Oak Construction Co. v. Department of State HighwaysOak Construction Co. v. Department of State Highways
This appeal comes to ns from the Court of Claims. Plaintiff contracted with the State Highway Department to do certain repair work on US 10 in Pontiac, Michigan. The work began on May 21, 1963, and was completed on November 30, 1964.
On December 17, 1965, plaintiff submitted claims for “extras” to the project engineer. “Extras” are requests for compensation for necessary work done while completing the contract but not included in the contract specifications.
Final estimates of costs were completed by the project engineer on February 28, 1966, and sent to plaintiff on March 22, 1966. On April 28, 1966, plaintiff received a check from defendant covering the amount of the final estimate. This check excluded over $68,000 worth of “extras” plaintiff claimed was due him under the contract.
Pursuant to procedures set up by defendant highway department, plaintiff, on May 7, 1966, presented a list of these disputed claims to the central office adjustment board of the highway department
Subsequently, plaintiff filed a complaint in the Court of Claims for the amount of the “extras” on March 28, 1969. Defendant filed a motion for an accelerated judgment on the grounds that plaintiff had not filed a notice of claim within one year after the claim accrued as required by
The sole question for our determination and interpretation in this appeal is: when does a claim accrue, under the instant facts, within the meaning of
Plaintiff argues on appeal that his claim did not accrue until it was finally rejected by the central adjustment board of the highway department. He argues that as long as he was pursuing remedies within the highway department his claim had not accrued.
Defendant counters that plaintiff’s claim accrued on February 28,1966, when he received the final estimates from the project engineer.
It appears that this particular issue is one of first impression in this state, although the issue has given rise to a not inconsiderable amount of litigation in other states. See
Edlux Construction Corporation
v.
State of New York
(1937), 252 App
The Court of Claims act contains two limitations. The first is that found in
This' Court, in the case of
Anthonsen
v.
State Highway Commissioner
(1966),
In the case before us today, it is quite obvious that the plaintiff relied upon these internal procedures of the highway department. He thus did not file his claim in the Court of Claims until these internal procedures were exhausted.
The action of plaintiff was entirely consistent with the applicable doctrine of exhaustion of administrative remedies. That general precept holds that one must avail oneself of all administrative remedies before one seeks redress in the courts. See
To rule as defendant urges in the instant case would place plaintiff in a position that is inconsistent with our system of justice. For example, if plaintiff is required to file in the Court of Claims before he exhausts all his administrative remedies,
Additionally, to hold as defendant argues here would enable defendant to defeat plaintiff’s claim by administrative delay. If defendant took longer than the three-year limitation period to finally review plaintiff’s claim, then plaintiff would lose his action in the Court of Claims while waiting for the defendant to make its final review. We note in passing that in the instant case the central office adjustment board took nearly two years to review plaintiff’s claim before rejecting it. The concern over a possible three-year delay is certainly not spurious.
Furthermore, the notice policy as embodied in
Fairness and logic mandate that we hold that a claim accrues under
We therefore reverse the Court of Claims, reinstate plaintiff’s action, and remand for a trial on the merits. No costs, a public question being involved.