56 Kan. 298 | Kan. | 1896
The opinion of the court was delivered by
Early in the year of 1888, Cydon Lodge No. 5, Knights of Pythias, of Salina, Kan., determined to erect a building upon real estate which it owned in Salina. To accomplish its purpose it was necessary to procure a loan upon the property. During the month of June, 1888, it applied to the Kansas Loan and Trust Company, of Topeka, for a loan of $20,000. While the application was pending, and before any loan was secured, the lodge procured plans and specifications for the building. During the month of August, 1888, the Kansas Loan and Trust Company notified the lodge that it had a customer who would make a loan of $20,000 to the lodge for the purpose of erecting the building. Immediately after this information was received the lodge advertised for bids for the construction of the building, and on August 27, 1888, the contract was let to Rutledge Bros., who entered into an agreement to furnish the material and
It is contended that the statement for a lien filed by Rutledge Bros, is fatally defective because it is not itemized as the law required. It is as follows :
“ Items :
“To contract price as per agreement........ $28,800 00
“ Value and amount of material furnished and labor performed up to the abandonment of contract and building by the owner....... $23,523 60
“ By cash paid.......................?..... 12,423 17
“ Balance.............................. $11,100 43”
Ulrich Bros, entered into a,contract with one of the subcontractors to furnish certain stone to be used in the erection of the building, and they have filed a statement and are attempting to enforce their lien for the unpaid balance due upon the contract. Do the provisions of the law extend to persons so remote as subcontractors of subcontractors, or are they limited to those who furnish material or perform labor under a subcontract with the original contractor? It is urged that under the rule of liberal construction subcontractors in the second or successive degree may be included. As mechanics’ liens are purely statutory, their operation and extent must be found within the terms of the statute creating and defining them. As the statutes confer special privileges upon one class of persons over others, it must clearly appear that those claiming the benefits of the statute are within its provisions. The law is entitled to a liberal interpretation in its application to all persons or classes who are within the protection of the statute, but this rule cannot be invoked to confer the special privileges and preferences of the law upon those not definitely included by the statute. ■ From a reference to the statute, it will readily appear that the person intended to be described by the term "subcontractor” is the one who directly contracts with the original contractor. So much of the provision as is pertinent to this question is as follows :
"Any person who shall furnish any such material*305 or perform such, labor under a subcontract with the contractor, or 'as an artisan or day laborer in the employ of such contractor, may obtain a lien upon such land,” etc. (Civil Code, §632.)
For the reasons mentioned, the judgment must be modified so far as it awards liens to Rutledge Bros, and to Ulrich Bros. ; but we find no prejudicial error in any other respect. When the judgment is so modified, it will stand affirmed.