21 S.D. 368 | S.D. | 1907
Lead Opinion
To- recover $645.74 for drilling, casing, and completing an artesian well, appellant pleaded the performance of a written contract executed by the parties to the action on the 23d day of October, 1903, but subsequently modified by parol, and the complaint also contains a count in assumpsit on a quantum meruit for the same labor performed and material furnished in constructing the well, and, as reasonable compensation therefor, judgment i<:,- the amount claimed under the contract is demanded.
A single cause of action being thus duplicated, counsel were required to determine before the commencement of the trial whether they would rely upon an alleged breach of the written contract or upon the implied obligation to- pay a reasonable amount as compensation, and they elected to proceed under the contract, but preserved an exception to the ruling of the court. Plaintiff in the action of Davis v. Tubbs, 7 S. D. 488, 64 N. W. 534, sought to recover on a written contract and also for the tortious acts of the defendant by which he sustained damages in not being able to complete the contract. In reversing a judgment in his favor, we said: “He must elect upon -which theory he will proceed, as the evidence required to sustain his action in the one form wlil be entirely different frorh that required to sustain the action in the other form.” At common law, where there was an express contract for a stipulated amount and a method of compensation for services performed and material furnished, it was not permissible to abandon the con
It is nowhere claimed that the well was completed according to the strict terms' of the written contract, which required the use of three-inch pipe for the first 300 feet, and nothing less than two-inch pipe below that depth, but it is alleged iri the complaint and shown by the testimony offered on behalf of appellant that the parties orally agreed before anything was done under the contract that, if hard rock was struck, one inch and a quarter pipe was to be used thereafter, and it was established that such rock was encountered at a depth of 890 feet, and it became absolutely necessary to use about 80 feet of such pipe.in the bottom of the well. While there .is some difference of opinion as to the volume of the flow, it must be conceded that without paying anything whatever, respondent obtained a valuable well, which furnished from 45 to 90 gallons of water per minute. That the pleader had reasonable ground to doubt the legality of the parol modification of the written contract is suggested by his effort to pursue a double remedy under the same state of facts for the enforcement of appellant’s right to recover in the action. Moreover, the fact that a verdict was directed in favor of respondent upon testimony sufficient to justify the jury in finding that the modified contract was fully performed on appellant’s part by the completion of a well in the manner shown by the undisputed evidence proves the necessity of setting forth the cause of action in two different forms. Concerning statutes prohibiting unnecessary repetition, and requiring a brief and concise statement of the facts as they actually took place, an eminent
This action being upon a written contract, which appellant claims was slightly modified by parol and faithfully carried out without any compensation from respondent, who was substantially benefitted by the transaction, it was impossible to- anticipate the judicial view as to the exact nature of the obligation or the state of the record at the conclusion of the trial, and it cannot he said that
As the conclusion that appellant should not have been required to elect is decisive of the appeal, the judgment entered against him upon a directed verdict is reversed, and a new trial ordered.
Concurrence Opinion
(concurring specially.) While concurring with the views of the presiding judge that the court erred in requiring the plaintiff to elect upon which cause of action he would proceed to lhc. trial, I am of the opinion that the judgment should also be reversed upon the ground that the court erred in directing a verdict in favor of the defendant. ■ In my judgment there was evidence on the part of the plaintiff tending- to prove that the plaintiff had substantially complied with the terms of the contract. The contract provides that it should “drill said well to the necessary depth to obtain sufficient flow of water to fill a two-inch pipe in a horizontal position.” It was further provided that “said well is ¡o be piped with three-inch standard Black pipe to a depth of 300 feet or deeper, if deemed necessary by the party of the first part and to be piped with two-inch standard Black pipe from thereon onto water-bearing sand rock, said two-inch pipe to be perforated where it passes through the water bearing artesian sand rock. Said two-inch pipe to extend up into the three-inch pipe not less than fifteen feet.” It is disclosed by the evidence on the part of the plaintiff that the terms of this contract were complied with down to the depth of about 890 feet, when hard rock was encountered, and that the 3-inch pipe and 2-inch pipe were used down to> the hard rock as specified in the contract; that the hole drilled
This was the view taken by this court of a building contract in the case of Aldrich et al. v. Wilmarth, 3 S. D. 523, 54 N W. 811, in which the plaintiff’s failure to literally comply with the terms of his contract was fully considered and discussed. Again, there was evidence on the part of the plaintiff tending to prove that the substitution of the 11 -4-inch pipe for the 2-inch pipe through and below • the hard rock was with the knowledge and consent of the defendant. It is true there was some conflict in the evidence upon this subject; but, if the jury believed from the evidence that the substitution of the 1 1-4-inch pipe for the 2-inch pipe, through and below the hard rock, was with the knowledge and consent of the defendant, he is estopped from .now claiming that the plaintiff failed to strictly comply with the terms of his contract in that regard. Mr. Sutherland in his w-ark on Damages (volume 3, § 710, 3d Ed.), in discussing this subject, says; “On the other hand, the want of objection and apparent acquiescence where there is knowledge of the actual character of the work would be a fraud on the contractor if he were thus encouraged to proceed, and still be at the hazard of losing all compensation except on terms of showing a punctilious performance of the contract.” The case therefore, should have been submitted -to the jury upon the evidence disclosed by the' record.
Concurrence Opinion
(concurring). The same cause of action having been stated in different counts, a method of pleading, in my opinion, neither necessary nor proper in this state under any circumstances, the learned circuit court did not err in requiring plaintiff to elect upon which count it would rely. But the question of substantial compliance with the contract on the part of the plaintiff should have been submitted to the jury under proper instructions; it being borne in mind that the principal object of the contract was to obtain a “sufficient flow of water to fill a two-inch pipe in a horizontal position.”