OPINION
Plaintiff, Northrop Grumman Computing Systems, Inc. (Northrop), brings this action seeking damages for the alleged breach of an agreement with the Department of Homeland Security, Bureau of Immigration and Customs Enforcement.
I. BACKGROUND
On September 24, 2004, ICE awarded Delivery Order COW-4-D-1025 (Delivery Order) to Northrop pursuant to a preexisting contract between ICE and plaintiff — Contract No. NAS5-01143. According to the Delivery Order, plaintiff was to lease the Oakley software to ICE and perform specific support services for a one-year base period in return for payment of $900,000, with three one-year options at $800,186 per option year — for a total contract price of $3,597,558 if all three options were exercised. On September 28, 2004, ICE provided plaintiff with an “essential use statement” that described the intended use of the Oakley software and was designed to facilitate third-party funding for the Oakley software. From September 30, 2004, to October 18, 2004, ICE executed three modifications to the Delivery Order, adding, inter alia, a first priority clause, a best efforts clause, and a nonsubstitution clause. On October 13, 2004, plaintiff delivered the Oakley software to defendant and was paid $900,000.
To finance the agreement, Northrop relied on ESCgov, with whom Northrop had a preexisting Purchase and Assignment Agreement. Pursuant to this preexisting agreement, on October 22, 2004, ESCgov entered into Equipment Schedule No. 1, in which it agreed to pay Northrop $3,296,093 in exchange for Northrop’s assignment to ESCgov of any payments it received under the Delivery Order. On November 19, 2004, ESCgov assigned its rights under Equipment Schedule No. 1 to Citizens Leasing Corporation, n/k/a RBS Citizens, N.A. (Citizens), in exchange for $3,325,252.16. Neither plaintiff, ESCgov, nor Citizens ever notified ICE of these assignments.
On September 30, 2005, ICE informed plaintiff that it would not exercise the first one-year option due to a lack of funds. On September 21, 2006, Northrop filed a “claim” with the contracting officer pursuant to the Contract Disputes Act of 1978 (the CDA), 41 U.S.C. § 601, et seq., “to recover damages resulting from the Government’s breach of the provisions of the [Delivery Order] by failing to use best efforts to seek and utilize available funding from all sources, by failing to reserve funds from the annual budget on a first priority designation, and by replacing the software with another system performing similar or comparable functions.” The claim requested damages of $2,697,558, because defendant’s breach of contract entitled “a contractor to be placed in as good a position as it would have had the breach not been committed by the Government.” Alternatively, “if the Government’s breaches of the Contract are found to constitute а Termination for Convenience, the amount of ... damages owed by the Government would be $2,674,032.80.” A Northrop official certified that the claim was “made in good faith,” “accurate and complete” and stated an accurate damages amount for which defendant was liable. The claim did not mention ESCgov, Citizens or any of the aforementioned assignments. On December 29, 2006, the contracting officer denied this claim.
On August 20, 2007, plaintiff filed a complaint in this court, asserting that defendant breached the Delivery Order by failing to seek funding and exercise the options. The complaint averred that, as a result of this breach, “Northrop Grumman is entitled to recover its damages as described in the contract, including the payments not made under the Contract in the amount of $2,697,558.00, plus interest.” On May 20, 2010, the parties’ cross-motions for summary judgment were denied, and after supplemental discovery, trial was scheduled to begin on
II. DISCUSSION
Deciding a motion to dismiss “starts with the complaint, which must be well-pleaded in that it must state the necessary elements of the plaintiffs claim, independent of any defense that may be interposed.” Holley v. United States,
The United States “is immune from suit save as it consents to be sued ... and the terms of its consent to be sued in any court define that court’s jurisdiction to entertain the suit.” United States v. Sherwood,
One such waiver statute, the CDA, “was enacted to ‘provide[] a fair, balanced, and comprehensive statutory system of legal and administrative remedies in resolving government contract claims.’ ” Winter v. Floor-Pro, Inc.,
In the case sub judice, on September 21, 2006, Northrop sent the contracting officer a letter that it asserts was a “claim” under the CDA. Defendant contends otherwise. It argues that this claim was deficient because it failed to reveal that Northrop had assigned its rights under the contract to ESCgov, which, in turn, had assigned those rights to Citizens. Defendant asseverates that Northrop should have revealed that it was seeking damages on behalf of a second-level assignee. Indeed, defendant questions whether, after the assignments, Northrop remained the proper party to file such a claim under the contract.
Turning to the latter question first, the court is persuaded that Northrop was the proper party to file the claim here. Northrop relies heavily, in this regard, upon Beaconwear Clothing Co. v. United States,
Beaconwear thus remains the only party which has a legal claim to the amount due under the contract. It alone signed the contract; all the arrangements and adjustments were negotiated and executed solely in its name and all administrative appeals were prosecuted in its name. It was the prime contractor on [the] contract [ ] and has been held responsible by defendant for performance at all times.
Id. at 591. But for a counterclaim, the court was prepared to allow Beaconwear to recover on its original contract claim. Id.
There is little doubt that, as in Beacon-wear, Northrop’s assignment here ran afoul of 31 U.S.C. § 3727. While that section allows for assignments to a “financing institution of money due or to become due under a contract,” 31 U.S.C. § 3727(e), and ESCgov arguably qualifies as such an institution, Northrop admits that it did not notify defendant of its assignment, as is required by the statute. See 31 U.S.C. § 3727(c)(3); Uniroyal, Inc. v. United States,
But did Northrop’s letter supply the contracting officer with “adequate notice of the basis” for the claim, as required by the CDA? The answer to this question depends upon a “logical, common sense analysis” of the facts and circumstances of this ease. Transamerica Ins. Corp. v. United States,
Before turning to this analysis, it is well to note the four purposes that the “adequate notice” requirement serves within the broader context of the CDA: First, compliance with the requirement permits the contracting officer to give meaningful, reasoned consideration to thе claim, on a case-by-case basis. See PAE GmbH Planning & Constr., 92-2 B.C.A. ¶ 24,920 (1992).
Several of these issues involve the validity of the assignments, as against the United States, under the Anti-Assignment Act. While Northrop now admits that the assignments were invalid as against the United States, it did not always have this view. Indeed, until it briefed the current motion, Northrop apparently believed that the assignments were valid and that it was sponsoring a claim against the United States on behalf of the second-level assignee, Citizens. But, remarkably, it did not reveal this sponsorship — or even the existence of the assignments — to the contracting officer when it filed its claim. Per contra. It appears that Northrop’s claim was drafted carefully to avoid mentioning these matters — consistently framing its various requests in terms of what the government was obliged to pаy, rather than what Northrop (in reality, Citizens) was owed.
By failing to reveal the assignments, Northrop also prevented the contracting officer from considering important issues involving damages. Under the so-called Severin doctrine, Northrop was entitled to recover damages under its claim only if it remained financially obligated to its assignee upon defendant’s breach. In Severin v. United States,
Severin holds that a prime contractor cannot recover on behalf of a subcontractor unless the former has reimbursed the latter or is liable to make a reimbursement. “These are the only ways in which the damages of the subcontractor can become, in turn, the damages of the prime contractor, for which recovery may be had against thе Government.” J.L. Simmons Co. v. United States,
Indeed, although the Severin doctrine is most closely identified with eases involving subcontracts, it has been applied in other factual contexts, including those involving assignments. The latter was the case in Keydata Corp. v. United States,
Strictly speaking, the question here, however, is not whether the Severin doctrine requires dismissal of this action. This сourt thus need not decide whether the assignment documents here exculpated Northrop from any liability. The court must rather decide whether Northrop should have alerted the contracting officer to the assignments, so that the latter could have considered, ab initio, whether Northrop was injured by defendant’s actions. And everything points to the conclusion that Northrop should have afforded the contracting officer this opportunity. Its failure to do so is particularly troubling given that the Severin doctrine is an affirmative defense that must be raised by defendant. Thus, defendant bears the burden of establishing that the claimant has been completely exonerated against claims brought by an assignee. See W.G. Yates & Sons Constr. Co.,
In sum, the court finds that Northrop’s putativе claim did not “contain ‘a clear and unequivocal statement that [gave] the contracting officer adequate notice of the basis’ ” of its claim. M. Maropakis Carpentry,
This is not to say that Northrop is guilty of any artfulness here. Nor is to say that its claim needed to discuss any of the legal issues described above. The deci-sional law does not require this аnd, instead, provides that a contractor may raise different legal theories for recovery than those disclosed in the claim provided “they arise from the same operative facts [and] claim essentially the same relief.” Scott Timber Co.,
III. CONCLUSION
Based on the foregoing, the court GRANTS defendant’s motion to dismiss the complaint under RCFC 12(b)(1).
IT IS SO ORDERED.
Notes
. The Homeland Security Act of 2002, Pub.L. No. 107-296, 116 Stat. 2135 (Nov. 25, 2002), created the Department of Homeland Security (DHS). The Act also consolidated the United States Immigration and Naturalization Service and the United States Customs Service into a newly-formed Bureau of Immigration and Customs Enforcement, which is now known as United States Immigration and Customs Enforcement (ICE).
. These facts are largely drawn from plaintiff’s complaint, and, for purposes of this motion, are assumed to be correct. See Bell Atl. Corp. v. Twombly,
. Section 3727(b) of Title 31, antecedents of which date back to 1846, states that the assignment of a claim against the United States "may be made only after a claim is allowed, the аmount of the claim is decided, and a warrant for payment of the claim has been issued.” In a similar vein, another provision of the Anti-Assignment Act, 41 U.S.C. § 15(a), provides that "[n]o contract or order, or any interest therein, shall be transferred by the party to whom such contract or order is given to any other party, and any such transfer shall cause the annulment of the contract or order transferred, so far as the United States is concerned.” See Fireman’s Fund Ins. Co. v. England,
.See Sun Cal, Inc. v. United States,
Defendant attempts to parry plaintiff’s reliance on Beaconwear by citing First Hartford Corp. Pension Plan & Trust v. United States,
. See also ECC Int'l Corp. v. United States,
. The CDA requires, for сlaims in excess of $100,000, that the contractor—
certify that the claim is made in good faith, that the supporting data are accurate and complete to the best of his knowledge and belief, that the amount requested accurately reflects the contract adjustment for which the contractor believes the government is liable, and that the certifier is duly authorized to certify the claim on behalf of the contractor.
41 U.S.C. § 605(c)(1). This requirement is designed to "push contractors into being careful and reasonably precise in the submission of claims to the contracting officer.” Tecom, Inc. v. United States, 732 F.2d 935, 937 (Fed.Cir.1984); see also AAB Joint Venture v. United States,
. Thus, for example, Northrop’s claim stated: "The amount for which the Government is liable as a result of the breaches of the Contract identified above is $2,697,558.00, which represents the sum of the remaining unpaid lease payments for the full lease term of the Oakley software, including all option years.” In alternatively seeking termination for convenience damages, Northrop again shifted the focus to what defendant owes rather than discussing to whom damages are owed: "If the Government’s breaches of the Contract are found to constitute a Termination for Convenience, the amount of ... damages owed by the Government would be $2,674,032.80, which represents the present value of the remaining unpaid lease payments discounted at a rate of 3.01%, ...”
. In Severin the court relied on one of the "Gold Clause” cases, Nortz v. United States,
. See also W.G. Yates & Sons Constr. Co., Inc. v. Caldera,
. The limitations placed on the Severin doctrine over the years have little or nothing to do with its basic thrust, but rather focus on; (i) whether a given lawsuit is for breach of contract — if it is, Severin applies, and if it is not (as would be true in the case of an equitable adjustment), Severin does not apply, see E.R. Mitchell Constr. Co.,
. See also A.J. Hodges Indus., Inc. v. United States,
. Various commentators have summarized these issues at length. See 1A-6 Government Contracts: Law, Admin. & Proc. § 6.80 (2011); 3 Karen L. Manos, Government Contract Cost & Pricing § 89.4 (2d ed. 2011); McKenna Long & Aldridge and Ronald A. Kienlen, Government Contract Disputes §§ 17.15-17.16(2010); Steven W. Feldman, Government Contract Guidebook § 25.4 (4th ed. 2010); John Cibinic, Jr., Ralph C. Nash, Jr., & James F. Nagle, Administration of Gоvernment Contracts 675-78, 1247-52 (4th ed. 2006).
. As noted by the Federal Circuit in Reflectone, one of the purposes of the CDA was the "settlement of disputes at the administrative level, short of litigation."
. Plaintiff entirely misses this point in suggesting that that there is no problem here because “[t]his is not a case where the contracting officer approved a claim based on potentially inaccurate information,” but rather one in which “the contracting officer denied Northrop’s claim.” As with other questions involving jurisdiction and sovereign immunity, courts do not assess the adequacy of a document asserted to be a claim on a post hoc, "no harm, no foul” basis. (This is the CDA, after all, not the NBA). Nor does the law require less of a contractor who thinks its claim will be denied than of one who thinks its claim will be granted. See Wujick v. Dale & Dale, Inc.,
.The court is mystified as to why defendant did not file its motion to dismiss until a month before the trial scheduled in this case (since cancelled). The timing of this motion is all the more puzzling as plaintiff had previously identified, as fact witnesses, representatives from the two assignees involved and because attorneys for Citizens had attended some of the depositions in this case. While the court hesitantly accepts defendant’s explanation that it did not realize the need for the motion until preparing its pretrial submissions, it notes that other courts have, on occasion, sanctioned a party viewed as having brought belatedly a motion to dismiss for lаck of jurisdiction. See United States v. Ken Mar Assocs., Ltd.,
. The court intends to unseal and publish this opinion after June 23, 2011. On or before June 21, 2011, each party shall file proposed redac-tions to this opinion, with specific reasons therefor.
