The opinion of the court was delivered by
In this appeal from an order dismissing plaintiffs’ complaint seeking to enforce defendants’ compliance with public bidding laws, the principal issue is whether a subsidiary of a State authority, the New Jersey Schools Construction Corporation (the SCC), may permit a general (or prime) contractor to substitute major trade subcontractors for those listed in the general contractor’s bid documents after the bid has been awarded. We conclude that such a practice is contrary to public bidding laws and their underlying policies.
Plaintiffs are an association of New Jersey-based mechanical contracting firms and its executive director. The SCC is a subsidiary of the New Jersey Economic Development Authority, a public entity authorized by the Educational Facilities Construction and Financing Act, N.J.S.A. 18A:7G-1 to -44, to construct and finance school facilities projects in Abbott
The New Jersey Economic Development Authority Act requires that when the SCC procures contracts, it
shall advertise and receive (1) separate bids for each of the branches of work specified in subsection a. of this section;[3 ] or (2) bids for all the work and materials required to complete the school facilities project to be included in a single overall contract, in which case there shall be set forth in the bid the name or names of all subcontractors to whom the bidder will subcontract for the furnishing of any of the work and materials specified in branches (1) through (If) in subsection a. of this section; or (3) both.
*316 [N.J.S.A. 34:lB-5.7b (emphasis added).]
Thus, the SCC can obtain separate bids from and award separate contracts to certain major trade contractors; enter into a single contract with one general contractor; or a combination of the two. N.J.S.A. 34:1B-5.7b(2), (3).
In their complaint in lieu of prerogative writs, plaintiffs, claiming a violation of N.J.S.A. 34:lB-5.7b(2), sought mandamus-type relief to compel the SCC to end its practice of permitting general contractors to substitute major trade subcontractors for those the general contractor named in its bidding documents.
In the Law Division, the SCC acknowledged that it was permitting prime contractors to substitute subcontractors for those named in their bids, but contended it was within its discretion to do so. The SCC claimed substitutions were made pursuant to a specific written policy it had implemented during the pendency of the instant litigation. Specifically, the policy allowed the SCC to permit subcontractor substitutions where the subcontractor identified in the price proposal was going out of business; refused to perform; refused to adhere to the contract requirements; stated in writing that it was over-extended or over-committed and pro
As a result of the implementation of this policy, plaintiffs moved to transfer the case to this court, contending that the policy is a “rule” promulgated by a State administrative agency, and as such, was in violation of the statutory requirements of the Administrative Procedure Act, N.J.S.A. 52:14B-1 to -15. See generally Metromedia, Inc. v. Dir., Div. of Taxation, 97 N.J. 313, 328-38,
We first turn to whether the case should have been dismissed because no controversy existed between plaintiffs and defendants. In arriving at its decision, the court reasoned:
At this time, the [SCC] has exercised its discretion and has in place a subcontractor substitution policy and an uncompleted contracts form for each subcontractor. Although O’Shea argues that there are additional duties the [SCC] should perform, absent some violation that impacts on the rights of a particular bidder; to wit, an aggrieved party, the exercise of that discretion is best left to the agency.
We disagree. Plaintiffs have demonstrated a justiciable controversy. A justiciable controversy exists when “one party definitively asserts legal rights and such rights are positively denied by the other party.” Registrar & Transfer Co. v. Dir., Div. of Taxation, 157 N.J.Super. 532, 539,
Plaintiffs also have standing to sue. Standing is an aspect of justiciability. Flast v. Cohen, 392 U.S. 83, 98-99, 101, 88 S.Ct. 1942, 1952-53,
Here, plaintiffs have standing for two reasons. First, they are taxpayers. Second, it is uncontested that members of the association regularly vie for plumbing and HVAC subcontracts for the SCC’s school facilities projects. Plaintiffs have therefore demonstrated an interest in the litigation both as taxpayers and as representatives of the organization’s constituent members, who have a personal interest in the SCC’s bidding procedures. Thus, given plaintiffs’ standing and the existence of a justiciable controversy, the complaint should not have been dismissed.
Plaintiffs contend that N.J.S.A. 34:1B-5.7b(2) does not permit substitutions of the bid-named major-trades subcontractors in the post-award/pre-subcontracting period. Defendants argue that neither the statutory provision itself, nor the case law interpreting it, prohibits post-award subcontractor substitution, and that the SCC has the discretion to develop and implement a substitution policy. On balance, we conclude that plaintiffs’ position more accurately reflects the statutory language and the policies underlying the public bidding statutes.
“[Pjublic bidding statutes exist for the benefit of taxpayers ... and should be construed with sole reference to the public good.” Borough of Princeton v. Bd. of Chosen Freeholders of Mercer, 169 N.J. 135, 159-60,
In this case, plaintiffs claim that N.J.S.A 34:1B-5.7b(2), which requires a prime contractor to list in its bid all of the major trade subcontractors with whom the prime will contract for the project being bid, precludes subcontractor substitution after the contract has been awarded. Though no published opinion has directly addressed this issue, our inquiry is informed by our construction of N.J.S.A. 40A:11-16, a provision of the Local Public Contracts Law (LPCL), N.J.S.A. 40A:11-1 to -51.
N.J.S.A. 40A:11-16 says that in a single bid by a prime contractor, there “shall be set forth in the bid the name or names of all subcontractors to whom the bidder will subcontract.” This provision contains language identical to that found in N.J.S.A 34:1B-5.7b(2). In construing the former provision, we have concluded that it precludes substitution of subcontractors not named in the bid. See Gaglioti Contracting, Inc. v. City of Hoboken, 307 N.J.Super. 421, 431, 434-35,
Stano is illustrative. There, the County awarded a lump sum contract to Soldo Construction Company, which listed the names of various subcontractors in its bid. Stano, supra, 187 N.J.Super. at 529,
[t]he purpose of bidding statutes is to secure the benefits of competition for the public, and they are to be strictly construed to achieve this end. (citation omitted) If a bidder were able to substitute unlisted subcontractors, he could wait until after being awarded the bid and negotiate for a lower price, the savings from which would accrue to him and not to the public. Thus, a strict interpretation of “all subcontractors to whom the bidder will subcontract” as those subcontractors whom the bidder will actually use is consistent with the manner in which the act has been interpreted.
{Id. at 535,455 A2d 541 .]
See also Clyde M. Lattimer & Son Constr. Co. v. Twp. of Monroe Utils. Auth., 370 N.J.Super. 130, 138,
We came to a similar result in Prismatic, supra, 236 N.J.Super. 158,
We revisited the issue of substitution of subcontractors under the LPCL in Gaglioti, supra, 307 N.J.Super. 421,
A common thread is woven through the fabric of the case law interpreting N.J.S.A 40A:11-16. The statute is strictly construed to require the prime contractor to use the subcontractors listed in the bid documents. This construction gives meaning to the statutory language, fosters competition and decreases the chance of bid shopping. We see no reason why N.J.S.A 34:1B-5.7b(2) should be construed any differently. Both N.J.S.A. 34:1B-5.7b(2) and N.J.S.A 40A:11-16 require that the names of all subcontractors to whom the bidder will subcontract be part of the bidding documents. To allow the agency here to permit substitutions after the bid has been awarded would effectively neutralize that requirement.
The public policies underlying bidding by local governments also underly public bidding by the SCO, a State authority. It would be inconsistent to preclude subcontractor substitution by the former, but permit it by the latter.
Our conclusion is buttressed by the language of N.J.S.A 18A:7G-37, which requires that both the contractor who bids a school facilities project in New Jersey, as well as “any subcontractors required to be named under [the Educational Facilities Construction and Financing Act] shall, as a condition of bidding, submit a sworn contractor certification regarding qualifications and credentials.” N.J.S.A. 18A:7G-37a. This statute would have little meaning if the subcontractor named in the bid could be removed by the prime contractor after the bid was awarded.
The need to furnish the names of subcontractors along with the bid of a general contractor is also found in the public bidding statutes of the State government, N.J.S.A 52:32-2b; as well as in the public bidding requirements of other State agencies, including boards of education, N.J.S.A 18A:18A-18; State colleges, N.J.S.A. 18A:64-76.1a; county colleges, N.J.S.A. 18A:64A-25.25; and the New Jersey Building Authority, N.J.S.A. 52:18A-78.11. While the construction of each of these statutes is not before us, defendants’ position would lead to inconsistent treatment of bidders by the various State agencies, uncertainty in the contracting community, and would open the door to mischief that could undermine competition and public confidence in the process. Cf. Exec. Order No. 37 (2006) (requiring consistency and openness in the procurement of public contracts by all State authorities).
Notes
This opinion does not affect a general contractor’s remedies if a subcontractor breaches after a contract between the general contractor and the subcontractor has been signed.
See, inter alia, Abbott v. Burke, 100 N.J. 269,
The work referred to in subsection a of the statute includes:
(1) the plumbing and gas fitting and all work and materials kindred thereto,
(2) the steam and hot water heating and ventilating apparatus, steam power plants and all work and materials kindred thereto, (3) the electrical work,
(4) structural steel and miscellaneous iron work and materials____
[N.J.S.A. 34:1B-5.7a.]
Plaintiffs also asserted that defendants failed to enforce N.J.S.A. 18A:7G-37a and c, which require that the contractor, and all subcontractors, must certify, among other things, "that, at the time that the firm is bidding a project, the amount of its bid proposal and the value of all of its outstanding incomplete contracts does not exceed the firm’s existing aggregate rating limit.” Because the SCC has since recognized its obligation to enforce this provision, we do not address this claim in this opinion.
In addition, because we have concluded that the SCC may not, by policy or by rule, permit subcontractor substitutions after the contract has been awarded, we need not decide plaintiffs' claim that the SCC's policy constituted improper rulemaking. See R. 2:2-3(a)(2) (jurisdiction to determine validity of agency rules lies in the Appellate Division).
