delivered the opinion of the court:
Plaintiffs appeal from the circuit court’s award of summary judgment (735 ILCS 5/2—1005 (West 1992)) in favor of defendant City of Chicago (the City), based on the statute of repose contained in section 13—214(b) of the Code of Civil Procedure (735 ILCS 5/13—214(b) (West Supp. 1993)). We affirm.
On March 17, 1986, Donna Sclafani (Sclafani) and Hope D. Hughes (Hughes) were traveling southbound on North Lake Shore Drive (the Drive) in the City of Chicago when a private vehicle in the northbound lanes crossed the median and collided with their vehicle, severely injuring both of them. Sclafani’s injuries proved fatal. Plaintiffs’ complaint alleged that the City had been negligent in the design and maintenance of the Drive at the location of the accident by "[f]ail[ing] to provide an adequate median dividing northbound and southbound traffic.” According to plaintiffs, in 1966, the City, together with the Chicago Park District, the County of Cook, and the State of Illinois, entered into an agreement to redesign a section of the Drive (the redesign agreement), including the location where the accident occurred. Because City officials at that time recognized that differences in elevation of the opposing streams of traffic of parts of the redesigned section created a dangerous condition and were thus the cause of cross-over accidents, they recommended and approved the installation of a "Steel Plate Beam Guard Rail” to supplement the then existing "relatively narrow sloped median” of the roadway; nevertheless, the redesign project was completed without installing the guardrail.
Plaintiffs’ first contention on appeal is that the circuit court erred in granting the City summary judgment based upon the statute of repose since a genuine issue of material fact remained as to the completion date of the redesign project from which date the repose period would have begun to run.
Summary judgment motions (735 ILCS 5/2—1005 (West 1992)) permit the trial court to determine whether any genuine issue of material fact exists in the action, and if not, to provide an expedient means of resolution. (Purtill v. Hess (1986),
Here, in its motion for summary judgment, the City argued that the applicable statute of repose for cases predicated upon design defects (735 ILCS 5/13—214(b) (West Supp. 1993)), which provides a maximum period of 14 years after construction of an improvement within which to bring suit, barred plaintiffs’ claim. The circuit court denied the motion, stating that the City had failed to present sufficient evidence of the date of completion of the redesign project.
The City filed a timely motion to reconsider, attaching thereto a certified copy of an Illinois Department of Transportation (IDOT) document (the document) that "memorialize[d]” the completion date of the project as March 28, 1969, and consequently the date marking the commencement of the running of the statute of repose. Based on this new information, the court granted the City a partial summary judgment, holding that plaintiffs’ counts based on negligent design were time-barred as a matter of law under the statute of repose, but that those regarding negligent maintenance were not. Thereafter, plaintiffs voluntarily dismissed the maintenance counts of their complaint, thus making the summary judgment order final and appeal-able.
Plaintiffs contend that the document the City attached to its motion for reconsideration was insufficient to support summary judgment since that document contains a "job” number (C—90—712—67) different from the one on the cover sheet of the City’s redesign plans for the Drive (P—90—024—67); therefore, plaintiffs argue, the document could not possibly refer to the redesign project at issue here, but must necessarily refer to some other project. They also maintain that the document does not memorialize an acceptance date for any project.
However, although "Job. No C—90—712—67” appears on the document and "JOB NO P—90—024—67” appears on the cover sheet of the redesign plans, record number "C—90—712—67” appears on the cover sheet of the redesign plans as well. Moreover, the City persuades that record numbers C—90—712—67 and P—90—024—67 both refer to the redesign project. As attested to by Thomas R. Bright (Bright), an employee of IDOT, Division of Highways, Bureau of Construction, for record keeping purposes, "C” represents a construction number and "P” represents a planning number; and since construction and planning are separate activities within IDOT, records are kept under separate construction and planning numbers although both refer to the same project, as is evidenced by the fact, as mentioned above, that both record numbers appear on the cover sheet of the City’s redesign plans.
We also note that nothing in the record casts the slightest doubt on IDOT’s certification that the document truly memorializes that the State accepted the redesign project on March 28, 1969, thus making that the date upon which the redesign project was officially completed and from which the statute of repose began to run. In fact, the document certified provides an inspection date of June 19, 1968, and a final scheduled inspection date of March 24, 1969, as well as an acceptance date of March 28, 1969, all for "Job No. C—90—712—67.”
Consequently, we hold that no genuine issue of material fact exists as to whether the State accepted the redesign project on March 28, 1969, nearly 19 years before plaintiffs filed their complaint on March 14, 1988; the trial court was therefore correct in holding that plaintiffs’ counts as to negligent design were time-barred as a matter of law.
Plaintiffs next contend that the 14-year period of repose in section 13—214(b) was enlarged in this case by section 13—214(d), which states:
"Subsection (b) shall not prohibit any action against a defendant who has expressly warranted or promised the improvement to real property for a longer period from being brought within that period.” (735 ILCS 5/13—214(d) (West Supp. 1993).)
They assert that the language in the redesign agreement stating that the improvements along the Drive would (1) "be a lasting benefit to the people in the area as well as the motorist” and (2) comply with federally adopted standards amounted to an express warranty or promise by the City within the meaning of section 13—214(d).
Where, as is the case here, a defendant has produced sufficient evidence which would entitle it to judgment as a matter of law on a statute of repose defense, the plaintiff has the burden of proving that any exception to that law applies. (See Henderson v. Jones Brothers Construction Corp. (1992),
The courts’ role in interpreting a statute is to ascertain and give effect to legislative intent. (City of Decatur v. American Federation of State, County, & Municipal Employees Local 268 (1988),
A complete reading of the construction design management and supervision section of the Code of Civil Procedure’s provisions relating to limitations (735 ILCS 5/13—214 (West Supp. 1993)) reveals that section 13—214(d) was incontrovertibly drafted to prevent the impairment of contractual rights associated with express warranties and promises. Stelzer v. Matthews Roofing Co. (1987),
In the case at bar, plaintiffs offer no evidence which demonstrates that any contractual rights associated with an express warranty or promise contained within the redesign agreement were extended to Sclafani or Hughes, or for their direct benefit, i.e., plaintiffs fail to show that Sclafani and Hughes were either parties to or third-party beneficiaries of the redesign agreement. Rather, plaintiffs contend that they need not make such a showing since they are not suing under a contract theory, but under a negligence theory.
However, even though plaintiffs base their action on a negligence theory, in invoking the protection of section 13—214(d), they are essentially asserting that Sclafani and Hughes had contractual rights associated with an express warranty or promise under the redesign agreement entered into between the City, the State, the county, and the park district. But surely, plaintiffs must be aware of the legislature’s intent to limit the exception created by 13—214(d) to apply only to "actions on express warranties or promises” (emphasis added) (Stelzer,
As a general rule, only third parties who are direct beneficiaries have rights under a contract, and it is not enough that the third party will reap incidental benefits from the contract. (Ball Corp. v. Bohlin Building Corp. (1989),
With respect to construction contracts, this court has held that "[i]t is not enough that the parties to the contract know, expect or even intend that others will benefit from the construction of [a structure] in that they will be users of it. The contract must be undertaken for the plaintiff’s direct benefit and the contract itself must affirmatively make this intention clear.” (Waterford Condominium Association v. Dunbar Corp. (1982),
Additionally, "[i]n Illinois, the promisor’s intention must be evidenced by an express provision in the contract identifying the third-party beneficiary.” (Wheeling Trust & Savings Bank,
In the case sub judice, plaintiffs have the burden of proving that the City intended to confer a direct benefit upon Sclafani and Hughes (see Altevogt v. Brinkoetter (1981),
Although the preamble of the agreement declares that the redesign of the Drive would "be a lasting benefit to the people in the area as well as to the motorist,” such language evinces nothing more than that most contracts entered into by a governmental unit are made for the benefit of the public at large. (See Restatement (Second) of Contracts § 313, Explanatory notes, Comment a, at 472 (1981) ("Government contracts often benefit the public, but individual members of the public are treated as incidental beneficiaries unless a different intention is manifested”).) Also, the mere fact that the agreement states that the redesign of the Drive would comply with Federal standards does not manifest an intent to confer a direct benefit upon Sclafani and Hughes.
Furthermore, plaintiffs fail to convince that the City "expressly warranted or promised” the redesign of the Drive. For the same reasons stated above, that the City intended the redesigned portions of the Drive to "be a lasting benefit to the people in the area as well as to the motorist” does not amount to an express warranty or promise. In addition, the argument that the language in the agreement stating that the redesign of the Drive would comply with Federal standards amounted to an express warranty or promise can be rejected out of hand. Plaintiffs rely exclusively on their expert’s opinion that Federal standards required the redesigned portion of the Drive where the accident occurred to have had "a use expectancy of at least 25 years.” However, all that their expert clearly meant by that phrase was that it would have been economically sound for the City to install median guardrails where the accident occurred, since, according to the then applicable Federal standards, such guardrails would have had a "use expectancy of at least 25 years”; that is, according to the expert, the cost of installing the guardrails could have been depreciated over a number of years, and the City could not now claim otherwise as a budgetary "excuse” for not having installed them along the Drive. But this reasoning has no bearing whatsoever on whether or not the City "expressly warranted or promised” the redesign of the Drive pursuant to section 13— 14(d).
We conclude, therefore, that Sclafani and Hughes were not third-party beneficiaries to the redesign agreement, and even if they were, plaintiffs have failed to show that the City "expressly warranted or promised” the redesign of the Drive; consequently, plaintiffs may not avail themselves of the benefits afforded by section 13—214(d)..
Plaintiffs’ final contention is that the City waived the affirmative defense of the statute of repose by raising it for the first time in their January 26, 1993, motion for summary judgment, nearly five years after plaintiffs filed their complaint. They assert that the City had a duty to raise any limitations defense at the earliest possible time but presented no explanation for failing to do so. McKinnon v. City of Chicago (1993),
Plaintiffs’ reliance on McKinnon is unwarranted. There, the cour,t held merely that a limitations defense cannot be asserted for the first time on appeal, which, of course, is not the case here, and in support of that holding it simply stated that the party wishing to plead such a defense has a duty to do so at the earliest possible moment. (McKinnon,
Furthermore, section 2—616(a) of the Code of Civil Procedure specifically provides that amendments adding new defenses may be allowed at any time prior to final judgment (735 ILCS 5/2—616(a) (West 1992)); and section 2—1005(g) provides that "[bjefore or after the entry of a summary judgment, the court shall permit pleadings to be amended upon just and reasonable terms” (735 ILCS 5/2—1005(g) (West 1992); see also In re Estate of Hoover (1993),
A circuit court’s decision to allow or deny late amendments, as Turner exemplifies, will not be disturbed on review absent an abuse of discretion; this court has upheld the allowing of such amendments when the opposing party would not be prejudiced thereby, even regarding matters of which the pleader was aware at the time the action was filed and for which the pleader offered no acceptable reason for omitting it in the original pleading. (Behr v. Club Med, Inc. (1989),
In People ex rel. Foreman, the court upheld the trial court’s allowing the defendant leave to amend its answer to plead a statute of limitations defense even though that defense had been available from the date the action was filed, almost A1! 2 years before amendment was sought. The appellate court reasoned that at the time of the amendment the trial had not yet begun, the assertion of the limitations defense did not require further investigation by either party, and the defense, if upheld, would eliminate the necessity and expense of a trial. People ex rel. Foreman,
Similarly, here, the trial had not yet begun when the circuit court granted the City leave to file its affirmative defenses. Further, the City first raised the repose defense in its amended motion for summary judgment on October 27, 1993, nearly five months before trial was then scheduled to begin. In addition, that defense, if upheld, would eliminate the necessity and expense of a trial. Besides, plaintiffs make no claim that they were required to conduct any further investigation due to the City’s late assertion of that defense. Finally, while plaintiffs’ expenses would have been less if the City had raised the repose defense earlier, such a factor does not rise to the level of prejudice needed to show an abuse of discretion on the part of the circuit court. (People ex rel. Foreman,
For the foregoing reasons, we uphold the ruling of the circuit court that plaintiffs’ action is time-barred by the 14-year statute of repose contained within the construction design management and supervision section of the Code of Civil Procedure (735 ILCS 5/13—214(b) (West Supp. 1993)).
Affirmed.
HARTMAN and DiVITO, JJ„ concur.
