39 Wash. 244 | Wash. | 1905
This is an action upon a contractor’s bond. The amended complaint avers that the defendant Heinzerling entered into a written contract to construct for the plaintiff a warehouse, in-accordance with plans and specifications attached to the contract.' The specifications provided that the building should rest upon forty-five concrete piers, and the latter were also to be constructed by said defendant. It was provided that, in constructing each pier, four piles should be driven to a good foundation, and cut off from one to three feet above ground, the earth to be excavated around the piling .one foot below the surface, and a casing built around the same made of two-inch lumber, the casing having a dimension of five feet by five feet at the base and three feet by three feet at the top, inside. It was also required that the casing should be filled with concrete made with five parts sand and gravel and one part good Portland cement, said concrete to be well tamped.
The plaintiff alleges that the contractor did not build the piers in accordance with the specifications, in that he failed to use a sufficient quantity of cement, and that he did not use a good quality of Portland cement; that he failed to properly tamp and place the concrete; that he threw the concrete, when mixed, into deep water so that the cement became separated from the sand and gravel; that, in consequence of such defaults on the part of the contractor, the piers are now falling down, and the warehouse is falling by reason thereof, and has become unsafe and useless. It is alleged that the contractor is financially unable to rebuild said piers and make said building such as is contemplated by the contract; that he has refused to do so; and that plaintiff will be obliged to reconstruct the same at an expense of $2,500, for which amount judgment is demanded. A supplemental complaint filed since the commencement of the action alleges that the piers have been rebuilt, and demands $1,500 damages in addition to the demand in the principal complaint.
Appellant’s counsel asked a witness who it was who drew the specifications for the piers. The respondents objected, and the court sustained the objection. This is assigned as error. It was claimed by the respondents that the tamping of the concrete under water had caused the defect in the piers, and expert witnesses testified to that effect. It was also claimed that the contractor was required by the contract to tamp it, inasmuch as the specifications contained the following: '“Said concrete to be well tamped.” Appellant desired to show that the specifications were drawn by the contractor himself, but we are unable to see that such fact became material inasmuch as no fraud or overreaching was charged by appellant. The terms of the con
Error is urged upon the court’s rulings in not sustaining objections to the testimony concerning the orders and directions about the work, given by the miller Robertson. It was testified that Robertson was about the work daily, that he gave many directions concerning the work, and frequently ordered further tamping of the concrete after the contractor had ceased to tamp it. It is urged that this testimony was objectionable, for the reason that the agency of Robertson for appellant could not be established by his own acts and declarations. Standing alone, they were doubtless insufficient, but it appeared that he was often about the work in company with the secretary of appellant corporation, the officer who had executed the contract for the appellant, that this officer frequently heard Robertson giving the directions concerning tamping and other things, and that he at no time intimated to the contractor that Robertson was not authorized to so direct. Under such circumstances, the question as to Robertson’s authority and agency was for the jury, and the objections were properly overruled.
A number of assignments of error relate to instructions given, and to the refusal to give others requested by ap^ pellant. It is urged that it was error to refuse to instruct the jury to return a verdict for appellant in the full sum demanded. We think such an instruction would have been erroneous, in view of the evidence. There was evidence to the effect that the piers were weakened by too much knocking and jarring, which ruptured the crystals of the cement while they were becoming set in the salt water; that ■ the concrete was jarred by the tamping; that the contract called for the tamping; and that appellant not only observed the tamping and approved thereof, but insisted upon even more of it than the contractor was disposed to give; that appellant
Appellant further insists that it was error to refuse to give the following instruction:
“Under the contract and specifications, it was the duty of Heinzerling to know how to tamp the concrete ip boxes for the piers, and if the jury finds that it was faulty workmanship to tamp the concrete in the water, and that it was so tamped, and that such tamping caused the defects in the piers, it was the negligence and unskillfulness of Heinzerling which caused the defects in the piers, and plaintiff is entitled to recover.”
In view of the terms of the contract, which required tamping, we think the instruction asked was erroneous.
The following instruction was given:
“Now, with regard to the charge of improper tamping: As I have said, if the contractor did what he was required to do by the contract, he would not be liable for any damage because of a fault in the contract itself, and if he was required by the contract to tamp this concrete, and if the fall of the wharf was occasioned by the tamping of the concrete, the plaintiff could not recover, because under the contract he was required to tamp the concrete; but it is for you to say, under, the evidence, whether in tamping the concrete he did it in the way that it should have been done, whether there was any defect in the tamping of this concrete, and if you should find from the evidence that he did not tamp the concrete as it should have been done, or did not put it in place- as it should have been put there, or did not mix it in the proper proportions, or did not use a sufficient quantity, and if you should find that on any of these accounts or for any of these reasons, the wharf fell, and the plaintiff was put to the expense of reconstructing it, then you would find for the plaintiff to the extent of $4,000, if*250 you should be satisfied that the plaintiff incurred that expense in that way.”
We think the above instruction comprehensively and correctly covered the subject of tamping, under the issues and evidence.
The complaint made under the fourth and fifth assignments of error we shall not. discuss, inasmuch as we think the court> in general effect, gave instructions covering the same points contained in the appellant’s requests; and we think the same is true of the sixth, fifteenth, and seventeenth assignments, to the extent, at least, that no prejudicial error is involved therein.
Error’ is urged upon the refusal to give the following instruction:
“Any knowledge or information which the witness Robertson, the miller and, employee of the plaintiff company, may have gained as to the methods employed by the defendani Heinzerling in the construction of ' the forty-five concrete piers in question was not the knowledge of the plaintiff company, and cannot in any manner bind or control the plaintiff corporation, and the jury are instructed to disregard and not consider any such Imowledge or information of said witness Robertson.”
We have already said that the question of Robertson’s agency was, under the evidence, for the jury. The above requested instruction would have taken that question from the jury, and it was therefore properly refused.
We think the instruction criticized under the eighth assignment of error was not erroneous. It stated, in effect, that the fact that the miller of appellant company was around the work and saw how it was being done, and the fact that he may have undertaken to direct how it should be done, would not charge the - mill company with notice, unless the miller was authorized by the company to look after the work, and was held out as its agent for that purpose, which latter fact the jury were to determine from the evidence.
Complaint is made that some of the instructions were misleading and confusing in their terms. We do not find them so, and we believe the instructions, as a whole, fairly covered the law of the case, under the issues and evidence.
We think it was not error to deny the motion for a new trial. The fact was fully submitted to the jury whether the defect in the piers was due to any violation of the terms of the contract on the part of the contractor. The verdict established that it was not caused by a breach of the contract, and we shall not disturb it. The judgment is affirmed.