cited by plaintiffs, goes on to state that “assignment of lease ’’ means "[a]n assignment in which a lessee transfers the entire unexpired remainder of the lease term, as distinguished from a sublease transferring only a portion of the remaining term.” (emphasis added). This comports with the Restatement (Second) of Property definitions, cited by the intervenors, as noted supra.
. Likewise, the West Niakuk PA was not formed until November 17, 1997.
. Though the phrase "Niakuk Project” appears only in the lease term describing the first phase of the lease, BPX’s "written notice that it intends to procede [sic] with the Niakuk Project” is the mechanism which automatically triggered the onset of the second phase of the lease, and as such the references to the Niakuk Project must be considered to have bearing on the scope of both the first and the second phases. See DA 13 ¶ 1; see also Tr. of Oral Arg. 117:23-25 (Counsel for the intervenors indicated that "[i]f the time had passed ten years and BP[X] had not delivered the notice, the lease would have expired.”); NVT Techs., 370 F.3d at 1159 ("When interpreting the contract, the document must be considered as a whole and interpreted so as to harmonize and give reasonable meaning to all of its parts.”).
. This reading of the lease is consistent with BPX's July 29, 1993 letter giving notice to the BIA of its intent to proceed with the “Niakuk Development Project,” which stated that "[tjhe [1989] Lease provided authorization for BP[X] to construct production facilities to support development of, and production from, our Niakuk oil accumulation." DA 20 (emphasis added). This confirms that the Niakuk Project was understood to be tied to a particular oil accumulation, the boundaries of which may not have been completely known, but which certainly did not refer to the unmentioned Lisburne accumulation, already encompassed at that time by the Lisburne PA. Cf. Intervenors’ Mot. at 23 ("The Lisburne accumulation, the Niakuk accumulation, and the Raven accumulation all were known to exist pri- or to the execution of the Oenga Lease effective January 1, 1989 ____”); see also Teg-Paradigm, 465 F.3d at 1338 ("Although extrinsic evidence may not be used to interpret an unambiguous contract provision, we have looked to it to confirm that the parties intended for the term to have its plain and ordinary meaning.” (citing Coast Fed. Bank, FSB v. United States, 323 F.3d 1035, 1038 (Fed.Cir.2003))).
The plaintiffs maintain that the July 29, 1993 letter should be considered the first lease amendment, and that no notice of the amendment was given to the plaintiffs prior to the signing of the July 29, 1993 letter by the BIA on August 3, 1993. See, e.g., PPFUF ¶¶ A.5.b-c; PLA 1. The intervenors counter that the letter was not an amendment and merely provided notice to the BIA of (1) the shift to the second phase of the lease and (2) the exercise of BPX’s option to increase the size of the leased premises. See, e.g., Intervenors' Mot. at 20.
As described supra, BPX’s July 29, 1993 letter was characterized by its own terms as a "Lease Amendment” and was formally approved as such by the BIA. DA 20. However, the letter had two titles, "Notification of Niakuk Project Com
For purposes of claims one and two, the court need not decide whether the July 29, 1993 letter was a formal amendment, as those claims are time-barred in any event, as discussed supra. For purposes of the Lisburne area portion of claim three, the court need not decide whether the letter was an amendment, as the court finds that the lease did not contemplate development and production from the Lisburne area, and the reference in the July 29, 1993 letter to the "Niakuk oil accumulation" only serves to confirm that understanding, as discussed above. To the extent that the nature of the July 29, 1993 letter is relevant to the West Niakuk area portion of claim three, the court defers ruling on the question until the factual issues surrounding that claim have been further developed.
With regard to the plaintiffs’ charge that they did not receive proper notice of the changes mentioned in the July 29, 1993 letter, the court finds that such a claim is not timely. The record contains a letter from Ms. Stevens of ASNA to Leroy Oenga, dated July 30, 1993, describing BPX’s planned expansion to twenty acres and the corresponding increase in rental payment, and stating that ”[a]s you know, BP[X] will be constructing a pad at the point.” DA 23. In addition, the Oenga heirs each signed a counseling record in January 1994, stating, “I understand that the original lease is still in effect except for those parts changed by the amendment signed in August hy BIA and [the 1994] amendments.” DA 33 (emphasis added). Accordingly, any claim that notice of these changes was not properly given to the plaintiffs prior to the BIA’s August 3, 1993 approval accrued when they became aware of that approval, no later than the signing of the counseling records in January 1994, and well over six years before the plaintiffs brought their claims in this court. See 28 U.S.C. § 2501.
. The court notes that inclusion of activities in the Lisburne PA within the scope of the original lease would have increased the value of the leased premises to BPX and consequently the rent bargained for by the heirs. Similarly, if the plaintiffs had been apprised of the later addition of oil and gas development and production from the Lisburne PA, they would have been in a position to renegotiate the lease to increase the rent accordingly.
. See, e.g., TEG-Paradigm, 465 F.3d at 1338 (“When a provision in a contract is susceptible to more than one reasonable interpretation, it is ambiguous, and we may then resort to extrinsic evidence to resolve the ambiguity.” (internal citations omitted)).
. 25 C.F.R. § 162.617(b) (entitled "How will BIA determine whether the activities of a tenant under a lease are in compliance with the terms of the lease?”) states that "[i]f an Indian landowner notifies [BIA] that a specific lease violation has occurred, [BIA] will initiate an appropriate investigation within five business days of that notification.” 25 C.F.R. § 162.618 (entitled "What will BIA do in the event of a violation under a lease?”) states that "[i]f [BIA] determine[s] that a lease has been violated, [BIA] will send the tenant and its sureties a notice of violation within five business days of that determination,” upon receipt of which the tenant must either cure, dispute, or request additional time to cure the violation.
Under 25 C.F.R. § 162.619 (entitled "What will BIA do if a violation of a lease is not cured within the requisite time period?"), in turn, "[i]f the tenant does not cure a violation of a lease within the requisite time period, [BIA] will consult with the Indian landowners, as appropriate, and determine whether” the lease should be canceled, other remedies should be invoked, or the tenant should be granted additional time to cure the violation. If the BIA decides to cancel the lease, 25 C.F.R. § 162.619 also requires that notice be sent to the tenant, including "the amount of any unpaid rent, interest charges, or late payment penalties due under the lease,” and that the tenant be ordered to vacate the property within thirty days, barring an appeal of the cancellation decision.
25 C.F.R. § 162.620 specifies appeal bond procedures in the event of lease cancellation, while 25 C.F.R. § 162.621 specifies the effective date of cancellations. 25 C.F.R. § 162.622 provides that the BIA will take "appropriate emergency action,” including "judicial action," if "a tenant or any other party causes or threatens to cause immediate and significant harm to the leased premises during the term of a lease.” Finally, 25 C.F.R. § 162.623 (entitled "What will BIA do if a tenant holds over after the expiration or cancellation of a lease?”) provides that "[i]f a tenant remains in possession after the expiration or cancellation of a lease, [BIA] will treat the unauthorized use as a trespass,” and "[ujnless [BIA] ha[s] reason to believe that the tenant is engaged in negotiations with the Indian landowners to obtain a new lease, [BIA] will take action to recover possession on behalf of the Indian landowners, and pursue any additional remedies available under applicable law.”
. As set forth in n. 71, supra, this notice, in turn, triggers a duly to respond on the part of the tenant, either by curing the violation or by disputing it. 25 C.F.R. § 162.618. Moreover, if the tenant does not cure the violation, the BIA must, under 25 C.F.R. § 162.619, "consult with the Indian landowners, as appropriate,” to determine whether the lease should be canceled or other remedies should be invoked. Lease cancellation, in turn, carries additional responsibilities, including treating a tenant who holds over as a trespasser. 25 C.F.R. § 162.623; see also 25 C.F.R. § 162.108 (entitled “What are BIA's responsibilities in administering and enforcing leases?”) ("[BIA] will ensure that the tenants comply with the operating requirements in their leases, through appropriate inspections and enforcement actions as needed to protect the interests of the Indian landowners and respond to concerns expressed by them. [BIA] will take immediate action to recover possession from trespassers operating without a lease, and take other emergency action as needed to preserve the value of the land.”).
The government mischaracterizes the plaintiffs' claim as challenging the government’s failure to bring a lawsuit against a third party upon request, for which the government argues there is no trust duty and therefore no breach of trust, citing Creek Nation v. United States, 318 U.S. 629, 639, 63 S.Ct. 784, 87 L.Ed. 1046 (1943). As described above, however, there are numerous requirements in 25 C.F.R. § 162 that may be triggered by a lease violation, long before a lawsuit, if any, would be required to be filed. The plaintiffs assert that "[t]he breach occurred not by failing to sue, but because the United States assumed the ... sole obligation to communicate with the oil company” and failed to take the corrective actions mandated by the regulations. Tr. of Oral Arg. 126:16-25. Accordingly, Creek Nation is inapposite.
. The responsibilities set forth in 25 C.F.R. § 162 are bolstered where, as here, the government assumed sole responsibility for contacting BPX regarding "any and all matters arising out of this Lease Agreement,” as set forth in the 1995 lease amendments. DA 41.