Edward O‘HARA, Plaintiff and Respondent, v. Jay A. HALL, Jr., Defendant and Appellant.
No. 16820.
Supreme Court of Utah.
April 21, 1981.
1289
Appellant also argues that a more stringent standard of proof requires a correspondingly more stringent standard of appellate review and that a more lax standard results in a denial of due process. There was competent evidence adduced which the trial court could have found clear and convincing to support its findings, and there is no foundation on which to base a due process objection.
Finally, appellant recognizes that his assertion that the trial court should be required to make findings specifically on the credibility of witnesses “is a novel one and may be without merit.” Appellant asserts that without findings regarding credibility of witnesses the losing party cannot know which facts were determinative of the outcome. Appellant‘s suggestion is indeed novel and unpersuasive. It is obvious that a fact-finder must weigh conflicting evidence by assessing the credibility of the witnesses. Credibility itself, however, is not a factual issue that is appropriately the subject of the court‘s findings. Rather, the findings of ultimate facts implicitly reflect consideration of the believability of the witnesses’ testimony.
Having considered the arguments of appellant and finding them to be without substance, we affirm the decree and order of the court below. Costs awarded to respondent.
MAUGHAN, C. J., and HALL, STEWART and OAKS, JJ., concur.
Dexter L. Anderson, Fillmore, for defendant and appellant.
Eldon Eliason, Delta, for plaintiff and respondent.
MAUGHAN, Chief Justice:
We reverse, and remand for a new trial.
The facts of this case are indeed in dispute. Plaintiff alleged that he and defendant, a carpenter, entered a valid, written construction contract1 on August 15, 1977, by which defendant promised to build an addition to plaintiff‘s house for the sum of $24,200. He further alleged that defendant breached said contract by completing the work in a defective and unworkmanlike manner, causing plaintiff substantial damages. Defendant, on the other hand, denied that the written contract was ever intended to be a binding agreement between the parties, but was merely an estimate to be submitted by plaintiff to his bank to obtain a loan. Defendant pointed to the lack of details in the alleged contract to support his view. He instead claimed that he and plaintiff entered an employment contract for hourly wages, similarly to a prior arrangement between the parties.
At trial, the judge listened to extensive conflicting testimony by both parties and then ruled as a matter of law that the parties had entered a binding construction contract. He consequently left to the jury only the issue of damages to decide. The jury returned a special verdict for plaintiff, awarding damages of $10,237.56.
This case is properly before us in conformity with Rule 72, Utah Rules of Civil Procedure, which permits appellate review of cases at law only on questions of law. Here there is one basic question of law presented for review. Did the trial judge err in ruling that a valid and binding contract existed as a matter of law?
As a general rule, the construction and interpretation of a contract is a question of law to be decided by the judge.2 In
Plaintiff alleged that the writing was intended to be a binding construction contract. Defendant, on the other hand, asserted that its sole purpose was to help plaintiff obtain a bank loan, and that the parties instead entered an oral employment contract for hourly wages. Despite this conflicting evidence, the trial judge ruled as a matter of law that the parties intended the writing to bind them. In this he erred.
It is the rule “that where the existence of a contract is the point in issue and the evidence is conflicting or admits of more than one inference, it is for the jury to determine whether the contract did in fact exist.”4 In Thornton v. Pasch,5 this court held that whether a party accepted an offer so as to form a binding contract was for the jury to decide. And in Brown v. Board of Education of Morgan County School District,6 we held that “while it is for the court to interpret and assess the meaning of a contract, issues of fact are properly submitted to a jury.”
Whether the parties intended to enter a binding contract is such an issue of fact. The Supreme Court of Wisconsin formulated it thus: “There is no meeting of the minds where the parties do not intend to contract and the question of intent generally is one to be determined by the trier of fact.” Household Utilities v. The Andreiss Co.7
Here there is substantial evidence that the parties did not intend the writing to bind them as a construction contract. The issue of intent was one of fact and should have been submitted to the jury for resolution. We, therefore, reverse and remand for a new trial, in accordance with this opinion.
Defendant also asks us to determine, as a matter of law, that the writing here was too indefinite to be enforced as a contract. Because of the result we have reached we need not meet this issue.
HALL and OAKS, JJ., concur.
STEWART, J., concurs in the result.
HOWE, Justice (concurring and dissenting):
I concur, but believe that we should also decide the other question raised by the defendant, i. e., whether the writing here was too indefinite to be enforced as a contract. Since this question may emerge again upon remand for a new trial, this Court should observe its long-standing practice of deciding questions which may again arise. Deciding the question now may well save the parties another appeal.
Notes
“I, Jay Hall, propose to furnish all materials and perform all labor necessary to complete the following:
“An addition to the old house (12’ × 30‘) comprising family room, kitchen, and fruit om. Reshingle old roof. Install thermal pane windows in all house. Remodel bathroom in old house. Lower ceiling in living room, and install radiant heat. Remodel upstairs. Remove old porch. Remodel stairs. Install several doors in old house. (not including siding and cabinets).
“All of the above work to be completed in a substantial and workmanlike manner according to standard practice for the sum of . . . . $24,200.”
