delivered the opinion of the court:
Third-party plaintiff, Lipowski & Associates, Inc. (Lipowski), appeals from the dismissal of its action to foreclose on a mechanic’s lien and to recover for breach of contract. On appeal, Lipowski argues that its failure to submit a sworn contractor’s statement does not preclude it from pursuing a breach of contract action. We reverse and remand.
This litigation arises out of the construction of improvements to the home of Casimir J. Komperda and Dawn M. Komperda. The Komperdas hired Lipowski to provide architectural and construction management services on the project. Plaintiff, Northwest Millwork Company (Northwest), furnished doors, trim, and hardware for the project. On June 8, 2001, Northwest sued the Komperdas; Andrew Lipowski, who was Lipowski’s principal; and St. Paul Federal Bank for Savings/Charter One Bank (St. Paul). The complaint alleged that on May 21, 1999, Northwest and Andrew Lipowski agreed that Northwest would furnish lumber materials for the project. Northwest was to receive $8,096.22 for its services. Northwest completed its work on June 17, 1999. It sought to foreclose on its mechanic’s hen, damages for breach of contract, and damages under section 28 of the Mechanics Lien Act (Act) (770 ILCS 60/28 (West 2000)). The contract claim was directed against Andrew Lipowski only, and the remaining claims were directed against all defendants.
Lipowski filed a third-party claim against the Komperdas, St. Paul, and unknown owners and lien claimants. Count I of Lipowski’s third-party complaint sought to foreclose on its mechanic’s lien, and count II sought damages for breach of contract. Lipowski alleged that it and the Komperdas entered into an oral agreement on or about September 26, 1999. For the architectural services, Lipowski’s compensation would equal 8% of the construction costs, and, for the construction management services, Lipowski’s compensation would equal 12% of the construction costs. On July 13, 1999, Lipowski completed its obligations under the contract. At that time, $48,425.61 became due. Despite Lipowski’s repeated requests, the Komperdas never paid the balance. On September 23, 1999, Lipowski served a notice of a mechanic’s hen claim and on October 21, 1999, filed a mechanic’s hen claim with the Lake County recorder of deeds.
Lipowski attached to its complaint a billing statement dated September 17, 1999. According to the statement, the base construction cost was $77,165.76. The construction management fee was $9,259.85, and the architectural fee was $6,173.30. Lipowski charged an additional architectural fee of $7,426.70. Thus, the total bill was $100,025.61. The statement reflects that the Komperdas paid $50,000 to Lipowski and $1,600 to a window supplier, thus reducing the total amount due to $48,425.61.
Relying on section 2 — 619(a)(9) of the Code of Civil Procedure (Code) (735 ILCS 5/2 — 619(a)(9) (West 2000)), the Komperdas moved to dismiss the third-party claim. Citing this court’s decisions in Malesa v. Royal Harbour Management Corp.,
Lipowski responded that it was not a general contractor but instead an architect and construction manager. Therefore, it was not required to submit a sworn statement under section 5.
On September 18, 2001, the trial court dismissed with prejudice Lipowski’s third-party claim. Also, the court dismissed with prejudice Northwest’s mechanic’s hen claim as to all defendants and dismissed with prejudice the section 28 damages claim as to the Komperdas only.
On September 20, 2001, Lipowski moved to reconsider. It urged the trial court to follow National Wrecking Co. v. Midwest Terminal Corp.,
A motion to dismiss pursuant to section 2 — 619 of the Code admits the legal sufficiency of the complaint and all well-pleaded facts and the inferences therefrom but asserts an affirmative matter that avoids or defeats the claim. Avakian v. Chulengarian,
The affirmative matter the Komperdas have raised is that Lipowski failed to tender them a contractor’s affidavit under section 5 of the Act. The purpose of the Act is to permit a lien upon premises where a benefit has been received by the owner and the value or condition of the property has been increased or improved by the furnishing of labor and materials. R.W. Dunteman Co. v. C/G Enterprises, Inc.,
Section 5 of the Act provides:
“It shall be the duty of the contractor to give the owner, and the duty of the owner to require of the contractor, before the owner or his agent, architect, or superintendent shall pay or cause to be paid to the contractor or to his order any moneys or other consideration due or to become due to the contractor, or make or cause to be made to the contractor any advancement of any moneys or any other consideration, a statement in writing, under oath or verified by affidavit, of the names and addresses of all parties furnishing materials and labor and of the amounts due or to become due to each.” 770 ILCS 60/5 (West 2000).
The Act becomes a part of every construction contract between an owner and a contractor. Abbott Electrical Construction Co. v. Ladin,
In Abbott Electrical,
Malesa followed Ambrose. The contractor in Malesa argued that, because the owner has a concurrent duty under section 5 to request a sworn statement, a contractor may maintain a breach of contract action where the owner fails to request the statement. The Malesa court rejected the argument. The court explained that the owner’s duty is to refrain from paying the contractor until the owner receives the sworn statement. This is a duty owed to the subcontractors, and, under section 32 of the Act, a breach of the duty can lead to liability to the subcontractors. The court observed that section 5 does not explicitly require the owner to request the statement and does not condition the contractor’s duty to provide the statement on receiving such a request. Malesa,
In National Wrecking, the Appellate Court, First District, declined to follow Ambrose and Malesa. First, the court observed that Ambrose and Malesa conflicted with its decision in Hall v. Harris,
The Fifth District also has disagreed with Malesa in its decision in Prior. Prior involved only a mechanic’s lien claim. Holding that the contractor’s failure to provide a sworn statement did not bar the claim, the court observed that the doctrine of strict construction never was meant to be a pitfall to the unwary and that owners should not be able to rely on a technicality to defeat an otherwise valid lien. Prior,
Lipowski urges us to adopt National Wrecking and Prior. Also, Lipowski insists that the Ambrose court’s concern about the risk to the owner simply is not present here. Initially, the Komperdas respond that Lipowski has waived these arguments because it did not properly raise them below. They stress that Lipowski did not raise National Wrecking and Prior until it moved to reconsider, never cited Abbott Electrical, and never attempted to distinguish Ambrose.
Lipowski has not waived the arguments it raises on appeal. In its motion to reconsider, Lipowski argued generally that its failure to provide a sworn statement did not preclude a breach of contract action. Where, as here, Lipowski afforded the trial court an opportunity to consider the issue now raised on appeal, application of the waiver rule would not further the reason for the rule. See People v. McKay,
We conclude that Ambrose and Malesa are distinguishable and therefore do not control here. The Ambrose court noted that the owners’ “refusal to make the final payment in the absence of a contractor’s statement was justified in order to protect against potential subcontractors’ hen claims.” Ambrose,
“Sub-contractors *** may at any time after making his or her contract with the contractor, and shall within 90 days after the completion thereof *** cause a written notice of his or her claim and the amount due or to become due thereunder, to be sent *** to or personally served on the owner of record or his agent or architect ***.” 770 ILCS 60/24 (West 2000).
Serving the 90-day notice is a condition precedent to a mechanic’s lien claim. Caruso v. Kafka,
Moreover, in Ambrose, the contractor abandoned the work after the owners refused to make the final payment. Likewise, in Malesa, the project never was completed. Here, Lipowski alleged that it completed its obligations under the contract. It is significant that Ambrose and the case on which the Ambrose court relied, Deerfield Electric Co. v. Herbert W. Jaeger & Associates, Inc.,
Under the facts developed so far, it is impossible to say as a matter of law that Lipowski’s failure to provide a sworn contractor’s statement prevents it from pursuing a breach of contract claim. Also, the record contains no evidence that the Komperdas requested a sworn statement. Under Abbot Electrical, the failure to provide the statement does not defeat Lipowski’s mechanic’s lien claim. Accordingly, we conclude that the trial court erred in dismissing Lipowski’s third-party claim.
We reverse the judgment of the circuit court of Lake County and remand the cause for further proceedings on Lipowski’s third-party complaint.
Reversed and remanded.
HUTCHINSON, EJ., and CALLUM, J., concur.
