O & G Industries, Inc. v. National Railroad Passenger Corp.O & G Industries, Inc. v. National Railroad Passenger Corp.
This case is procedurally complicated. The present appeal arises out of a third-party complaint brought by National Railroad Passenger Corporation (hereafter “Amtrak” or “appellee”) against 0 & G Industries, Inc. (hereafter “0 & G” or “appellant”) in the United States District Court for the District of Connecticut (Dorsey, J.). In its complaint, Amtrak sought indemnification from 0 & G for any liabilities and costs, including attorneys’ fees, that Amtrak would incur in two consolidated tort actions against it for wrongful death and personal injury damages resulting from a train accident. 1
The proceedings in the district court included two rulings that 0
&
G now appeals to this Court. First, before trial of the third-party indemnity action began, the district judge granted partial summary judgment to Amtrak on the basis of an explicit indemnity provision in a right-of-access contract between Amtrak and 0
&
G. The court upheld the validity of the indemnity provision, ruling that
Second, the judge granted Amtrak’s post-trial motion for judgment as a matter of law, setting aside a jury verdict that O & G was relieved of its obligation to indemnify Amtrak because of Amtrak’s material breach of the contract with O & G. Judge Dorsey held that Amtrak’s contractual default did not affect the validity of the indemnity agreement, which explicitly covered accidents attributable to Amtrak’s negligence.
See Roberts v. Nat’l R.R. Passenger Corp. v. O & G Indus.,
Nos. 3:04— cv-1318, 3:04-cv-1622
&
3:04-cv-2195,
O & G argues on appeal that the district court erred in (1) granting partial summary judgment to Amtrak; (2) entering judgment for Amtrak as a matter of law; (3) curtailing O & G’s cross- and direct examination of an Amtrak employee during the trial; and (4) awarding Amtrak attorneys’ fees and defense costs without any evidence as to their amount and reasonableness.
On the first and second of these issues, we affirm the district court. On the third, we find the limitations of O & G’s cross-examination rights by the district court, even if erroneous, were not substantially prejudicial to appellant. On the fourth issue, we conclude that we lack appellate jurisdiction over the district court’s non-final award of attorneys’ fees and costs.
I. BACKGROUND
The accident that led to this litigation occurred in June 2004, while Gregory Rob
David Roberts (hereafter “Roberts”), the brother of the deceased 0 & G employee and administrator of his estate, filed in August 2004 a wrongful death action against Amtrak, seeking compensatory and punitive damages. The suit by Roberts was consolidated with Quintiliani’s personal injury action. After answering the two actions, Amtrak filed its third-party complaint against 0 & G.
The indemnity claim was based on a clause in the “Temporary Permit to Enter Upon Property” (hereafter “Permit”), a contract concluded between O & G and Amtrak in October 2003. Under the Permit, Amtrak allowed O & G access to Amtrak’s property in East Haven, in order to perform construction work in relation to O & G’s contract with the Connecticut State Department of Transportation regarding the re-building of a stretch of Interstate 95 between New Haven and Branford, Connecticut; consideration was $1. O & G, on its part, undertook to “use all necessary care and precaution to avoid accidents, delay or interference with [Amtrak’s] trains or property” and abide by Amtrak’s safety regulations. Pursuant to the Permit, Amtrak would provide, at its discretion and at O & G’s expense, “flag service and/or other protection” necessary to maintain the “safety and continuity of railroad traffic,” over which Amtrak retained exclusive control. However, the provision of “protective services” would “not relieve [O & G] from [its] complete responsibility for the adequacy and safety of [its] operations.” A key feature of the Permit is the following provision:
The Permittee [O & G] shall defend, indemnify and hold harmless Railroad [Amtrak], its officers, directors, employees, agents, servants, successors, assigns and subsidiaries, irrespective of their negligence or fault, from and against any and all losses and liabilities, ... claims, causes of action, suits, costs and expenses incidental thereto (including cost of defense and attorney’s fees), which any or all of them may hereafterincur, be responsible for, or pay as a result of injury, [or] death, ... to any person ... arising out of or ... resulting from activities of or work performed by [0 & G], its officers, employees, agents, servants, contractors, subcontractors, or any other person acting for or by permission of [0 & G]. The foregoing obligation shall not extend to situations where the negligence or fault of Amtrak, its officers, directors, [or] employees ... is the sole causal negligence or fault, except that it shall so extend to injury [or] death ... to employees of [0 & G], its agents, servants, contractors, subcontractors, or any other person acting for or by permission of[0 & GJ. The foregoing obligation shall not be limited by the existence of any insurance policy or by any limitation on the amount or type of damages, compensation, or benefits payable by or for [0 & G] or any contractor or subcontractor, and shall survive the termination of this permit for any reason.
(Emphasis added.) In the district court, 0 & G argued that the above provision was invalid under Connecticut General Statute § 52-572k(a), which declares void as against public policy agreements to indemnify a party against its own negligence, if such agreements were made “in connection with or collateral to” construction contracts.
Before trial began on Amtrak’s indemnity claim, Amtrak sought summary judgment and orders directing 0 & G to defend Amtrak in the two tort actions and reimburse Amtrak’s reasonable attorneys’ fees in defending against those claims. In March 2006, Judge Dorsey granted Amtrak partial summary judgment, concluding that
The jury trial of the consolidated actions by plaintiffs Roberts and Quintiliani against Amtrak began in March 2006. The first phase (“Phase I”) was limited to the issue of damages to be awarded to plaintiffs. Amtrak conceded negligence (but not recklessness). In April 2006, the jury awarded plaintiffs $1,425 million each in compensatory damages, but rejected the punitive damages claims, finding that Amtrak’s conduct was not willful or reckless. 3 At the end of the second phase of the trial (“Phase II”) concerning Amtrak’s third-party complaint against O & G, the jury found that O & G was excused from its obligation to indemnify Amtrak, because Amtrak’s failure to provide O & G’s crew adequate on-site protection amounted to a material breach of the Permit, rendering it void in its entirety.
After this second verdict, Amtrak moved for judgment as a matter of law, under
In September 2006, the judge granted Amtrak’s
In December 2006, the court entered judgment in favor of Amtrak in its indemnity action against O & G. This timely appeal by O & G followed.
II. DISCUSSION
The parties to this appeal raise several issues. First, we must decide whether the Connecticut statute, which nullifies indemnity agreements insulating a contracting party from its own negligence,
4
applies, on its face, to the Permit; if it does, we must next examine whether
A. Preemption
Our review of a grant of summary judgment under Rule 56 is plenary. “[S]um-mary judgment is appropriate where there exists no genuine issue of material fact and, based on the undisputed facts, the moving party is entitled to judgment as a matter of law.”
D’Amico v. City of New York,
1) Applicability of the Connecticut Statute
In its appeal, O & G relies heavily on the Connecticut statute. In response, Amtrak claims for the first time that the Connecticut statute does not apply to the Permit because it allegedly bars indemnity agreements only if inserted in construction contracts. Amtrak argues that the Permit was not such a contract. In the district
2) Preemption by
O
&
G counters that
Federal preemption of state law is a doctrine grounded in the Supremacy Clause of the Constitution.
See
As the district court correctly concluded,
O & G first contends that no irreconcilable conflict exists between the federal and the Connecticut statutes, because Congress intended
Furthermore, if Congress intended
The title of
We conclude that
0 & G also argues that the scope of
Nonetheless, 0 & G’s argument that congressional intent, as evidenced by the legislative history of
The legislative history of
[T]his bill clarifies that indemnification agreements related to the provision of rail passenger service entered into by Amtrak and other parties would be enforceable. The Committee has been requested by Amtrak to include this provision in order to aid Amtrak in achieving operating self-sufficiency .... As long as there is the possibility that state laws governing indemnification contracts may make these contracts unenforceable, Amtrak and a freight railroad may find themselves litigating with each other. Amtrak believes that such litigation inevitably would not only adversely impact business relationships between Amtrak and the host freight railroads, but it would also lead to significantly higher outlays in settlements and judgments to plaintiffs.
S.Rep. No. 105-85, at 5 (1997) (emphasis added). Congress unmistakably intended “[t]he language in
Against this legislative background, contentions that Congress intended to allow state law or public policy to interfere with Congress’s attempt to rescue Amtrak are simply not persuasive. We believe that we must enforce and recognize the validity of the indemnity provision in the Permit. Applying the Connecticut statute would violate the plain language and spirit of
B. Material Breach of the Permit
At the conclusion of Phase II of the trial, the jury found that, under the indemnity provision in the Permit, O
&
G was required to reimburse Amtrak for costs incurred and damages awarded in the Roberts and Quintiliani actions, but that Amtrak’s material breach of the Permit relieved O & G of all its contractual duties, including the obligation to indemnify Amtrak. However, the district judge overturned the jury verdict, ruling that as a matter of law 0 & G’s contractual obligation to indemnify Amtrak was valid regardless of Amtrak’s negligence.
See Roberts,
“[A] material breach is a failure to do something that is so fundamental to a contract that the failure to perform that obligation defeats the essential purpose of the contract or makes it impossible for the other party to perform under the contract.” 23
Williston on Contracts
§ 63:3 (4th ed.2007) (footnotes and internal quotation marks omitted). Under Connecticut law, an uncured, material failure of performance by one contracting party discharges the other party from any further performance under the contract, which is rendered unenforceable
in toto. See Bernstein v. Nemeyer,
It is uncontroverted that O & G complied with its obligations under the Permit to perform its work on Amtrak’s property so as to observe Amtrak’s safety regulations and not “interfere with [Amtrak’s] operations.” By contrast, Amtrak’s failure to provide adequate protection to O & G’s workers, O
&
G claims, negated the
We agree with the district judge’s holding. Not only is the indemnity clause not qualified by or conditioned on Amtrak’s obligation to operate its trains safely through the worksite, but it explicitly provides Amtrak with a right to indemnity even where “the negligence or fault of Amtrak [or] its ... employees” is the sole cause of “injury, death, disease, or occupational disease to employees of’ 0 & G. 9 0 & G cannot circumvent its indemnity obligation by invoking Amtrak’s negligence, which the parties envisaged and clearly determined would not exonerate 0 & G from its contractual duties. As Judge Dorsey emphasized, if 0 & G is allowed to evade its obligation to hold Amtrak harmless, “Amtrak’s protection against ultimate responsibility for any unsafe train operation, as provided in the Permit, would be nullified.” Id. at *6. Since the indemnity provision expressly contemplates the factual situation that arose here (i.e., Amtrak’s negligence was the sole cause of injury and death to 0 & G’s employees), Amtrak’s failure to safely operate its trains through 0 & G’s work zone could not have thwarted the Permit’s essential purpose.
A reading of the Permit as a whole suggests, in fact, that at the core of the agreement was the parties’ preoccupation with the “safety and continuity of railroad traffic,” rather than the safety of 0 & G’s personnel. The emphatic references to 0 & G’s undertaking to take all measures necessary to avoid undue interference with train operations and its “complete responsibility for the adequacy and safety of’ its activities suggest that the Permit was drafted with a principal focus on Amtrak’s interests. Even Amtrak’s promise to furnish protection was aimed at ensuring the safety and continuity of railroad traffic and would come into play only if, in the opinion of Amtrak’s officers, “conditions warrant” it, and under the condition that 0 & G would bear all the costs. It is a fair inference that the essential purpose of the Permit was not to guarantee the safety of 0 & G’s employees, but rather to authorize 0 & G’s temporary access to Amtrak’s property while reassuring Amtrak that 0 & G’s presence on its property would neither disrupt train operations nor damage Amtrak’s trains and facilities. Amtrak’s negligent failure to provide adequate protection to 0 & G’s workers did not vitiate this purpose.
0 & G does not claim that every negligent act by Amtrak would constitute a material breach of the Permit. According to 0 & G, there could be situations involving negligent acts by Amtrak representatives that, nevertheless, would be covered by the indemnity provision without necessarily amounting to a breach of a fundamental contractual term. For example, 0 & G claims, “an Amtrak employee could accidentally strike someone with a tool or a piece of equipment, or could dig a hole into which an individual might fall.” See Br. of Appellant at 36.
The breadth of the indemnity provision refutes the distinction 0 & G seeks to introduce. The provision does carve out
“Simply stated, ... the evidence [here] is such that, without ... considering the weight of the evidence, there can be but one conclusion as to the verdict that reasonable men could have reached.”
Simblest v. Maynard,
C. Cross-Examination of Amtrak’s Employee by O & G
The district court permitted O & G to participate in Phase I of the trial, in which plaintiffs Roberts and Quintiliani sued defendant Amtrak. The judge’s rationale was that evidence presented in relation to plaintiffs’ claims against Amtrak might well bear on Amtrak’s indemnity claim against O & G. Nevertheless, the judge did not permit O & G’s counsel to cross-examine Amtrak’s New England Division Superintendent Fred Fournier. O & G’s stated reason for cross-examining Fournier was to elicit testimony tending to prove that O & G was not at fault for the accident, which was entirely attributable to Amtrak’s reckless conduct. O & G argues that a showing of Amtrak’s recklessness would enable O & G to avoid its indemnity obligations on public policy grounds. Judge Dorsey’s reasoning for denying O & G’s request to cross-examine Fournier was that issues pertaining to O & G’s role in the accident would be addressed in Phase II. O & G was told that it would have ample opportunity to present its recklessness defense at that time. However, when O & G attempted to question Fournier in Phase II of the trial about whether Amtrak followed proper internal procedures to avert safety risks to O & G’s on-site employees, the court sustained Amtrak’s objection to this line of questioning. The judge noted that the jury had already resolved the issue of Amtrak’s fault in Phase I of the trial.
O & G now claims that by precluding its cross-examination of Fournier in Phase I and limiting its questioning of the same witness in Phase II of the trial, the district judge prevented O & G from fully litigating the question of Amtrak’s recklessness — on which one of O & G’s defense was premised' — and thus deprived it of its cross-examination rights. The error, according to O & G, warrants a new trial.
As a preliminary matter, we reject Amtrak’s contention that this claim has not
We turn to the merits of 0 & G’s claim. “Whether an evidentiary error implicates a substantial right depends on ‘the likelihood that the error affected the outcome of the case.’”
See Tesser v. Bd. of Educ.,
We believe that the court’s alleged error did not have a substantial impact on the outcome of the case. 0 & G’s interests were adequately protected by Roberts and Quintiliani, the plaintiffs in Phase I. These parties were seeking punitive damages from Amtrak and thus had an equal, if not greater, incentive than 0 & G to show that Amtrak’s conduct was reckless. The question of Amtrak’s recklessness was adequately litigated by Roberts and Quintilia-ni and there is no indication that the jury would have found recklessness, had 0 & G been allowed to cross-examine Fournier. The limitation of 0 & G’s cross-examination rights, even if erroneous, did not cause any prejudice to 0 & G, because “it is [not] likely that in some material respect the factfinder’s judgment was swayed by the error.”
Tesser,
Furthermore, even supposing the district judge had not restricted 0 & G’s examination of Fournier in Phase I, and that 0 & G had convinced the jury that Amtrak’s conduct was reckless, it is doubtful that the outcome of the case would have been more favorable to 0 & G. The indemnity provision in the Permit unequivocally requires 0 & G to reimburse Amtrak for all the losses Amtrak may sustain as a result of death or injury to 0 & G’s employees, even when Amtrak’s own negligence or fault is the sole cause of the incident. The unmistakable wording of the clause would thus not allow 0 & G to nullify its obligation to indemnify Amtrak, even if the jury had entered a punitive damages award against Amtrak on recklessness grounds.
0
&
G argues to us that, had it been allowed to fully participate in Phase I of the trial, and had the jury found Amtrak’s conduct reckless, 0 & G would have been relieved of its duty to hold Amtrak harmless, by raising a public policy defense against enforcement of the indemnity agreement. We disagree. We have already held in this opinion
(see
Part II.A, supra) that the Connecticut statute embodying the public policy of Connecticut against indemnification for liabilities due solely to the negligence of the indemni-tee
10
is preempted by § 28103(b). Subsection § 28103(b) also superseded the opinion that would have been most helpful to 0 & G in its public policy defense against indemnification for reckless conduct.
See Nat’l R.R Passenger Corp. v. Consol. Rail Corp. (“ConRail”),
698
In view of the above, we hold that, assuming arguendo that the district judge erred in preventing O & G from cross-examining Fournier in Phase I and from fully pursuing its recklessness defense in Phase II, the error was not prejudicial to O & G in the context of the trial as a whole and does not justify a new trial.
D. Attorneys’Fees
In granting Amtrak’s
Pursuant to
This defect does not impair the finality of the district court’s ruling on Amtrak’s motion for judgment as a matter
III. CONCLUSION
We have considered all of appellant O & G’s arguments- and find them to be without merit. For the reasons discussed above, we affirm the district court on all issues except for the ruling on attorneys’ fees, over which we lack appellate jurisdiction. Affirmed in PART and Dismissed in Part.
Notes
. The two actions were Roberts v. Nat’l R.R. Passenger Corp., No. 3:04-cv-1318 (D. Conn. filed Aug. 9, 2004), and Quintiliani v. Nat'l R.R. Passenger Corp., No. 3:04-cv-2195 (D. Conn, filed Dec. 29, 2004). A third action was brought against Amtrak by the Hartford Fire Insurance Company, as subrogee of O & G, for damage to O & G property caused by the train accident. See Hartford Fire Ins. Co. v. Nat’l R.R. Passenger Corp., No. 3:04-cv-1622 (D. Conn. filed Sept. 28, 2004). This action was settled and is not part of the present appeal.
. A more detailed description of the train accident can be found in the district court's March 2006 ruling on the parties’ motions for summary judgment. See
Roberts v. Nat’l R.R. Passenger Corp. v. O & G Indus.,
Nos. 3:04-cv-1318, 3:04-cv-1622 & 3:04-cv-2195,
. The Roberts estate appealed from the judgment of the district court entered against Amtrak after the verdict. That appeal was heard by this panel the same day as the appeal now before us. In November 2007, we summarily affirmed the judgment of the district court.
See Roberts v. Nat’l R.R. Passenger Corp.,
No. 06-3036-cv,
. Connecticut General Statute § 52-572k states:
(a) Any covenant, promise, agreement or understanding entered into in connection with or collateral to a contract or agreement relative to the construction, alteration, repair or maintenance of any building, structure or appurtenances thereto including moving, demolition and excavating connected therewith, that purports to indemnify or hold harmless the promisee against liability for damage arising out of bodily injury to persons or damage to property caused by or resulting from the negligence of such promisee, such promisee’s agents or employees, is against public policy and void, provided this section shall not affect the validity of any insurance contract, workers' compensation agreement or other agreement issued by a licensed insurer.
.
A provider of rail passenger transportation may enter into contracts that allocate financial responsibility for claims.
. Our refusal to consider Amtrak's waived argument on the applicability of the Connecticut statute is of little importance to the final disposition of the case. As set forth below, we agree with the district court's finding that the Connecticut statute is preempted by federal law and thus does not invalidate the indemnity clause in the Permit.
. That subsection provides:
(a) Limitations.
—(1) Notwithstanding any other statutory or common law or public policy, or the nature of the conduct giving rise to damages or liability, in a claim for personal injury to a passenger, death of a passenger, or damage to property of a passenger arising from or in connection with the provision of rail passenger transportation, ... punitive damages, to the extent permitted by applicable State law, may be awarded in connection with any such claim only if the plaintiff establishes by clear and convincing evidence that the harm that is the subject of the action was the result of conduct carried out by the defendant with a conscious, flagrant indifference to the rights or safety of others. If, in any case wherein death was caused, the law of the place where the act or omission complained of occurred provides, or has been construed to provide, for damages only punitive in nature, this paragraph shall not apply.
(2) The aggregate allowable awards to all rail passengers, against all defendants, for all claims, including claims for punitive damages, arising from a single accident or incident, shall not exceed $200,000,000.
.
Definition. — For purposes of this section—
(1) the term "claim” means a claim made — ■
(A) against Amtrak, any high-speed railroad authority or operator, any commuter authority or operator, any rail carrier, or any State; or
(B) against an officer, employee, affiliate engaged in railroad operations, or agent, of Amtrak, any high-speed railroad authority or operator, any commuter authority or operator, any rail carrier, or any State.
. The indemnity provision is quoted in full in section I of the opinion, see supra at pp. 157— 58. Its applicability in this case has not been called into question by the parties.
. See supra note 3.
. Some of our
pre-Budinich
precedent might be read to support the proposition that the non-finality of an award of attorneys’ fees sought as an element of contractual damages renders non-appealable the entire judgment in which such award is incorporated.
See, e.g., Union Tank Car Co. v. Isbrandtsen,