115 N.W. 679 | N.D. | 1908
Plaintiff recovered a judgment in the court below condemning certain real property to its use for alleged railway purposes. From such judgment and from an order denying a motion for a new trial, this appeal is prosecuted.
The purpose for which said property is sought by the railway company, as alleged in its complaint, is to construct a reservoir for the collection and storage of surface water for use in operating its engines, and for the purpose of laying a pipe line therefrom to its railway track at Sterling. A mere easement for the latter purpose is all that is prayed for. The necessity for such use is duly alleged in the complaint. Defendants deny the existence of such necessity, and -they contend that the facts alleged and proven ao not entitle plaintiff to the relief demanded.
After the first witness was sworn, and before any testimony was offered, defendants objected to the introduction of any evidence, for the reason, as stated, that the complaint shows on its face
Such objection was overruled, and at the close of plaintiff’s evidence defendants moved to dismiss the action on the following grounds: (1) That the evidence introduced fails to establish the public necessity for the condemnation of the, premises described in the complaint, or any portion thereof. (2) The evidence fails to-show a public necessity for the condemnation of all the premises-described and sought to be condemned in this action. (3) The evidence affirmatively shows that no sufficient public necessity exists to warrant the condemnation of the premises or .any part thereof-(4) The evidence fails to show that the general public will receive any material benefit from the proposed condemnation. (5) The evidence shows that the object of the proposed condemnation is wholly for the private convenience and profit of the plaintiff. (•6) The evidence and the allegations of the complaint are too-vague and indefinite, especially in regard to the proposed 'easement for a pipe line mentioned in the evidence for the court to properly adjudge the condemnation asked. This motion was also overruled, as was a similar motion made at the close of all the evidence. A verdict having been returned in plaintiff’s favor, and judg
The first contention is that the trial court erred in overruling the first, fourth, sixth and eighth grounds of defendants’ objection to the jurisdiction of the court. It is argued by appellants’ counsel that the complaint fails to allege that the property is .sought to be taken for a public use, but that it discloses, on the contrary, that the use to which the property is sought to be subjected is a mere private use, namely, the private convenience of plaintiff in obtaining a supply of water at said station for its engines. The general propositions of law advanced by appellants’ counsel, that private property cannot be taken for other than public uses, and that the complaint must allege the necessity for the taking and that it is intended for a public use, are undoubtedly sound, and it only remains to apply such well-settled rules to the case before us. Is the use to which the property is sought to be applied a public use? If so, the foundation of appellants’ argument necessarily falls and with it the superstructure which he has reared. We think section 7575, Rev. Codes 1905, furnishes a complete answer to the above question. This-section provides: “Subject to the provisions of this chapter, the right of eminent domain may be exercised in behalf of the following public uses: * * * (4) Wharfs, docks, piers, chutes, booms, ferries, bridges, toll roads, by-roads, plank and turnpike roads, railroads. * * *” Here is an express legislative declaration that the taking of property for a railroad purpose is the taking for a public use. What better authority can be produced? Again, section 4266, Rev. Codes 1905, provides: “Every corporation formed under this article, and every railroad corporation authorized to construct, operate or maintain a railroad within this state shall have * * * the following powers: * * * (3) To acquire under the provisions of the chapter on eminent domain or by purchase all such real estate and other property as may be necessary for the construction, maintenance and operation of its railroads, and the station, depot grounds and other accommodations reasonably necessary to accomplish the object of its incorporation. * * * (4) To lay out its road, not exceeding 100 feet in width
It is next contended that the trial court committed error in overruling the first five grounds urged for a dismissal of the action. By these grounds of the motion the sufficiency of the evidence as to the necessity for the condemnation of the property and that it is sought to be taken for a public use is called in question. The gist of appellants’ contention in this respect is that the evidence shows that the taking is sought solely for the private convenience of plaintiff. An examination of the testimony has convinced us of the fallacy of such contention. Without reviewing the evidence in detail, it is sufficient to say that the undisputed testimony discloses the utter impracticability, if not the impossibility, of securing a suitable supply of water at or in the vicinity of Sterling, except in the manner proposed. In fact, the company has for years attempted by sinking wells to obtain such supply, but without avail, and it has been compelled to haul water in tank cars for such purpose from Bismarck to Sterling, a distance of twenty-five miles. The testimony discloses, and, indeed, it goes without saying, that such water trains are more or less an impediment to the efficient operation of the road by interference with the regular passenger and freight traffic over the same, a matter regarding which the interests of the public are materially concerned. The question, therefore, whether the plaintiff shall be restricted to its present methods of securing such needed water supply by hauling the same from Bismarck, or shall be permitted to carry out its proposed scheme of constructing a reservoir upon the land in question is of vital importance, not alone to the plaintiff railway company, but to the public as well. We are entirely clear that the proof is amply sufficient to show the urgent necessity for the condemnation of this property, and that the use for which it is sought to be appropriated is a public one. We call attention to the following recent authorities cited in respondent’s brief bearing upon the question of the necessity for the exercise of the right of eminent domain: Fallbrook v. Bradley, 164 U. S. 112, 17 Sup. Ct. 56, 41 L. Ed. 369; Clark v. Nash 198 U. S. 361, 25 Sup. Ct. 676, 49 L. Ed. 1085; State v. Centralia, etc., 42 Wash. 632, 85
It is next contended that it was error to condemn more than 37 acres out of the entire tract of 67 acres. The proof discloses that but 37 acres are proposed to be actually used for reservoir purposes. We think such contention is without merit. The plaintiffs civil engineer testified without contradiction that the entire tract was necessary, although not to be actually used for the storage of water, and an examination of the plat of the proposed reservoir serves to confirm the truth of his testimony. Much latitude is given to the corporation vested with the right of acquiring property by eminent domain in determining the extent of the property necessary to be taken. 10 Am. & Eng. Enc. Law, 1057, and cases cited. The courts are generally concluded by the good faith determination by the corporation or its officers of the necessity for taking any particular land. 2 Elliott on Railroads, § 954, and cases cited. It is, no doubt, true that, if the corporation is seeking to abuse the power delegated to it by asking to condemn more property than is reasonably necessary for the public use contemplated, the courts will interfere to prevent such taking. The testimony' in the record fails to show any such abuse in this case.
Appellants’ contention that the easement sought to be condemned for a pipe line is not described with sufficient certainty is not sustained by the record. The location of the proposed line is as definite as it is possible to make it. The exact point of its beginning and
The remaining assignments of error are sufficiently answered by what we have heretofore said.
Finding no error in the record, the judgment and order appealed from are affirmed. Respondent to recover its costs.