108 F. Supp. 217 | D. Alaska | 1952
By this action plaintiff seeks to recover damages from the defendant and his surety for breach of contract for the construction of a house, the cost of which was financed by the plaintiff bank.
When the defendant’s bid was accepted July 14, 1950, it was orally agreed that, pending the grant of a loan to the plaintiff and the furnishing of a bond by the defendant, work would immediately commence on the concrete basement, the cost of which, in case the loan or bond could not be obtained, would be paid for on a quantum meruit basis. Athough the loan was obtained and the parties reduced the agree
The defendant contends that the contract of July 14, was breached by plaintiff’s failure to obtain a loan and that the contract of October 5, is without consideration •because it merely obligated the plaintiff to do what he was already required to do under the original contract; and, in the alternative, that the contract was breached by plaintiff’s continual interference with the performance of work thereunder, which breach he adopted on or about May 15, 1951 and abandoned the job.
The defendant surety contends that the alteration of the contract was material and prejudicial, thereby discharging it from liability, and that there was a fraudulent concealment by plaintiff of material facts in connection with the assistance rendered the defendant in obtaining a bond. Since the first contention was disposed of adversely to the defendant’s surety on its motion to dismiss, it will not be discussed here.
A singular feature is that the work progress payments appear to have greatly exceeded the value of the work, but this point is not strenuously argued, although it is mentioned in the surety’s brief. In view of the derelictions referred to, however, the Court cannot find that the plaintiff should have been aware of the disparity between the value of the work done and the payments made, particularly since the cost of remedying the defective workmanship was shown to be, as is usually the case, wholly disproportionate to the result. Such defects account, at least in part, for the unwillingness on the part of the builders to submit bids for completion of the job.
The oral contract of July 14 provided for compensation on a quantum meruit basis, and, hence, differed materially from the written contract of October 5. There would, therefore, appear to be no basis for the contention of absence of consideration. I also find that the acts of the plaintiff, which the defendant asserts
From the facts recited, which I ■find, I conclude that the contract of October 5, 1950, was valid and that the plaintiff was warranted in treating the job as aban•doned and in terminating the contract on July 17, 1951.
Turning to the contention of the defendant surety, I find that it has failed to ■establish, by clear and convincing proof, Shat the plaintiff fraudulently concealed or misrepresented material facts in connection with the defendant’s application for a bond, it appears that it not only made no inquiry as to the state of affairs between the plaintiff and the defendant, but that it had bonded the defendant before in connection with similar contracts, and had not, in the instant case, even bothered to procure a copy of the contract. Moreover, with knowledge of the facts, it requested the defendant to refrain from resuming work and asked the plaintiff to obtain bids for the completion of the job as well as to submit other information to it, which warrants the inference or recognition of its liability. Indeed, the surety never denied its liability in conferences with the plaintiff or after his repeated demands that it proceed with the performance of its contract. These facts suffice to estop the surety from denying liability.
I find that the plaintiff spent and incurred liability for $6,484.54 in connection with the purchase of materials and performance of labor and that such materials and labor were reasonably necessary, except the expenditure of $25 by the plaintiff for the license of the defendant as contractor. I further find that the delay in completing the house from May 15, 1951 to December 31, 1952, cost the plaintiff in rentals, interest, storage charges and insurance on furniture $1,767.03, and that the cost of completing the job will be $11,300. Adding to this the $17,500 paid the defendant under the contract and subtracting the contract price of $17,540 results in total damages of $19,-486.57, for which plaintiff may have judgment.