NORTHERN CONTRACTING, INC., Plaintiff-Appellant, v. State of ILLINOIS, Illinois Department of Transportation, Kirk Brown, in his capacity as the Illinois Secretary of Transportation, et al., Defendants-Appellees.
No. 05-3981.
United States Court of Appeals, Seventh Circuit.
Argued April 13, 2006. Decided Jan. 8, 2007.
Rehearing and Rehearing En Banc Denied Feb. 7, 2007.
473 F.3d 715
Erik G. Light (argued), Office of the Attorney General, Kevin J. Burke, Hinshaw & Culbertson, Chicago, IL, PHB, Department of Justice, Civil Rights Division, Washington, DC, for Defendants-Appellees.
Charles E. Leggott, Dept. of Justice, Civil Rights Div., Appellate Section, Washington, DC, for Defendant, U.S. Dept. of Transp.
Before COFFEY, KANNE, and WILLIAMS, Circuit Judges.
I. BACKGROUND
Northern Contracting, Inc. (“NCI“) is a corporation that specializes in the construction of guardrails and fences for highway construction projects in Illinois. Generally, Illinois highway construction projects are awarded to a prime contractor on the basis of the lowest qualified bid, and then the prime contractor completes the project through the use of subcontractors who perform work such as the guardrails work that is the specialty of NCI. Most of NCI‘s revenue comes through successful bids as a subcontractor in state and local highway projects.
In 2000, NCI filed this action seeking declaratory and injunctive relief against the State of Illinois, the Illinois Department of Transportation (“IDOT“), the United States Department of Transportation (“USDOT“), the Secretary of IDOT, and IDOT‘s Bureau Chief of the Bureau of Small Business Enterprises, under
IDOT‘s DBE program is an outgrowth of federal policy. Federal law establishes a national goal that ten percent of federal highway funds are to be spent with DBEs. See Surface Transportation Assistance Act of 1982, Pub.L. No. 97-424, § 105(f), 96 Stat. 2097, 2100 (1983); see also Transportation Equity Act for the 21st Century (“TEA-21“), Pub.L. No. 105-178, § 1101(b)(1), 112 Stat. 107, 113 (1998). USDOT‘s implementing regulations for TEA-21 require all recipients of federal highway funds (such as IDOT) to have an approved DBE program. See
To qualify as a DBE, a company must be at least 51% controlled by “individuals who are both socially and economically disadvantaged.” See
A recipient of USDOT funds, such as IDOT, must take several steps in order to assure compliance with federal law pertaining to its required DBE program. First, the recipient must determine at the local level the figure that would constitute an appropriate DBE involvement goal, based on the relative availability of DBEs.
After a local goal is established, the recipient must submit its DBE plan to USDOT for approval, with explanations as to how it arrived at the goal.
At the implementation stage, a recipient is required to maximize the portion of its goal that can feasibly be achieved through race-neutral means.
IDOT typically adopts a new DBE plan each year. In preparing the Fiscal Year 2005 plan, IDOT retained National Economic Research Associates, Inc. (“NERA“), a consulting firm, to conduct a “custom census” in order to determine DBE availability. The NERA custom census was ultimately conducted by Dr. Jon Wainwright, an economist. Wainwright‘s analysis involved first identifying the relevant geographic market (Illinois) and the relevant product market (transportation infrastructure construction). Next, Wainwright surveyed Dun & Bradstreet‘s Marketplace, which is a comprehensive database of American businesses that identifies which businesses are minority or woman-owned. Wainwright supplemented this survey with IDOT‘s list of DBEs in Illinois. After arriving at this beginning list of DBEs, Wainwright corrected for errors in the data by surveying a random sample from the group; this survey led him to conclude that 22.8% of the firms listed as minority or woman-owned were actually owned by white men. He then surveyed all of the firms listed as not being minority or woman-owned; this survey led him to conclude that 14.5% were actually owned by minorities or women. In light of these two surveys, Wainwright adjusted his calculation of DBE availability and arrived at an overall relative availability of 22.77%. Wainwright then ran a regression analysis of Census Bureau data on earnings and business formation, and concluded that in the absence of discrimination, relative DBE availability would be 27.5%.
In arriving at its final goal for Fiscal Year 2005, along with the NERA report prepared by Wainwright, IDOT considered: (1) a study NERA conducted for
Though 22.77% was IDOT‘s overall goal, it determines individually whether each project should carry a DBE goal, based on the type of project and the availability of DBEs to perform the subcontracting that will be necessary. After the prime contractor is selected (on the basis of the lowest qualified bid), the prime contractor has seven days to report its DBE utilization plan to IDOT. IDOT awards waivers and reductions of the goal if a contractor later demonstrates that it made a good-faith effort but was incapable of meeting the goal.
At the outset of this litigation, NCI‘s complaint alleged that (1) TEA-21 and USDOT‘s regulations were outside of the scope of Congressional power; (2) these federal provisions violated the Fifth Amendment‘s guarantee of equal protection; (3) the Illinois statute implementing the federal DBE requirement violated
After discovery closed in 2003, all of the parties to this suit filed cross-motions for summary judgment. The district court granted only USDOT‘s motion for summary judgment, concluding that the federal government had demonstrated a compelling interest (ending effects of current and past discrimination in highway contracting market) and that TEA-21 and its implementing regulations were sufficiently narrowly tailored. The court concluded that a trial was necessary to determine whether IDOT‘s program was narrowly tailored.
At the bench trial, the State introduced the testimony of Wainwright, the testimony of owners of DBEs, and the testimony of an IDOT employee (Colette Holt) who explained the Fiscal Year 2005 DBE plan. NCI introduced the testimony of non-DBE prime contractors. The parties stipulated that: (1) the percentage of IDOT‘s total contracting expenditures that went to DBEs was 15.19% in 2003 and 18.05% in 2004; (2) the percentage of IDOT‘s contracting expenditures received by DBEs on contracts with DBE goals was 19% in 2003 and 17% in 2004; and (3) the percentage of contracting expenditures that went to DBEs on contracts with no DBE goals was 2% in 2003 and in 2004.
At the conclusion of the trial, Judge Pallmeyer found that IDOT‘s Fiscal Year 2005 DBE program was narrowly tailored to the compelling interest identified by the federal government—remedying the ef-
II. ANALYSIS
The only question that we must answer in this appeal is whether NCI can prove that IDOT‘s DBE program does not pass constitutional muster. Since the program involves racial classifications, we must employ strict scrutiny in making this determination.3 See Adarand Constructors, Inc. v. Pena, 515 U.S. 200, 235, 115 S.Ct. 2097, 132 L.Ed.2d 158 (1995). In order to survive strict scrutiny, a government program that uses racial classifications must be narrowly tailored to serve a compelling governmental interest. See id. Following a bench trial, we review the district court‘s legal conclusion that IDOT‘s program is constitutional de novo and its factual determinations for clear error. Bricklayers Local 21 of Ill. Apprenticeship & Training Program v. Banner Restoration, Inc., 385 F.3d 761, 766 (7th Cir.2004); Riggins v. Walter, 279 F.3d 422, 428 (7th Cir.1995).
A. Compelling Interest
NCI appears to have forfeited the argument that IDOT‘s DBE program does not serve a compelling governmental interest, focusing instead on the narrow tailoring prong of the test. Nevertheless, we think it prudent to briefly address the compelling interest aspect of the strict scrutiny analysis and we agree with the district court that IDOT has satisfied its burden here. As a state entity implementing a congressionally mandated program, IDOT relies primarily on the federal government‘s compelling interest in remedying the effects of past discrimination in the national construction market.4 In the post-Adarand era, two other circuits have considered the question of whether a state may properly rely on the federal government‘s compelling interest in implementing a local DBE plan for highway construction contracting, and both have concluded that a state may properly do so. See Western States Paving Co., Inc. v. Washington State Dep‘t of Transp., 407 F.3d 983, 997 (9th Cir.2005) (“When Congress enacted TEA-21, it identified a compelling nationwide interest in remedying discrimination in the transportation contracting industry. Even if such discrimination does not exist in Washington, the State‘s implementation of TEA-21 nevertheless rests upon the compelling interest identified by Congress.“), cert. denied, ___ U.S. ___, 126 S.Ct. 1332, 164 L.Ed.2d 49 (2006); Sherbrooke Turf, Inc. v. Minn. Dep‘t of Trans., 345 F.3d 964, 970 (8th Cir.2003) (“When the program is federal, the inquiry is (at least usually) national in scope. If Congress or the federal agency acted for a proper purpose and with a strong basis in the evidence, the program has the requisite compelling government interest nationwide, even if the evidence did not come from or apply to every State or locale in the Nation.“), cert. denied, 541 U.S. 1041, 124 S.Ct. 2158, 158 L.Ed.2d 729 (2004).
B. Narrow Tailoring
We are convinced that IDOT has satisfied its burden of demonstrating that its program is narrowly tailored. Our holding in Milwaukee County Pavers that a state is insulated from this sort of constitutional attack, absent a showing that the state exceeded its federal authority, remains applicable. See Milwaukee County Pavers, 922 F.2d at 424-25; Tennessee Asphalt Co. v. Farris, 942 F.2d 969, 975 (6th Cir.1991) (citing Milwaukee County Pavers for the same point); see also Western States Paving, 407 F.3d at 1003-04 (McKay, J., concurring in part and dissenting in part) (noting the continuing applicability of Milwaukee County Pavers and concluding that the plaintiffs should be limited to challenging the state‘s adherence to its grant of federal authority).5 In Adarand, the Supreme Court did not seize the opportunity to conclude that our decision in Milwaukee County Pavers, along with the Sixth Circuit‘s in Tennessee Asphalt, was incorrect. The Court only decided that federal programs involving racial classifications must also be subjected to strict scrutiny. See Adarand, 515 U.S. at 235. It did not invalidate our conclusion that a challenge to a state‘s application of a federally mandated program must be limited to the question of whether the state exceeded its authority. Here, because NCI has not challenged on appeal the district court‘s grant of summary judgment for the federal government, it has forfeited the opportunity to challenge the federal regulations.
Thus, the remainder of our inquiry is limited to the question of whether IDOT exceeded its grant of authority under federal law. NCI presses three arguments in this respect. First, NCI argues that IDOT violated
The regulations make clear that “relative availability” means “the availability of ready, willing and able DBEs relative to all businesses ready, willing and able to participate on your DOT-assisted contracts.”
NCI‘s second objection, that IDOT failed to properly adjust its goal based on local market conditions, also fails. As IDOT correctly responds in its brief,
Finally, we find meritless NCI‘s argument that IDOT violated
Race-neutral DBE participation includes any time a DBE wins a prime contract through customary competitive procurement procedures, is awarded a subcontract on a prime contract that does not carry a DBE goal, or even if there is a DBE goal, wins a subcontract from a prime contractor that did not consider its DBE status in making the award (e.g., a prime contractor that uses a strict low bid system to award subcontracts).
NCI argues that IDOT‘s calculation of past levels of race-neutral DBE participation erred by failing to include a calculation of the instances when DBEs winning subcontracts from prime contractors on goal projects where the prime contractor did not consider DBE status. IDOT calculated the level of past race-neutral DBE participation by assessing the rate of DBEs winning contracts on no-goal projects. Though the regulations indicate that where DBEs win subcontracts on goal projects strictly through low bid this can be counted as race-neutral participation, NCI points to no aspect of the regulations requiring IDOT to engage in a search for this information for the purpose of calculating past levels of race-neutral DBE participation. As IDOT explains, this evidence was not before it at the time that the Fiscal Year 2005 plan was adopted and NCI has not produced any evidence proving that IDOT‘s past participation figure is invalid. NCI accurately points out that, under
In any case, the record makes clear that IDOT uses nearly all of the methods described in
III. CONCLUSION
The judgment of the district court is AFFIRMED.
