Norwalk Door Closer Co. v. Eagle Lock & Screw Co.Norwalk Door Closer Co. v. Eagle Lock & Screw Co.
In this аction, the plaintiff, hereinafter called Norwalk, is seeking to recover $100,000 as liquidated damages for the breach of a written contract by the defendant, hereinafter called Eagle, and an additional sum for Eagle’s failure to deliver goods which had been ordered undеr the contract. Claims for consequential damages and for loss of profits and good will are no longer in issue. Eagle counterclaimed to recover $63,574.33 for goods delivered to Norwalk. Norwalk does not dispute this indebtedness. The trial court denied recovery of the $100,000 on the ground that it was a penalty, but it awarded damages to Norwalk of $1687.19 for Eagle’s failure to deliver goods ordered under the contract. The court found Eagle entitled to recover $63,574.34 on its counterclaim. This admitted indebtedness is, however, incorrectly stated in the judgment to be $61,887.15. Norwalk has appealed from the judgment, and Eagle has filed a cross appeal.
When the contract was made, Sereno L. Mastorgi was Eagle’s president and general manager. In paragraph 13 of the contract, Norwalk reserved the option to terminate the agreement on thirty days’ notice tо Eagle in the event that Mastorgi should, for any reason, cease to be Eagle’s general manager. In that event, Norwalk agreed to pay Eagle specified amounts in full liquidation of all damages.
Paragraph 14 of the contract presents the principal issue betwеen the parties. That paragraph reads as follows: “In the event that Eagle shall for any reason desire to terminate this agreement, it shall give not less than ninety (90) days’ notice of such intention to terminate unless such
The parties operated under thе contract until September 29, 1960, when Eagle notified Norwalk that the agreement would terminate on December 31, 1960, and that it would complete all orders received from Norwalk prior to November 15, 1960. In October, 1960, Eagle sold all its assets to another corporation. On December 16, 1960, Norwalk notified Eagle of its election to treat the notice of
The trial court concluded that paragraph 14 of the contract, calling for payment of $100,000, was not a provision for liquidated damages but was a penalty and consequently was unenforceable. This conclusion is attacked by Norwalk in its appeal. Incidental to this claim is the issue as to pleading and burden of proof.
The complaint did not allege the contract in full or incorporate it by reference. It alleged that paragraph 14 of the contract provided “that in the event Defendant desired to terminate the agreement for any reason, or if Defеndant liquidated its business or ceased to occupy its then plant in Terryville, Connecticut, or if Defendant for any reason ceased or was unwilling or unable to manufacture and ship door closers as provided in said agreement, then, in any such event, at the option of Plaintiff, thе said agreement could be deemed by Plaintiff as breached and terminated by Defendant, and Defendant would thereupon be required to pay to Plaintiff the sum of $100,000.00.” Eagle in its answer admits the existence of a contract “but refers to said contract for a correct statеment of the terms thereof.” Eagle did not file a special
It is settled law that a contract provision which imposes a penalty for a breach of the contract is contrary to public policy and is invalid, but a contractual provision which fixes liquidated damages for a breach of the contraсt is enforceable if it satisfies certain conditions.
Berger
v.
Shanahan,
Under our rules, illegality not apparent on the face of the pleadings, must be specially pleaded. Practice Book § 120. Prom the allegation in the complaint, it did not appear that a recovery by Norwalk of $100,000 would necessarily be illegal. Consequently, any facts claimed to establish illegality should have been pleaded as a special defense.
Personal Finance Co.
v.
Lyons,
Inasmuch as Norwalk’s claims of law make clear that the issue was actuаlly before the trial court regardless of the formal state of the pleadings, the issue assumes a secondary importance. Under the circumstances of this case, Norwalk stands to gain nothing by the claim that illegality was not affirmatively pleaded because it is unnecessаry for us to decide the correctness of the court’s conclusion that the contract imposed a penalty for its breach.
The court has found that the corporation which acquired Eagle’s assets immediately formed a subsidiary named Eagle Lock Company, which occupies the same premises and employs the same
In
Miller
v.
Macfarlane,
The principle is based on justice and fairness. “The probable injury that the parties had reason to foresee is a fact that largely determines the question whether they made a genuine pre-estimate of that injury; but the justice and equity of еnforcement depend also upon the amount of injury that has actually occurred.” 5 Corbin, Contracts § 1063. For a collection of cases on the general subject see the annotation in
The circumstances which the parties might reasonably foresee at the time of making a contract could, in any given case, be vastly different from the circumstances which actually exist when a court is called upon to enforce the contract. It is not the function of the court to determine by hindsight the reasonableness of the expectаtion of the parties at the time the contract was made, but it is the function of the court at the time of enforcement to do justice. In the ordinary contract action the court determines the just damages from evidence offered. In a valid contract for liquidated dаmages, the parties are permitted, in order to avoid the uncertainties and time-consuming effort involved, to estimate in advance the reasonably probable foreseeable damages which would arise in the event of a default. Implicit in the transaction is the premise that the sum agreed upon will be within the fair range of those just damages which would be called for and provable had the parties resorted to proof. Consequently, if the damage envisioned by the parties never occurs, the whole premise for their agreed estimate vanishes, and, even if the contract was to be construed as one for liquidated damages rather than one for a penalty, neither justice nor the intent of the parties is served by enforcement.
Under the facts of the present case, where the court has found that Norwalk is continuing its business without having been harmed, and substantially as it did before the breach, neither justice nor reason permit it to recover $100,000 in damages. This is so whether the contract provided for liquidated damages or for a penalty.
The court rendered judgment for Norwalk on the complaint for $1687.19. As already indicated, this represented damages for failure to deliver items ordered between the date of the notice of intention to terminate and the date of the terminаtion of the contract. The finding is completely silent as to the basis on which this figure was determined, and the omission is attacked by Eagle’s cross appeal. Consequently, the judgment for Norwalk on the complaint cannot stand.
There is error only in the award of damages to the рlaintiff on the complaint and in the amount of damages awarded the defendant on the counterclaim; the judgment is set aside and the case is remanded with direction to render judgment for the defendant on the complaint and for the defendant to recover of the plaintiff $63,574.34 on the counterclaim.
In this opinion the other judges concurred.
Notes
No issue is made of the timeliness of this notice.
See
Chisholm
v.
Reitler,