4 F. 688 | U.S. Circuit Court for the District of Minnesota | 1880
The complainant owns and has for years operated a line of railroad running across the state of Minnesota, constructed by virtue of authority conferred by certain acts of congress in this bill mentioned. The respondents are the owners of another line of railroad, now in process of construction under authority conferred by the state of Minnesota, as alleged in the answer. Each of these companies has power to acquire, by purchase or condemnation, the land required for right of way, depot, grounds, etc. The lines of the two railroads cross each other at a point near Fargo, in the state, the exact point of crossing being on the N. W. jr of section 9, township 139, range 8, in the county
At the time of the passage of the act of congress incorporating the complainant company, the land in question was public land; but at the time of the definite location of the line of the road under that act said land was owned by one J. S. Schreiber, who in the meantime had obtained a patent therefor, and from whom, through several mesne conveyances, the title passed to the respondents. No proceedings under the statute of Minnesota to recover damages for the right of way were ever instituted by said Schreiber, or any of his grantees, against the complainant. The respondents claim, under these circumstances, that they are the owners of the land and have the right to construct their railroad across it, and in doing so to cross the track of complainant, without making compensation. The complainant claims that it has a vested right and a valuable property in its right of way, which cannot be taken by the respondents without condemnation, under the statute, and payment of damages. Numerous questions arising upon the admitted facts have been discussed by counsel, the more important of which arc the following: First. Whether, under the charter of the complainant company, (act of congress of July 2, 1864,) that company acquired the right of way over all lands that were public at the time of its passage, or only over such as wore public at the time of the location of the line. Second. Whether the respondents, or those under whom they claim, had a complete title to the locus in quo at the time the complainant entered upon the same; and, third, if so, whether by permitting the complainant to take the right of way, and use the same for eight years, the respondents and their grantors lost their rights therein, and the complainant acquired a vested right. Fourth. Whether the respondents’ right to claim so much of the land as is embraced within complainant’s right of way is barred by section 7 of the aforesaid act of congress.
Besides these questions, which arise upon the admitted
1. Whatever doubts we may have upon other questions, we have none as to the absolute right of the respondents to build their railroad along the line specified in their charter, and to cross the line of the complainant at the point in controversy, upon paying the damages, if it be finally decided that complainant is entitled to damages, and without such payment, if, upon final hearing, it shall be so determined. The most that the complainant is entitled to is its damages; and if that be amply secured its rights are protected.
2. The case is peculiar in this: that the controversy is not as to the amount of damages, but as to the right of complainant to any damages. It is not a controversy that can be settled in a few days by tho appointment of a board of commissioners to assess the damages of complainant. As already suggested, the right of complainant to damages may depend upon a disputed question of fact, which cannot be determined until proofs are taken in the regular course of proceedings. Enough has already appeared in the case to satisfy us that a somewhat protracted litigation may precede the determination the question of damages. Already tho proceedings instituted in the state court for the purpose of having the complainant’s damages assessed have been interrupted and delayed by removal thereof into this court, where they are now pending. We will not anticipate, much less decide, any of the questions that may arise here in that proceeding. It ir enough for che present to say that the controversy which must precede an assessment and payment of damages in this case may be protracted.
3. The pubEb is interested in the construction of newlines of railway, which are indeed only improved highways. The policy of the law is to encourage and facilitate such construction. The statute of Minnesota provides for railroad crossings upon the theory that the public interest requires that these highways of commerce and travel should run in different directions over the state, and that no one line shall
But we are met with a question as to the power of this coúrt in a case of this character to adopt this course. It is not necessary to cite authority to show that to accept such a bond is within the ordinary powers of a court of chancery when proceeding according to the general principles of equity. It is a mode of proceeding, not only authorized by the general principles of equity jurisprudence, but it is in common use in courts of chancery, and especially in federal courts. In patent cases, for example, where it is supposed that an injunction to restrain the use of a patented article may operate injuriously, the complainant is protected by a bond to account for profits and pay damages instead of an injunction. It is only necessary to add that the federal courts of equity administer the same general principles in all cases and in every state, irrespective of local laws and state practice. If the court has jurisdiction to try and determine a case in equity, it must determine it according to these general principles, which are the same in every state. U. S. v. Howland, 4 Wheat. 115; Boyle v. Zacharie, 6 Pet. 658; Never v. Scott, 13 How. 268; Noonan v. Lee, 2 Black, 499.
It is not necessary, in view of these authorities, to decide what the power of a state court might be in a case of this character; but we see nothing in the statute which in our judgment ought to be construed to forbid a court of qhancery of the state to accept a bond under the circumstances disclosed by the record in this ease. It may be suggested that a bond cannot be substituted for payment of the damages. After the damages are assessed, 'the amount ascertained, tbip may be so. But the question here is, whether, in a case
It is said to dissolve this injunction and accept a bond instead would in effect authorize the respondents to commit a trespass, if not a crime, by laying their track across that of complainant. After this court has decided that upon giving-bond the respondents may extend their track across that of complainant, and after such bond shall have been given and approved, the right of the respondents to go on with the construction oi their line and to cross that of the complainant will be no longer, open to dispute or question. The case is before us; our jurisdiction of the parties and the subject-matter is complete.
The order will be that the injunction be dissolved upon the execution by the respondents to the complainant of a bond, with sureties to be approved by a judge of this court, in the sum of §5,000, conditioned that the respondents will pay all damages which may be awarded or adjudged in favor of complainant by reason of the construction of respondents’ line of railway across that of complainant.