Northeast Erectors Ass'n of the BTEA v. Secretary of Labor, Occupational Safety & Health AdministrationNortheast Erectors Ass'n of the BTEA v. Secretary of Labor, Occupational Safety & Health Administration
Northeast Erectors Assoc. (“NEA”) sued the Secretary of Labor, the Occupational Safety and Health Administration (“OSHA”), and OSHA’s Boston regional office, for declaratory and injunctive relief. NEA sought to enforce an asserted oral agreement with the Boston regional office of OSHA, under which the office allegedly agreed not to enforce certain OSHA regulations. The district court dismissed for failure to state a claim. NEA now appeals. We affirm, although on a different ground.
I.
NEA is an unincorporated association of contractors who perform structural steel and pre-cast concrete erection. The OSHA regulations at issue in this case establish standards designed to protect against falls of employees working in the construction industry and, particularly, of persons working in the steel erection industry.
We accept NEA’s allegations as true for the purposes of this appeal,
Watterson v. Page,
From 1989 through April of 1994, regional OSHA representatives, allegedly in compliance with the “agreement,” did not cite local steel erection contractors for noncomplianee with the fall protection standards for “connectors.” NEA argues that the agreement was breached in 1994 when the Deputy Assistant Secretary of OSHA sent a memorandum to all of the regional offices, directing them to cite employers who violated the fall provisions in
Defendants moved to dismiss for lack of subject-matter jurisdiction,
When faced with motions to dismiss under both 12(b)(1) and 12(b)(6), a district court, absent good reason to do otherwise, should ordinarily decide the 12(b)(1) motion first.
See
5A Charles Wright & Arthur Miller,
Federal Practice and Procedure
§ 1350, at 210 (1990);
Bell v. Hood,
We accordingly start — as well as end — with the jurisdictional issue, holding that the district court was without subject-matter jurisdiction over NEA’s claim. The Occupational Safety and Health Act (“OSH Act”) has an extensive administrative process for review of OSHA enforcement actions. After OSHA issues a citation, an employer may seek administrative review before-the Occupational Safety and Health Review Commission (“OSHRC”).
The OSH Act expressly authorizes the bringing of original actions in the U.S. District Court in only a few situations. None of these includes the bringing in the district court of pre-enforcement actions by employers.
See
In
Thunder Basin Coal Co. v. Reich,
— U.S. -,
Although the Mine Act did not expressly mention pre-enforcement challenges, the Court pointed to the detailed administrative review procedures established by the Act, After MSHA issues a citation, a mine operator may seek administrative review before
Pointing to the comprehensive review procedures, the Court held that a district court had no subject-matter jurisdiction to entertain a pre-enforcement challenge to the Act by a mine operator. The Mine Act’s “comprehensive review process does not distinguish between pre- and post-enforcement challenges, but applies to all violations of the Act and its regulations.” Id. The Court also pointed to the legislative history of the Act, which indicated that administrative review procedures were designed to be the exclusive mechanism through which mine operators were to obtain review of enforcement actions. The Court concluded that:
Nothing in the language and structure of the Act or its legislative history suggests that Congress intended to allow [employers] to evade the statutory-review process by enjoining the Secretary from commencing enforcement proceedings, as petitioner sought to do here. To uphold the District Court’s jurisdiction in these circumstances would be inimical to the structure and purpose of the ... Act.
Id. at-, 114. S.Ct. at 781.
This case falls squarely within the holding of
Thunder Basin.
We hold that the OSH Act’s comprehensive administrative review scheme precluded the district court from exercising subject- matter jurisdiction over the present estoppel-based pre-enforcement challenge. The administrative and judicial review procedures in the two acts are nearly identical.
Compare
OSHA’s decision would, moreover, be entitled to judicial review by a court of appeals.
See, e.g., Erie Coke Corp.,
1992 OSH Dec. (CCH) ¶ 29,653 (O.S.H.R.C.) (no estoppel where no evidence that reliance on earlier OSHA position was reasonable or that Secretary engaged in affirmative misconduct),
aff'd sub nom., Reich v. OSHRC,
III.
Because the district court lacked subject-matter jurisdiction over this case, we affirm the district court’s dismissal on that ground
Affirmed.
Notes
. A different priority is followed in cases where the 12(b)(1) motion is based on the plaintiffs alleged failure to state a federal claim. (The idea being that, if the plaintiff failed to state a federal claim, there could be no federal question jurisdiction.) In such cases, the prevailing view is that, unless the claim is entirely frivolous, a court should assume jurisdiction and dismiss for failure to state a claim, since federal question jurisdiction exists once plaintiff has alleged even a colorable federal claim.
See Bell,
.
Tierney v. Schweiker,