after stating the case, delivered the opinion of the court.
From the decree dismissing this bill the present appeal is prosecuted, and the errors assigned by the appellant may be embraced in the general proposition that the court below erred in declining to adjudicate and determine the amount of the damages sustained by the Chicago Company from the breach of the rail contract and set off the same against the judgment at law, and in dismissing the bill, even though such dismissal was without prejudice to the right of the Chicago Company to bring suit for the recovery of such damages.
In addition to the reasons on which the court below denied relief and dismissed the bill, it is urged by the appellee that the equitable ground for relief, viz., the insolvency of the St. Louis Company, ceased to exist before the final decree was rendered. It is urged that its solvency was shown by the
It is not shown by the record that the St. Louis Company was restored to a state of solvency before the final decree; but if that fact had been properly shown, it was not set up as a defence in the present suit, and it cannot now be invoked on behalf of the Joliet Company or its assignee.
It admits of no question that the St. Louis Company made default in the performance of the rail contract. It failed in the payment of the sum of $21,536.56 on July 10, 1884, for steel rails delivered in June. This default continued throughout the year 1884. Neither the St. Louis Company nor its receiver gave any order or orders for the manufacture of rails for July delivery. On the order for 1500 tons of rails; given for August delivery, the receiver was confessedly not prepared to pay, nor was any provision made by which the Chicago Company could reasonably expect payment therefor on September 10, 1884. The receiver had made every possible effort to raise funds by the sale of receiver’s certificates, and had failed. He had nothing to pay with except “certificates,” and the Chicago Company had declined to take them. It was certainly not bound to proceed with the manufacture and delivery of rails under the August order, after being notified in advance that the receiver was not prepared, and did not expect to be in funds to pay for the same unless certificates were accepted. For the reason that he had nothing to pay with, except “ certificates,” the receiver considered, as he stated to the president of the Chicago Company, in a letter dated September 26, 1884, that it would have been wrong to have asked the Chicago Company to make and forward rails without immediate or prospective means of paying for the same. So no further orders were given for rails, although the Chicago Company repeatedly, during August, September, and October, expressed its readiness and ability to fill all orders when the receiver was prepared to pay therefor according to the terms of the contract. The Chicago Company, early in October, indicated its willingness to reduce the price of the undelivered rails to $30 per ton, upon prompt
Under these circumstances there was a clear breach of the rail contract on the part of the St. Louis Company. The first default occurred on July 10,1884, in failing to pay the amount then due the Chicago Company. It was further in default in not giving an order to manufacture rails for July, which was continued during the succeeding months of the year 1884; so that at the close of December, 1884, when the time for the final performance of the contract expired, there were about 10,618 tons of rails that the St. Louis Company had failed to order, receive, and pay for at the contract price of $35 per ton. Steel rails continued to decline from July, 1884, to January, 1885, the price running down to $29.50 a ton between those dates.
It is claimed for the appellee that as the Chicago Company had not rescinded and terminated the rail contract for the July breaches thereof—-if entitled so to do — it was not in a position to bring suit for damages when the garnishor’s right became fixed. This, however, does not affect the merits of this case. The Chicago Company was not bound to treat the contract as at an end upon the first breach thereof by the St. Louis Company. It had a right to await the expiration of the time for its final performance, and then make its claim for the entire breach. In the view we take of the question it is not material to determine at what precise date there was such a breach as would entitle the Chicago Company to damages upon the entire contract. The material thing is that the contract (for the breach of which the claim for damages arises) was in existence when the garnishment process was served. It had then been broken in one particular, if not in more, and from the situation and embarrassed condition of the St. Louis Company there was almost a certainty that it would fail to perform the contract in the future. The Chicago Company gave repeated notices to the receiver of its readiness and willingness to fulfil the contract on its part. It could only manufacture rails as they were ordered, and their weights specified. It notified the receiver time and again that it
Cross-demands and counter-claims, whether arising out of the same or wholly disconnected • transactions, and whether liquidated or unliquidated, may be enforced by way of set-off whenever the circumstances are such as to warrant the interference of equity to prevent wrong and injustice.
Again, it is well established that equity will entertain jurisdiction and afford relief against the collection of a judgment where in justice and good conscience it ought not to be enforced, as where there is a meritorious, equitable defence thereto, which could not have been set up at law, or which the party was, without fault or negligence, prevented from interposing. Illustrations of these general principles are found in the cases of
Leeds
v.
Marine Ins. Co.,
The adjustment of demands by counter-claim or set-off rather than by independent suit is favored and encouraged by
By the decided weight of authority it is settled that the insolvency of the party against whom the set-oif is claimed is a sufficient ground for equitable interference.
Leeds
v.
Marine Ins. Co.,
In
Schuler
v.
Israel,
It is suggested by the appellee that this was merely “ incidental to the point decided in that case,” but the proposition it announces is supported by sound principle and authority, and the Illinois decisions are in full accord therewith.
In addition to insolvency, it is held by many well-considered
It is not deemed necessary to review these cases and make quotations from them. They fully establish the principles for tvhich they are cited. There is nothing in the Illinois statutes on the subject of attachment and garnishment inconsistent with the doctrine of the foregoing decisions. Applying the principle they announce to the present case, it admits of no doubt that the Chicago Company is entitled to the relief it seeks as against the St. Louis Company. The question then remains whether the attachment proceedings, or the garnishment process thereunder, resulting in the order or judgment at law declaring the Chicago Company’s ascertained indebtedness liable to the payment of the Joliet Company’s judgment against the St. Louis Company, in any way changes or defeats the equity or right of the Chicago Company to the same relief ?
The court below seems to have entertained'the theory that while the St. Louis Company may have failed to perform the rail contract, the Chicago Company’s right to claim damages for the entire breach thereof had not accrued July 21, 1884, when the garnishment process was served and the garnishor’s rights attached, and, furthermore, that such claim, however meritorious as against the St. Louis Compan}?, could not form the subject of an equitable set-off, especially as against a demand arising out of a disconnected transaction. This proceeds upon the assumption, as appellees here contend, that the garnishor by the service of the garnishment acquired such a lien upon or equitable right to the funds due from the garnishee which could not be disturbed or affected by any right or equity subsequently accruing to the latter as against the principal debtor. The service of garnishment neither changed nor interrupted the contractual relations existing between the
The English law upon the subject of garnishment and its effect differs in no material respect from that of Illinois, and in Chatterton v. Watney, 17 Ch. D. 259, it was held that a garnishee order did not have the effect of transferring the debt from the garnishee.
In the case of
Ex parte Chinery,
12 Q. B. D. 342, it was held by Lord Justice Cotton that a garnishee order absolute was not a final judgment against the garnishee, and did not make the garnishor a creditor of the garnishee. In the subsequent case of
In re
Combined
Weighing and Advertising Machine Co.,
43 Ch. D. 99, 104, 105, 106, the effect of a garnishee order was again under consideration, and it was'held that- the garnishee order did not effect any transfer, legal or equitable, of the debt owing by the garnishee, or create the relation of creditor and debtor as between the garnishor and the garnishee.
The proposition here laid' down is in harmony with the generally recognized principle that the rights of the garnishor do not rise above or extend beyond those of his debtor; that the garnishee shall not, by operation of the proceedings against him, be placed in any worse condition than he would have been in had the principal debtor’s claim been enforced,, against him directly; that the liability, lbgal and equitable, of'the garnishee to the principal debtor is a measure, of his liability to the attaching creditor, who' takes the shoes of the principal debtor and can assert only the- rights of the latter.
Towner
v.
George,
53 Illinois, 168;
Richardson
v.
Lester,
83 Illinois, 55;
Henry
From these propositions and authorities it follows that the Chicago Company is entitled to assert against the Joliet Company the equitable set-off it could enforce against the St. Louis Company in respect to its claim for damages.
It is hardly necessary to observe that the appellee Ferguson, having taken an assignment from the Joliet Company pendente lite, occupies the same position as his assignor, and is subject to the same equity. It is sought to defeat this right of the Chicago Company by invoking in favor of the Joliet Company and its assignee, Ferguson, the doctrine of relation so as to antedate the claim for damages. This cannot be done for two reasons: first, because the breach of contract, on which the claim for damages is based, had in fact commenced before the garnishment writ was served; second, if that had not been the case, the contract, for the non-performance of which the right for damages arises, was in existence when the garnishment proceedings were instituted.
This unquestioned fact is very material, if not controlling of the case. The-court below did not give the fact that the claim for damages arose under and by virtue of a contract in existence prior to the date of the attachment its due weight and importance, as will be seen by a brief reference to the authorities bearing upon the question. Thus in
Boston Type Co.
v.
Mortimer,
In the recent case of
Lannan
v.
Walter,
So in
Farmers’ and Merchants' Bank
v.
Franklin Bank,
In the first of the above cited cases the liability of the garnishee was conditional and undetermináte at the time of the service of the. garnishment process, and his right to claim against the principal debtor did not become fixed until long' after the service of process, so that the garnishee had no cause of action against the principal debtor when the attachment writ was served. Also in each of the other cases the set-off allowed matured after the service of garnishment, but arose under a contract entered into before the' service of the writ. In other words, the principle established by these cases is that, whatever rights the garnishee may have under existing contracts with the principal debtor, he is entitled to have the benefit thereof as against the attaching creditor.
The latter clause of the quotation from the case of Farmers' and Merchants' Bank v. Franklin Bank, supra, lays down the correct rule to be applied in cases of this character, and that rule is, that, while the garnishee may not, after service of the writ, by his own action acquire set-offs or counterclaims against the principal debtor to the prejudice of the attaching creditor, he may properly avail himself of all claims fairly arising out of contracts with the principal debtor which were in existence when the attachment was commenced, and under or out of -which his claim against the principal debtor arises.
From the foregoing considerations we think the court below should have ascertained the damages growing out of the failure to perform the rail contract on the part of the St. •Louis Company, and having ascertained the amount of such damages the same should have been allowed the complainant as a set-off against the sum of $16,473.28, found to be due from it to the St. Louis Company, and for which the garnishee order or judgment was rendered-; and if that adjustment left
The judgment of the cowrt below is accordingly reversed, and the ccmse remanded, with directions to proceed therein in conformity with this opinion.
