This appeal arises from the Bureau of Indian Affairs (“BIA”) approval of a lease of Passamaquoddy tribal land to a developer who wishes to construct a Liquified Natural Gas (“LNG”) terminal in part on that land. Nulankeyutmonen Nkihtaqmikon 1 (“NN”), a group of tribe members who oppose construction of the LNG terminal, and several individual tribe members (collectively, “Plaintiffs”) challenge the district court’s dismissal of their case for lack of jurisdiction. After careful review, and based in large part on the BIA’s change of position on appeal regarding the finality of its lease approval, we conclude that Plaintiffs have standing and that their claims are ripe for review, and therefore that the district court has jurisdiction to adjudicate Plaintiffs’ claims. We thus reverse the dismissal of this suit by the district court and remand the case for further action consistent with this opinion.
I. Background
A. Quoddy Bay Lease
The complicated nature of this case requires a slightly extended introduction. Part of the complexity stems from the fact that neither of the litigants are parties to the lease agreement that precipitated this dispute. The lease at issue is between the Pleasant Point Passamaquoddy Reservation 2 and Quoddy Bay, LLC (“Quoddy Bay”), a developer seeking to construct an LNG terminal on tribal lands. In May *24 2005, these parties formalized a ground lease agreement (“Quoddy Bay Lease”), which would allow Quoddy Bay to develop a LNG terminal on a 3/4-acre portion of tribally owned land known as Split Rock, pending federal approval of the project. The fifty-year lease is a complex and multistage contract, contemplating four distinct phases: Permitting, Construction, Operations, and Removal and Remediation. The latter periods call for heavily invasive construction and operation of the LNG terminal. The permitting period, however, allows only less-invasive testing and surveying, necessary for obtaining Federal Energy Regulatory Commission (“FERC”) approval. 3 During this initial period, Quoddy Bay is limited to
a non-exclusive right and license to enter upon and restrict access to the Premises, at any time and from time to time, to inspect, to examine, to survey, and to conduct, soil tests, borings, installation of water monitoring wells, and other engineering, geotechnical, archaeological, and architectural tests and studies on the Premises, and otherwise to do that which, in Tenant’s reasonable discretion, is necessary to conduct due diligence, to secure Permits and to determine the suitability of the Premises for the LNG Project. 4
The Tribal Council approved the lease on May 19, 2005, and pursuant to the Indian Long-Term Leasing Act of 1955 (“Leasing Act”), 25 U.S.C. § 415, sent the lease to the BIA for review. On June 1, 2005, the BIA approved the lease. 5 At the same time, the BIA issued a Categorical Exclusion Checklist, indicating that
lease approval is solely for the site investigation required for the [FERC] permitting process in the development of an [Environmental Impact Statement (“EIS”) ] .... [Complete environmental analysis and EIS development [will] be conducted through the FERC permitting process. Continuing the lease beyond the investigation period is contingent upon FERC permit approval, acceptability of the EIS analysis and insignificant impact on the leased property. The BIA will be a Cooperating Agency for the EIS development through FERC.
The BIA determined that the site investigation fell within the definition of a Categorical Exclusion, such that an EIS was not required prior to approval of the lease. 6
*25 B. Plaintiffs
In opposition to- the LNG project, a group of private citizens banded together to form NN. NN members live on Passa-maquoddy Tribal lands in Maine, though none possess individual ownership rights in Split Rock. They oppose the construction of the Quoddy Bay LNG terminal out of concern that “it will fundamentally and permanently transform the Split Rock site from a natural beach area with historical, cultural, religious, and recreational significance, to an industrial zone that will not be accessible to the members of the group.”
Plaintiffs — NN and individual tribe members — live within a mile of Split Rock and/or use the leased land for traditional tribal ceremonies, community events, and recreation. According to Plaintiffs, Split Rock is the Tribe’s “only remaining community space.”
C. Procedural History
On November 2, 2005, Plaintiffs initiated this suit claiming that the BIA’s approval of the Quoddy Bay Lease violated the Leasing Act, 25 U.S.C. § 415; the National Environmental Policy Act of 1969 (“NEPA”), 42 U.S.C. § 4321 et seq.; the National Historic Preservation Act (“NHPA”), 16 U.S.C. § 470 et seq.; the Administrative Procedure Act (“APA”), 5 U.S.C. §§ 701-706; and the Endangered Species Act (“ESA”), 16 U.S.C. § 1531 et seq. Specifically, Plaintiffs complain that the BIA failed to appraise the land, to prepare an environmental assessment, to provide an opportunity for public comment, or to consider the historical, religious, and cultural significance of the leased land. Plaintiffs later added a claim that, by violating the above statutes, the BIA had breached the federal government’s fiduciary duty to Indian citizens (the “Trust Obligation” claim). 7
The BIA moved to dismiss for lack of jurisdiction, contending that Plaintiffs lacked standing and that their claims were not yet ripe. On November 16, 2006, the district court dismissed all of Plaintiffs’ claims, concluding that the NEPA, NHPA, and Trust Obligation claims were not ripe and that Plaintiffs lacked standing to bring the NEPA, NHPA, ESA, and Leasing Act claims.
8
Nulankeyutmonen Nkihtaqmikon v. Impson,
II. Standard of Review
We review
de novo
the district court’s decision to dismiss for lack of jurisdiction on standing and ripeness grounds.
Mangual v. Rotger-Sabat,
*26 III. Finality of Lease Approval
Plaintiffs ask us to forego review of the standing and ripeness issues and instead remand the case to the district court based on the BIA’s “reversal of position” regarding the finality of its lease approval. Plaintiffs claim that the BIA argued before the district court that lease approval was limited to site investigation and was revocable upon further review by the BIA, and that the district court relied heavily on these representations. On appeal, the BIA concedes that its lease approval is final. It argues instead — -but to the same effect — that “implementation of the lease is contingent upon multiple factors, including FERC authorization,” and that therefore Plaintiffs’ alleged injuries resulting from construction of the LNG terminal are too attenuated to satisfy standing and ripeness requirements.
Because we review the standing and ripeness issues de novo, and because we have all the information we need to decide these issues, we see no reason to remand. We approach the standing and ripeness issues assuming — as everyone agrees— that the BIA has completed its lease approval process and will not have another opportunity to review the lease. For purposes of our review, we also assume, as alleged by Plaintiffs, that the BIA has failed to meet its federal obligations with respect to the lease approval. Whether or not this is true is a question on the merits of Plaintiffs’ case, which we need not address at this stage of the proceedings. 9
IV. Standing
The doctrine of standing addresses whether a particular plaintiff has “such a personal stake in the outcome of [a] controversy as to assure that concrete adverseness which sharpens the presentation of issues upon which the court so largely depends for illumination.”
Baker v. Carr,
A. NEPA, NHPA, and ESA Claims
To satisfy the “irreducible constitutional minimum of standing,” Plaintiffs must show (1) that they have suffered an injury in fact, (2) that the injury is fairly traceable to the BIA’s allegedly unlawful actions, and (3) that “it [is] likely, as opposed to merely speculative, that the injury will be redressed by a favorable decision.”
Lujan,
In cases of alleged procedural harm, however, plaintiffs receive “special treatment.”
Dubois,
one living adjacent to the site for proposed construction of a federally licensed dam has standing to challenge the licensing agency’s failure to prepare an environmental impact statement, even though he cannot establish with any certainty that the statement will cause the license to be withheld or altered, and even though the dam will not be completed for many years.
Id.
The case before us is very similar to the above example described by the Supreme Court in
Lujan.
Plaintiffs allege that they have been harmed by the BIA’s failure to follow the procedures required by NEPA, NHPA, and ESA before approving the Quoddy Bay lease,
10
bringing their claims within the procedural standing analysis. With immediacy concerns relaxed, to establish an injury in fact, Plaintiffs need only show that NEPA, NHPA, and ESA were “designed to protect some threatened concrete interest” personal to Plaintiffs.
Id.
at 572-73 nn. 7-8,
The BIA focuses its arguments on the causation requirement of standing. The agency characterizes Plaintiffs’ alleged injury as the harm to Split Rock, and consequently, Plaintiffs’ interests in the land, resulting from the impacts of the construction of the LNG terminal. It goes on to argue that any such harms are not fairly traceable to the BIA’s lease approval because the LNG terminal cannot be constructed until Quoddy Bay receives FERC approval, which is unpredictable.
11
Sea Shore Corp. v. Sullivan,
Finally, Plaintiffs meet the re-dressability requirement of Article III standing. All that is required in cases of procedural injury is “some possibility that the requested relief will prompt the injury-causing party to reconsider the decision that allegedly harmed the litigant.”
Massachusetts v. EPA,
— U.S. —,
Although the BIA does not challenge Plaintiffs’ prudential standing to pursue the NEPA, NHPA, and ESA claims on appeal, it is clear from our discussion above that “the violations and injuries alleged in the complaint are the sort that [these statutes] were specifically designed to protect,” and that Plaintiffs are asserting their own interests, rather than
*29
those of third parties.
12
Dubois,
B. Leasing Act Claim
The prudential standing concern at issue here is whether Plaintiffs’ Leasing Act claim “fall[s] within the zone of interests protected by the law invoked.”
13
Allen,
We disagree with the district court’s conclusion that Plaintiffs do not fall within the zone of interests protected by the Leasing Act. It is true, as the district court emphasized, that the Leasing Act requires federal approval when “ ‘restricted Indian lands, whether tribally or individually owned, [are] leased by the
Indian owners.’” Nulankeyutmonen Nkihtaqmikon,
The federal government’s duty under the Leasing Act, through the BIA, is to ensure that the parties to a lease of Indian land have given adequate consideration to the impacts of the lease on,
inter alia,
neighboring lands and the environment. 25 U.S.C. § 415(a). The land owners presumably have a vested interest in a lease’s approval, so it stands to reason that they would rarely challenge the BIA’s failure to comply with federal law in approving the lease. Congress surely intended, therefore, for other tribal members whose interests would be adversely affected by the lease’s impacts to complain of the agency’s action. See
Clarke,
*30
Furthermore, “[t]he [‘zone of interests’] test is not meant to be especially demanding.”
Clarke,
V. Trust Obligation Claim
The district court also dismissed Plaintiffs’ claim of breach of fiduciary duty to the extent that it was a separate cause of action from the Leasing Act claim.
16
Nulankeyutmonen Nkihtaqmikon,
Although the district court and the parties addressed this issue in their discussions on standing, we construe the court’s dismissal as one for failure to state a claim, and accordingly review
de novo. See Palmer v. Champion Mortgage,
We agree with the district court that Plaintiffs’ Trust Obligation claim cannot stand alone. Despite Plaintiffs’ vague assertions to the contrary, we can find no law in support of an enforceable fiduciary duty owed by the federal government to Plaintiffs qua individuals who are not landowners. As Plaintiffs acknowledge, the “general trust relationship between the United States and the Indian people” is insufficient to establish specific fiduciary duties.
United States v. Navajo Nation,
Here, Plaintiffs are not land owners and the BIA does not manage their interests in a fiduciary capacity. While Plaintiffs have standing to complain of the BIA’s failure to comply with federal law because they fall within the zone of interests protected by the Leasing Act, they cannot claim a specific trust relationship created by the Secretary’s general obligation to consider their interests before approving a lease.
See Brown,
*32
Although Plaintiffs have no fiduciary duty claim, their Leasing Act claim generally encompasses the same allegations, and the dismissal of the “separate” Trust Obligation claim in no way impairs their claimed right to the relief requested. The district court should therefore treat their references to the “Trust Obligation” as commensurate with the Leasing Act, which, as Plaintiffs explain, derives from the general trust obligation assumed by the federal government toward the Indian people.
See Morton v. Mancari,
VI. Ripeness
Whereas standing asks “who” may bring a claim, ripeness concerns “when” a claim may be brought.
R.I. Ass’n of Realtors, Inc. v. Whitehouse,
Plaintiffs’ remaining claims — aside from the Trust Obligation claim — allege that the BIA failed to comply with various federal laws before approving the Quoddy Bay lease. These claims of procedural injury are clearly ripe under
Ohio Forestry Ass’n, Inc. v. Sierra Club:
“[A] person with standing who is injured by a failure to comply with [statutory] procedure may complain of that failure at the time the failure takes place, for the claim can never get riper.”
The BIA argues, however, that Plaintiffs’ claims are not ripe because “the existence of the dispute itself hangs on future contingencies that may or may not occur.”
Texas v. United States,
The BIA also argues that the alleged procedural failures have not yet occurred, even though its approval is final, because FERC will consider the impacts of the lease during the permitting process. Moreover, the BIA will serve as a cooperating agency and contribute to review of the LNG project. These points are well-taken, but they do not go to ripeness. Whether the BIA can fulfill its statutory obligations by participating in the FERC process is a question on the merits of Plaintiffs’ claims.
VII. Exhaustion
In the alternative, the BIA argues that the district court lacks subject matter jurisdiction because Plaintiffs failed to exhaust their administrative remedies. BIA regulations require an appeal to the Interi- or Board of Indian Appeals before lease approval is “final,” and therefore subject to judicial review under the APA. 25 C.F.R. §§ 2.4(e), 2.6.
Plaintiffs correctly argue in response that exhaustion is not a jurisdictional bar in this case. Exhaustion of administrative remedies is a jurisdictional requirement only when Congress clearly ranks it as such.
Cf. Arbaugh v. Y & H Corp.,
Although exhaustion is not a jurisdictional issue, it is mandatory,
see id.
at 147;
R.I. Dep’t of Envtl. Mgmt.,
VIII. Conclusion
For the reasons stated above, we reverse the district court’s dismissal of Plaintiffs’ NEPA, NHPA, ESA, and Leasing Act claims. We also reverse dismissal of the APA claim, given that Plaintiffs’ other claims are revived.
See Nulankeyutmonen Nkihtaqmikon v. Impson,
Affirmed in part, reversed and remanded in part.
Notes
. "Nulankeyutmonen Nkihtaqmikon” translates into English from the Passamaquoddy language as "We Protect the Homeland.” It is pronounced "Nu-lahnk-kay-yoot-mah-nin Nee-kaht-mee-kahn. ”
. The Passamaquoddy Tribe, a federally recognized Indian tribe, maintains two separate reservations, Pleasant Point and Indian Township, both in Maine. While each Reservation has its own elected tribal government, a Joint Tribal Council manages lands held in common. The Joint Tribal Council has authorized each community to lease tribal land within its own reservation.
. For LNG import facilities located onshore and near shore in state waters, FERC has "to approve or deny an application for the siting, construction, expansion, or operation of an LNG terminal.” 15 U.S.C. § 717b(e)(l). FERC reviews proposed LNG facilities with the cooperation of numerous federal, state, and local agencies, and with the input of other interested parties. 71 Fed.Reg. 14,200-201 (March, 21, 2006) (explaining the process FERC will undertake to review the Quoddy Bay LNG project).
. At oral argument, Plaintiffs suggested that even during the site investigation period, Quoddy Bay was granted a right to exclude. Our analysis, however, does not depend on this allegation.
. The lease approval itself is a brief, one-sentence form attached at the end of the lease. It was signed by the Director of the Eastern Region of the BIA, Franklin Keel, and stated simply, "Approved: Secretary of the Interior.”
. The National Environmental Policy Act of 1969, 42 U.S.C. § 4321 et seq., requires federal agencies to assess environmental impact before taking any "actionf] significantly affecting the quality of the human environment.” 42 U.S.C. § 4332(2)(C). A detailed EIS is not required, however, for “categories] of actions which do not individually or cumulatively have a significant effect on the human environment and which have been found to have no such effect in procedures adopted by a Federal agency in implementa *25 tion of these regulations.” 40 C.F.R. 1508.4. The BIA has adopted procedures governing which of its activities constitute such "Categorical Exclusions,” and in this case, using the Checklist, determined that the Quoddy Bay Lease fell within its exclusion for "data gathering activities.” See National Environmental Policy Act; Revised Implementing Procedures, 53 Fed.Reg. 10,439, 10,442 (Mar. 31, 1988).
. The procedural history of this case is explained in more detail in the district court’s opinion.
See Nulankeyutmonen Nkihtaqmikon
v.
Impson,
. The APA claim was dismissed because, without the other statutory claims, NN had no private right of action.
Nulankeyutmonen Nkihtaqmikon,
. In particular, the argument that the BIA will participate in the FERC permitting process — and therefore that the BIA will have other chances to prevent the construction of die LNG terminal — properly goes to the merits of the case, i.e., whether the BIA has fulfilled its duties.
. For example, Count One of Plaintiffs' Second Amended Complaint alleges, inter alia, that "[t]he BIA breached its duty under NEPA by issuing a Categorical Exclusion for the lease approval because the effects of the ground lease constitute extraordinary circumstances that preclude it from categorical exemption under Appendix 2 of the BIA’s Departmental Manual.” Count Three alleges that "[t]he BIA breached its duty under section 470a(d)(6) of the NHPA by failing to consult with the tribe before approving the ground lease on a site of religious and cultural significance to the Passamaquoddy Tribe and which is eligible for listing on the Registry of Historic Places.” Plaintiffs’ ESA complaint alleges, inter alia, that the BIA failed to consult with the National Marine Fisheries Service as to the impacts of the lease on certain whales.
. While the BIA frames this argument as one involving causation, it is actually a question of imminence under the injury-in-fact analysis. As stated above, and shown by the Lujan example, immediacy is not of particular concern here.
. NN’s organizational standing is clear: the interests asserted and evaluated are those of the individual members,
see Dubois,
. Neither party raises constitutional standing concerns on appeal, and we see no obstacle to constitutional standing for the same reasons discussed above with respect to standing under NEPA, NHPA, and ESA.
. The BIA suggests that we not consider Plaintiffs’ argument that the zone of interests protected by the Leasing Act encompasses Plaintiffs’ environmental concerns, because they make this argument for the first time on appeal. Plaintiffs, however, point to specific language in their complaint and in the transcript that shows they raised the issue before the district court. Additionally, though not dispositive, the BIA is hardly in an equitable position to make such a claim considering its shift in position on crucial issues from the stance it took before the district court as compared to that before us.
. Contrary to the BIA’s assertions, we cannot — and will not — affirm the dismissal at this stage of the proceedings on the ground that the BIA complied with the Leasing Act. Further, it is irrelevant to our analysis whether "[t]he true gravamen of [Plaintiffs’] complaint apparently lies with the Tribal Resolution authorizing the lease.” Plaintiffs' have chosen their battleground and their opponent, and our review for standing is limited to the allegations of injury asserted in this suit.
.The district court was unclear as to whether Plaintiffs intended to assert a Trust Obligation claim apart from the Leasing Act claim.
Nulankeyutmonen Nkihtaqmikon,
. The district court ruled that Plaintiffs’ claims were not ripe "because the lease approval process is not yet complete."
Nulankeyutmonen Nkihtaqmikon,
