This case arises in the aftermath of a settlement agreement which brought to an end a federal civil rights action filed by appellant and seven other plaintiffs against the District of Columbia and some of its employees. 1 Under the terms of the settlement, the District agreed to pay each plaintiff a specified sum of money; appellant’s portion was $6,500. In return, each plaintiff agreed to a voluntary dismissal of the lawsuit and executed a release discharging all named defendants from any and all future claims arising, directly or indirectly, from the occurrences alleged in the complaint.
The settlement was reached on February 26, 1996. With the exception of appellant, all the plaintiffs received their settlement payments promptly. As to appellant, however, the District conceded below that “through mistake, inadvertence, or error,” the settlement with appellant “did not enter the process for payment.” By the time the Corporation Counsel became aware of this oversight, on June 7, the District of Columbia’s settlement fund had exhausted its allocated resources for the quarter. On December 19, 1996, after nearly ten months had elapsed since the settlement and appellant still had not received his payment, he filed this breach of contract action in the Superior Court, seeking judgment for the principal amount plus interest, costs, and attorney’s fees.
On January 27, 1997, the District finally paid appellant the principal amount due under the settlement agreement. The parties then submitted cross-motions for summary judgment on the remaining claims. The trial court granted the District’s motion, ruling that appellant was not entitled to pre-judgment interest because the parties “did not contract for interest to be paid on the settlement amount.” 2 For the following reasons, we hold that the court erred in granting the District’s motion.
Under our case law, a trial court’s inquiry into whether D.C.Code § 15-108 mandates an award of pre-judgment interest in a given case is not limited to determining whether such interest is authorized by the underlying contract. For example, in
District of Columbia v. Pierce Associates, Inc.,
We applied similar reasoning in
District of Columbia v. Potomac Electric Power Co.,
Finally, in
Riggs National Bank v. District of Columbia,
On remand, the trial court should consider whether the payment of pre-judgment interest “is customary or usual under similar or comparable circumstances.”
Riggs,
The rule upon which appellant relies was succinctly stated by the Supreme Court more than a century ago: “If a debt ought to be paid at a particular time, and is not, owing to the default of the debtor, the creditor is entitled to interest from that time by way of compensation for the delay in payment.”
Young v. Godbe,
We stated in
Riggs
that “a statute providing for pre-judgment interest is remedial and should be generously construed so that the wronged party can be made whole.”
Where there has been such a deprivation, pre-judgment interest is an element of complete compensation for the loss of use of such money “from the time the claim accrues until judgment is entered, thereby achieving full compensation for the injury those damages are intended to redress.”
Id.
(quoting
West Virginia v. United States,
We therefore remand this case for a determination of whether common law or customary usage provides for the payment of prejudgment interest on a liquidated debt in cases “analogous in principle”
5
to the breach of a settlement agreement. If the trial court answers this question affirmatively, it should then decide the exact date on which the
Remanded for further proceedings.
Notes
. Butler, et al., v. District of Columbia, C.A. No. 93-1930 (D.D.C.1993).
. The court also denied appellant's request for costs and attorney’s fees. That part of the trial court's ruling was summarily affirmed by this court on March 12, 1998, and is no longer at issue.
. The District also argues that appellant's claim is barred by the doctrine of accord and satisfaction. It maintains that appellant’s acceptance of the principal amount under the terms of the release constitutes a complete settlement of all of his claims against the District, including the claim for interest. Appellant contends, however, and we agree, that the release covers only those claims arising from the events underlying the original civil rights action, and that it does not insulate the District from the consequences of acts and omissions which occurred after the release was executed. The District’s failure to meet its contractual obligation under the settlement agreement is legally unrelated to the events covered by the release. We hold accordingly that the release has no bearing whatever on appellant’s claim here.
. Despite the lack of contractual or statutory authorization, the District conceded that "usage” provided for payment of some pre-judgment interest; it challenged only the rate of interest awarded, arguing successfully that it was limited by D.C.Code § 28-3302(a) (1996) to six percent per annum.
Pierce Associates, supra,
.
Riggs, supra,
. Since the trial court did not reach this issue, we do not decide whether the District was obligated to máke payment immediately upon execution of the settlement agreement or at some later time.
