187 Mass. 25 | Mass. | 1904
Under the contract, which included the specifications and plans, the plaintiff was required to provide a suitable foundation for the building to be erected, but the nature of the soil to be excavated was such that more work ultimately was required for this purpose than he originally anticipated.
It is his contention that this work is not covered by the contract, and that he is entitled to extra compensation for its performance.
By the specifications it was provided that “ The architects shall be the sole interpreters of their drawings and these specifications, and except as otherwise provided or specified, their decision upon all questions relative to drawings, specifications or contract for the said building shall be final and binding upon the owner and the contractor.”
While putting in the foundation the plaintiff discovered a quicksand, and asked the architects, subject to whose supervision the work was being done, for instructions.
Upon the evidence before him, the arbitrator found as a fact that the architects decided that the clause in the specifications relating to the excavation required was not inserted with the intent that the expense of the work made necessary by the quicksand should be borne by the plaintiff, as this circumstance
If the architects were clothed with authority to make this decision it is conclusive between the parties.
The clause which defined their powers and duties was contained in a contract under seal, voluntarily entered into by the parties, and provided a simple and convenient method for the settlement of any questions that, as the work proceeded, might arise over the interpretation of the contract, or of the drawings and specifications. Or, in other words, whenever it became necessary, whether for the information of the plaintiff, who had stipulated to work under their direction, or for the benefit of the defendant in securing a strict compliance with the terms of the contract, it was left to the architects finally to determine what their drawings and specifications covered as. to the quantity and quality of the work that was required to be done by the plaintiff.
In the practical working of this plan of supervision and adjustment of differences the cumbersome formalities of a notice to or a hearing of the parties before making a decision evidently were not contemplated, as such a requirement is not found in any provision of the contract. Neither was it required by the character of the undertaking. For the purposes of their decision they were free to adopt such legal principles as they honestly believed applicable, and to act on such evidence as they chose to receive. Boston Water Power Co. v. Gray, 6 Met. 131, 169. Flint v. Gibson, 106 Mass. 391, 395.
Although the defendant when notified declined to be bound by their decision, this action was taken after it had been communicated to the plaintiff, and, if it is treated as an attempt formally to revoke the power previously given, it came too late, and, if it had been in time, the power having been conferred by an instrument under seal could not have been revoked by parol. Wallis v. Carpenter, 13 Allen, 19, 24.
Besides, an attempted rescission by the defendant even if under seal and before the power had been exercised, could not have effected a revocation of the authority of the architects, for this was conferred by one part of an agreement which as a whole the defendant was not entitled to rescind. Haley v. Bellamy, 137 Mass. 357, 359.
The arbitrator, therefore, correctly ruled that the architects were authorized to act on the question submitted to them, and their decision thereon was binding on the defendant.
As the award well can rest on this ground, it becomes of no consequence to consider whether the contract, fairly construed, required the plaintiff to excavate through the quicksand, although on this question the arbitrator ruled in his favor. See Stuart v. Cambridge, 125 Mass. 102.
Award of the arbitrator accepted for the full amount; and judgment ordered thereon for the plaintiff.