Dоn Norman, Roger Norman, and South Meadows Properties (collectively “appellants” or “the Normans”) appeal two decisions of the United States Court of Federal Claims. The first, issued April 17, 2003, dismissed the Normans’ illegal exaction claim for lack of jurisdiction.
Norman v. United States,
I. BACKGROUND
The opinion of the Court of Federal Claims described the facts of this case in
The Normans are real estate developers who, in the late 1980s, planned to develop commercial and industrial office space in Reno, Nevada, on a 2425-acre property previously used for ranching and agricultural activities (the “Ranch”). See id. at 234. In 1986, a company called Southmark Corporation purchased the Ranch, intending to develop it for commercial and residential uses. Southmark prepared a “master plan” for the development of the property and submitted it to the Reno City Council for approval. On January 30, 1987, the city council “conditionally approved” the master plan, identifying 41 conditions that the developer was required to satisfy before final approval would issue. One of those conditions required the developer to submit to the council “plans approved by the United States Army Corps of Engineers ... delineating wetlands or any other lands the development of which were subject to the issuance of federal permits.” Id.
In June of 1988, the Army Corps of Engineers (the “Corps”) sent a team of wetlands experts to “conduct field work necessary to prepare a final wetlands delineation.”
Norman II,
On September 12, 1988, the Corps issued a delineation (the “1988 Delineation”), prepared pursuant to the 1987 version of the Corps’ Wetlands Delineation Manual. The 1988 Delineation identified 28 acres of jurisdictional wetlands on the Ranch property, of which 17 acres were located on the 470-acre parcel desired by the Normans. Following completion of the delineation, the Normans acquired the property. Id. At the same time, Robert Helms purchased the 1800-acre “residential” portion of the Ranch. The Normans and Helms then entered into an agreement whereby they agreed to develop their properties consistently with Southmark’s Master Plan. The parties do not dispute that the Normans relied upon the 1988 Delineation in purchasing the 470-acre plot, or that their reliance was reasonable.
After the 1988 Delineation became public, however, a “storm of controversy” erupted, as a variety of concerned entities criticized the delineation. Id. at 237. The Corps then “revoked the 1988 wetlands delineation and conducted a new delineation under the 1989 version of the Corps’ Wetlands Delineation Manual” (the “1991 Delineation”). Id. The new delineation effort began in April of 1991 and ended in October of 1991.
The 1991 Delineation substantially increased the acreage of jurisdictional wetlands on the subject property, identifying 230 acres of such wetlands. Of the 230 wetland acres, 87 acres were on the “commercial” portion of the parcel owned by the Normans. This increased the wetlands acreage by 70 acres.
See Norman II,
In 1995, appellants applied to the Corps for a permit under section 404 of the Clean Water Act
1
(a “404 Permit”) enabling them to impact 15 acres of jurisdictional wetlands and other waters of the United States. As mitigation for the proposed impact, “plaintiffs proposed to create additional wetlands to ensure no net loss of wetlands functions and values.”
Norman II,
In 1998, appellants submitted another 404 Permit application, this time seeking permission to impact wetlands throughout the 2280-acre development site. See id. at 239. The Corps responded that because appellants’ proposed actions “would result in significant environmental impacts,” the Corps would have to prepare an Environmental Impact Statement in compliance with the National Environmental Policy Act of 1969, unless appellants provided “a mitigation plan' which clearly reduced the project impacts to a less than significant level.” Id. The Corps also provided a “modified development alternative,” suggesting a development plan with less significant environmental impacts. Id.
In July of 1999, appellants submitted a revised mitigation proposal that was, according to the trial court’s findings of fact, “a result of a negotiations process between the Corps and plaintiffs,” in which “the parties discussed which areas of property on the 2280-acre Development could be utilized as mitigation wetlands.” Id. at 239. The resulting plan contemplated that “the areas designated ... for storm drainage could sufficiently serve as mitigation wetlands due to the hydrology surrounding that area.” Id. at 240. Under the modified development plan, a substantial portion of the mitigation wetlands would be on lands that would not otherwise have been developed in any case.
The Corps approved the proposal and, on August '31, 1999, issued the Normans a 404 Permit enabling them to proceed with their development plan (the “1999 Permit”). The 1999 Permit enabled appellants to fill approximately 60 acres of wetlands; in exchange, it required them to
Prior to and following issuance of the 1999 Permit, appellants “continued to sell the developable parts of the 2280-acre Development to various independent third parties.” Id. at 242. At the time the 1999 Permit .actually issued, appellants owned only 716 acres of the original 2280-acre parcel.
The Normans filed the first lawsuit in this matter in 1995, raising breach of contract and takings claims. The subsequent history of the litigation is lengthy and is recited in detail in
Norman II,
Following post-trial briefing, the Court of Federal Claims issued an opinion and order denying all of appellants’ takings сlaims and ordering the clerk of court to enter judgment against appellants and dismiss their amended complaint with prejudice. The clerk entered final judgment, and appellants timely filed their notice of appeal. We have jurisdiction pursuant to 28 U.S.C. § 1295(a)(3).
II. DISCUSSION
In their appeal, the Normans challenge the trial court’s rulings on both their takings claims and their illegal exaction claim. This court reviews the trial court’s findings of facts under the standard of “clear error.”
Hendler v. United States,
A. Significance of the 1991 Delineation
We recognize at the outset a fundamental tension in the Normans’ takings claim. The Normans place heavy weight on the revocation of the 1988 Delineation
In other words, the Normans want this cоurt to evaluate the entire sequence of events from 1988 through 1999 as a single transaction, in which the mitigation set-aside of 1999 followed ineluctably from the “unprecedented” 1991 Delineation. If we conclude that those two events were, for purposes of takings analysis, distinct — that the events of 1991 did not, in appellants’ words, “directly cause[] the Normans to lose 220.85 acres of property in 1999”— then the bulk of their takings claims fail on that ground alone, because their challenge to the terms of the 1999 Permit is, according to their own argument, based solely upon the role of the 1991 Delineation in imposing those terms.
We find the Normans’ argument unconvincing. The suggestion that Corps action in 1991 “directly” caused the Normans to lose 220.85 acres of property, most of which they did not own until 1994, strains the word “directly” well beyond its breaking point. The revocation and re-delineation that preceded the 1999 Permit by nearly a decade were but two of dozens of factual predicates leading up to the issuance of the 1999 Permit; others include the voluntary purchase, by appellants, of most of the land covered by that permit. That the decision to purchase that additional property may have been influenced, in small or large degree, by the events of 1988-1991 does not render it involuntary. The causal relationship between the revocation of the 1988 Delineation and the appellants’ alleged loss is simply too attenuated to support the weight the Normans place upon it.
Because the Normans have disclaimed any challenge to the “routine” mitigation requirements of the 1999 Permit except insofar as they resulted from the “unique” 1991 Delineation, we believe this conclusion disposes of most of their tаkings claims without further analysis. In order to fully respond to the arguments appellants raise, however, we shall evaluate their claims in greater detail.
B. Physical Takings Claim
In general, this court has analyzed takings claims arising from section 404 permit issues using the regulatory takings analysis set forth in
Penn Central Transportation Co. v. New York,
Neither did the Permit “exact” possession of the land. Appellants argue that “the Normans’ loss of exclusive possession ... constitutes a categorical taking under the Fifth Amendment,” relying for that proposition on
Nollan v. California Coastal Commission,
Because wе conclude that no physical invasion occurred here, the Normans’ reliance on cases like
United States v. Pueblo of Taos,
Even if the government’s action could reasonably be characterized as a physical invasion, the Normans’ claim for compensation would fail under the principles set forth by the Supreme Court in
Nollan
and in
Dolan v. City of Tigard,
Even if the nexus requirement of the
Nollan
and
Dolan
line of exaction cases were applicable here — and we think it clear that it is not — we would agree with the trial court’s conclusion that an appropriate nexus exists between the set-asidе of the 220.85 acres and the regulatory purpose. In the words of the trial court, “[t]he public interest served by requiring the preservation of wetlands in exchange for the filling and dredging of other [wetlands relates directly to the condition imposed. There is no disconnect.”
Norman II,
C. Categorical Takings Claim
A “categorical” taking is a regulatory taking in which government action deprives the landowner of all beneficial use of his property, such that the government action is the functional equivalent of a physical invasion.
See Lucas v. S.C. Coastal Council,
Assuming,
arguendo,
that the Normans intend to challenge the terms of the 1999 Permit despite their disavowal of such intent, the question here is whether the 1999 Permit in fact effected a deprivation of all beneficial use. The case law on
Here, the trial court identified the “parcel as a whole” as “the 2280-acre Development,” comprising the properties designated for development in Phases I, II, and III of the development plan, exclusive of property conveyed to the state for rights-of-way.
Norman II,
D. Regulatory Takings Claim
Having correctly found that there was no categorical taking of plaintiffs’ property, the trial court moved on to “weigh the three factors of the
Penn Central
ad hoc analysis to determine whether a regulatory taking” occurred.
Norman II,
After undertaking a meticulous analysis of the Penn Central factors as applied to the facts at bar, the trial court concluded that appellants had “reasonable investment-backed expectations” with respect to only the four-acre parcel described as “WL 17B,” which appellants purchased in 1989 but which was first delineated as wetlands in the 1991 Delineation. See id. at 267-68. The trial court then concluded that the economic impact factor weighed against a finding of a taking, because the 1999 Permit actually increased the economic value of the parcel as a whole by “allowing] plaintiffs to fill valuable commercial property and develop that property in exchange for setting aside other, less valuable property for mitigation.” Id. at 278. Finally, the trial court analyzed the character of the government action, concluding that the issuance of the 1999 Permit served a “legitimate public welfare obligation”; that appellants were treated fairly by the Corps and that the Permit was itself the product of negotiations between the Corps and appellants; and that appellants were not singled out for disparate treatment. See id. at 282-86. Weighing all these factors in light of the facts of the case, the trial court concluded that “no regulatory taking of property ... occurred,” because the Corps’ actions “simply did not unduly burden plaintiffs.” Id. at 287.
The Normans challenge very little of the trial court’s Penn Central analysis. Their briefs do not even mention the trial court’s extensive discussion of the “character of the governmental action” factor. With respect to the other two factors, their rather cursory arguments amount to little more than a reiteration of the claim, rejected above, that the critical causative element at issue here was not the 1999 Permit but the events of 1988-1991. Appellants argue, for example — albeit briefly — that the trial court erred in failing to measure economic impact as of the time of the 1988 Delineation. This position is illogical. The Normans cannot explain why the trial court should have measured economic impact as of a time when they did not own the great majority of the property allegedly taken.
The same is true regarding reasonable investment-backed expectations. The Normans argue that their expectation interest should have been measured as of 1988, when they purchased the initial 470-acre parcel. We notе first that the trial court did, in fact, measure appellants’ expectations with respect to the 470 acres as of the date they purchased that land, and found that the Normans had reasonable investment-backed expectations in a few of those acres.
See Norman II,
In addition, we note that although a takings claim “is not barred by the mere fact that title was acquired after the effective date of the state-imрosed restriction,”
Palazzolo v. Rhode Island,
The trial court found that the Normans reasonably relied on the 1988 Delineation when purchasing their original 470-acre parcel. In that delineation, the Corps designated only 17 acres of the 470-acre parcel as wetlands. The 1991 Delineation identified an additional 70 acres of that parcel as wetlands. Although as of the time they purchased the 470-acre parcel, the Normans had reasonable investment-backed expectations that they would be able to develop those 70 acres, the effect of the 1991 Delineation was considerably mitigated by the 1999 Permit and related Deed of Restrictions, which resulted in the transfer of 220.85 acres to the South Meadows Association but also resulted in the Normans gaining the right to develop all but a few of the 70 acres designated as wetlands in 1991. To be sure, in order to obtain the right to develop those acres, appellants had to agree to set aside additional acreage as mitigation wetlands. The trial court found, however, that almost all of the property that either had been designated as wetlands in the original 1988 Delineation (of which the Normans were fully aware when they purchased the 470-acre parcel), or was outside the 470-acre parcel (and thus was purchased by the Normans only after it had already been designated as wetlands in 1991), or was never intended for development (because it was intended to be used for storm run-off and flood control). Thus, the trial court found that of the 220.85 acres set aside for mitigation, only 4.07 acres constituted property that the appellants intended and reasonably expected to be able to develop.
The Normans argue that they had reasonable investment-backed expectations with respect to the entire 220.85 acres that were set aside as mitigation. They do not, however, specifically challenge the trial court’s characterization of each of the components of the 220.85 acres. Neither do they suggest any way in which the trial court erred in concluding that the 1991 Delineation, as applied to the 470-acre parcel, had any lingering effects other than with regard to the 4.07-acre parcel as to which the trial court found that the appellants had a reasonable investment-backed expectation. Because the trial court’s finding as to the appellants’ reasonable investment-backed expectations with regard to the 470-acre parcel has not been shown to be erroneous, we uphold the trial court’s finding that the Normans’ reasonable investment-backed expectations were limited to the 4.07-acre plot.
In light of the trial court’s finding with respect to reasonable investment-backed expectations, the Normans’ challenge to the court’s regulatory takings analysis is unpersuasive. The appellants claim that the trial court’s implementation of
Penn
In short, the Normans have provided us no basis on which to reverse the trial eourt’s conclusion that no taking occurred here.
E. Illegal Exaction Claim
On April 17, 2003, the Court of Federal Claims issued an opinion and order dismissing appellants’ illegal exaction claim for lack of jurisdiction.
See Norman I,
We note at the outset that both appellants’ amended complaint and their briefs appear to cоnflate two distinct types of “exactions.” Paragraph 40 of the complaint alleges that “[b]y reason of the 1999 permit requirement ... plaintiffs were required to dedicate for public use in perpetuity 220.85 acres of plaintiffs’ land in violation of Pub.L. 102-104 and the Fifth Amendment to the United States Constitution.” This sentence appears to allege the kind of “exaction” at issue in takings cases like Dolan and Nollan — where the government uses a permitting process to obtain from a landowner concessions which, if the government accomplished them directly, would constitute takings. Although such claims are phrased, in part, in terms of “exactions,” they are clearly Fifth Amendment takings claims. These claims were not dismissed by the trial court’s order of April 17, 2003, and are discussed in the sections on takings above.
An “illegal exaction,” as that term is generally used, involves money that was “improperly paid, exacted, or taken from the claimant in contravention of the Constitution, a statute, or a regulation.”
Eastport S.S. Corp. v. United States,
The Normans claim that the 1991 Delineation “exacted” from them their land, in contravention of Public Law 102-104, which prohibited the expenditure of public funds for delineations using the Corps’ 1989 Wetland Delineation Manual. They claimed below that “funds were expended on delineation of [the disputed property] as late as October 30, 1991, when the Corps claims the 1991 delineation became final.”
Norman I,
The trial court rejected that argument, concluding that even if the 1991 Delineation violated Public Law 102-104, the Court of Federal Claims lacked jurisdiction over the supposed exaction because the land was not exacted
“due to
[a] misapplication of’ the statute as required by
Aerolineas, Casa de Cambio Comdiv
and
Eastport. See Norman I,
Appellants argue that “it was precisely through the Corps’ illegal 1991 re-delineation of the Normans’ property ... that the Corps gained jurisdiction over an additional 70 acres of wetland and, as the price of allowing the Normans to regain the use of that 70 acres, exacted from the Normans 220.85 acres of ‘mitigation’ lands.” This is a reiteration of appellants’ argument, rejected above, that the 1991 Delineation somehow itself effected the taking of the 220.85 acres set aside in the 1999 Permit. The facts simply do not support that contention. Appellants’ assertion that “the loss of the 220.85 acres was the foreseeable and predictable result of redelineation under the 1989 manual,” such that the 220.85 acres were “exacted
as a direct result of
the application of’ Public Law 104-102, as required for Tucker Act jurisdiction over exaction claims, strains the meanings of the words “foreseeable,” “predictable,” and “directly” beyond all recognition.
See Casa de Cambio Comdiv v. United States,
This court has addressed this causal attenuation problem in exaction cases on several occasions. We have held, for example, that “a plaintiff has a claim for an illegal exaction only where the government [action] has direct and substantial impact on the plaintiff asserting the claim.”
Casa de Cambio Comdiv,
Assuming
arguendo
that illegal exaction principles are ever applicable to actions against the United States for just compensation for an alleged taking of real property, we agree with the trial court that “misapplication of Public Law No. 02-104 did not directly result in an exaction ... so as to satisfy the jurisdictional prerequisite for maintaining an illegal exaction claim” under the Tucker Act.
Norman I,
CONCLUSION
For the reasons set forth in this opinion, we affirm the trial court’s judgment in favor of the United States as to the Normans’ takings claims and affirm the trial court’s dismissal, for lack of jurisdiction, of the Normans’ illegal exaction claim.
No costs.
Notes
". Section 404 of the Clean Water Act, codified at 33 U.S.C. § 1344, establishes a program for the regulation of fill activities involving waters of the United States. The “basic premise of the program is that no discharge of dredged or fill material” into waters of the United States is "permitted if a practicable alternative exists that is less damaging” to the environment. Environmental Protection Agency, Section 404 of the Clean Water Act: An Overview, http://w ww.epa.gov/owow/wetlands/facts/factlO.html (last visited November 4, 2005).
. The Deed of Restrictions, as the trial court noted, imposed restrictions broader than those stated in the 1999 Permit itself. It called for the setting aside of a total of 235.14 acres of mitigation wetlands, while the Permit required only 195. Appellants arrive at the total of 220.85 acres they allege to have been taken by reading the Permit and the Deed together.
See Norman II,
. Appellants do not seriously dispute this, relying instead on a passage in the trial court’s opinion that could be read to suggest that the government stipulated that the conveyance was required.
See Norman II,
. In this regard, we note that appellants' own permit application related to the entire 2280-acre parcel, and not to any subdivision thereof.
. Appellants devote a few cursory sentences to disputing the trial court’s parcel as a whole analysis, but only in their reply brief. Arguments raised for the first time in a reply brief are not properly before this court. See,
e.g., Novosteel SA v. United States,
. The Supreme Court’s decision in
Hodel v. Irving,
