152 Ga. App. 489 | Ga. Ct. App. | 1979
Saint Joseph’s Hospital, Inc. negotiated a contract with a contractor to build a hospital in Chatham County, Georgia. On the default of the contractor its surety, Continental Casualty Company, assumed the obligation
After being awarded the contract Norair Engineering Corporation entered into a sub-contract with Erickson’s, Inc. for the plumbing and mechanical work which included installation of (1) bath tubs in patients’ rooms; (2) induction units for the heating and air conditioning systems; and (3) vacuum and oxygen outlets. This contract was modified by numerous amendments and change orders.
The hospital began operating the facility in June, 1970, although some work remained unfinished. In September, 1970, it gave Norair notice of termination of the contract. In January, 1971, it filed an action against Norair, Aetna Casualty, and others, seeking damages for delay and poor performance, amounts necessary to complete the hospital, an accounting, and for equitable relief to restrain enforcement of certain liens.
Norair and Aetna answered the complaint and counterclaimed against Saint Joseph’s and cross claimed against a number of sub-contractors, including Erickson’s. Erickson’s then filed its answer and cross claim against Norair for damages due under its sub-contract in the amount of $62,525.32. The original action ultimately involved some 22 separate parties and claims with reference to the construction of the hospital. For a general statement of facts in this multi-party and multi-claim litigation see Frank B. Wilder & Associates v. St. Joseph’s Hospital, 132 Ga. App. 373 (208 SE2d 145), and Norair Engineering Corp. v. Saint Joseph’s Hospital, 147 Ga. App. 595 (249 SE2d 642).
Because of numerous parties and the complexity of the issues the case was referred to an auditor. In order to avoid entangling the numerous litigants and the complex trial of the various issues between the principal litigants, the auditor heard the case by reducing it into a number of separate sub-cases. We are concerned here with the issues
The sole enumeration of error is that the trial court erred in awarding Erickson’s, Inc. interest on its
The auditor found that the stipulated balance of money due Erickson’s by Norair as to the subcontract was $60,825. The amount is not contested. Only the award of interest is contested. In Norair Engineering Corp. v. Saint Joseph’s Hospital, 147 Ga. App. 595, supra, at pages 604-605, this court held Code § 20-1408, would govern, and damages for the breach of contract may be increased by the addition of legal interest from that time until the recovery. However, the stipulated balance of the contract of Erickson’s, Inc. was found to be $60,825 due as of a date certain, and it became a liquidated claim at the time it was due. See Code § 57-110 which provides all liquidated demands, "where by agreement or otherwise the sum to be paid is fixed or certain, bear interest from the time the party shall become liable and bound to pay ...” In either view, the trial court did not err in awarding interest. However, on return of the remittitur the trial court is instructed to correct its final judgment to speak the truth as to the date from which interest was computed.
Judgment affirmed with direction.