48 Minn. 13 | Minn. | 1892
.The agreement entered into between defendants Brown and Belden as owners of the real property, on which plaintiff claims a lien under the terms of Laws 1889, ch. 200, and defendant Burns, whereby the former sold and agreed to convey to the latter said property, required of Burns the erection and completion of three houses within a given period of time. Prompt performance of the conditions imposed upon the vendee was demanded in express terms, and time was made of the essence of the agreement. Two of the houses were seasonably completed, but the third was not, nor was it commenced. It stands undisputed that, had the plaintiff performed his labor under the old statute, (1878 G. S. ch. 90,) he would have been entitled to the relief demanded in the complaint, under the conclusion reached in Hill v. Gill, 40 Minn. 441, (42 N. W. Rep. 294,) —a case which has been followed a number of times. But shortly before the opinion in that case was filed the legislature passed a new law upon the subject, (chapter two hundred, [200,] supra,) in which there appeared a section wholly unlike any to be found in the various lien laws previously enacted in this state or elsewhere, so far as we have discovered. It is this section which has rendered the Hill-Gill Case inapplicable and of no force as an authority here, and has deprived the plaintiff of a statutory remedy which, beyond question, would be his, were it not for its incorporation into the statute of 1889. We refer to section four, (4,) which reads thus: “Sec. 4. Whenever the owner of land has sold the same upon an executory contract of sale contingent upon or providing for the erection, construction, alteration, removal to, or repair upon such land by the vendee thereof, of any house, mill, manufactory, or other building or appurtenance,-or of any fixture, wharf, fence, or other structure, if the vendee or his assigns shall forfeit or surrender such contract, then, for the purpose of establishing and enforcing a lien for all labor, skill, material, or machinery performed or furnished by other persons for or to such vendee or his assigns, under contract or subcontract for such erection, construction, alteration, removal, or repair, such vendee [vendor]
The respondent’s counsel have not questioned with much earnestness the soundness in some degree of the views above expressed, but have argued that their client is entitled to a lien by virtue of the provisions of section five (5) of chapter two hundred, (200,) which authorizes the enforcement of a lien claim whenever the work has been performed or the materials furnished with the knowledge of the owner of the land, he failing to object in a prescribed manner, and also that the word “forfeit,” as used in section four, (4,) shall be construed as meaning “to become by one’s own act or omission liable to be deprived of.” This definition of the word, should we adopt it, would prove valuable in all cases where default upon the part of the vendee could be established, but would be of no assistance in cases where a default could not be shown by competent evidence. But it is perfectly apparent from the manner in which the words “forfeit” and “surrender” are used, and their juxtaposition in the sentence, that the legislature intended that the right of lien provided for and conferred hy section four (4) should only be asserted when the contractual relations between the vendor and vendee have actually ceased to exist. An absolute and unconditional termination of the contract as between the parties thereto, either by proceedings in invitum or by operation of law or by mutual consent, is required, for it cannot be said that a contract has either been forfeited or surrendered so long as the right to rely upon or to enforce it remains. The word, used as it is in connection with “surrender, ” which undoubtedly means “yielded, rendered, or delivered up,” must be given its common and general definition, which is “lost, by omission or negligence or misconduct,” instead of the restricted meaning contended for, and ordinarily expressed by using the word “forfeitable.” In respect to the claim that the plaintiff is entitled to a lien under section five, (5,) we need but to call attention to the concluding sentence of that section, which provides that nothing therein “shall apply to such vendor as is mentioned in section fourthat is, to a vendor who has entered into an executory contract of sale contingent
The case is remanded, with instructions to the court below to modify and amend the judgment decree of date March 11, 1891, so that the several sums adjudged to be specific liens and charges, equal and co-ordinate with each other, shall be liens solely upon such right, title, and interest in the real property therein described, and in the buildings situate thereupon, as was held by defendant Burns on the 18th day of January, 1890, or has since been acquired by him.
(Opinion published 50 N. W. Rep. 1016.)