127 Wash. 73 | Wash. | 1923
The appellant owns the water supply of the city of Port Angeles, a city of some 6,000 population, and distributes water to about 1,400 users. In September, 1922, a petition was filed with the respondent alleging that, during the summer months, some twelve or thirteen users residing on the highest point of the city were “unable to get water at all from their service of said company’s pipes during a period of several days.” In response to the petition, the appellant appeared and in its answer admitted that, on
The evidence introduced upon the hearing before the public works department showed that the appellant was voluntarily proceeding to make betterments. The answer concluded (in the nature of a summary of the entire situation) with the following:
“Ultimately the only way to get water distributed over such a large area as we have in this city is to place meters on individual consumers, at least this should apply to those disregarding sprinkling rules and those who waste water.”
After a hearing, an order was made by the department, containing several paragraphs, the majority of which provide for the installation of the betterments which the appellant had stated it was undertaking to make, and to this part of the order no exception was taken by the appellant. The appellant, however, does except to two paragraphs of the order, one of which requires that appellant should “install suitable water meters on all services not now metered,” and “construct a settling basin.” The record shows that the cost of installing the metering system and the settling basin would be from $45,000 to $80,000; and, in this appeal from these two portions of the order, it is alleged that they are invalid for the reason that they were not within the scope of the hearing upon the complaint filed and were in excess of the jurisdiction of the department under the evidence.
Under the statute “all grievances to be inquired into shall be plainly set forth in the complaint,” and the department is without jurisdiction to hear and determine matters which are not so set out. In State ex
That the complaint goes no further than this is virtually conceded by the respondent’s attorneys, for they seek to justify the order by the argument that the appellant’s answer presented the issue of metering by the paragraph quoted in the opening of this opinion. The pleading is not legitimately subject to such interpretation. The appellant’s answer met the issue presented by the complaint and admitted the fault, stated the appellant’s intention to remedy it, and the order recognized that these remedies were being undertaken and ordered .their completion; but it goes beyond that and, as the findings and order show, the department provided for things which would be “ample to care for all reasonable requirements for several years to come.”
“Q. Did it ever occur to you that about sixty per cent of all the water that goes into your system is wasted? A. Yes. Q. Do you know how to remedy that? A. Yes sir, by putting in a settling basin and metering the services.”
Under this record, it cannot be said that the department had before it, or tried, the issues of the necessity for meters and settling basin. It was clearly improper for the department to issue an order of so sweeping and serious a nature when it had no more before it than appears here.
The judgment, therefore, of the superior court affirming the third and fifth orders of the department is vacated, and those orders are declared void and their enforcement is restrained.