185 Iowa 368 | Iowa | 1919
“The work will be inspected frequently by the engineer in charge, who will make an estimate on the first of each month, of the amount of work done during the preceding month, which, when properly certified, shall entitle him to payment of eighty per cent of the amount earned, and upon final completion of the work as a whole, * * * the engineer shall report to the board of supervisors, who will thereupon inspect the work, and if satisfactory, shall finally accept the same and order payment in full to the contractor.”
After making the contract, the defendant entered upon its work, and as the work progressed, it was furnished from time to time with estimates of the same by the engineer in charge, and received 80 per cent of the compensation as fixed by the 'contract, based upon the estimates given by the engineer. On the 6th day of August, 1912, upon the final estimate of the engineer in charge of the work, the board of supervisors ordered the payment to the defendant of the
In the first count of the petition, plaintiffs seek to recover a certain sum of money, which they claim was overpaid to the defendant. It is claimed that the estimates given by the engineer, upon which defendant received payment, were not based on the amount of earth actually removed in the construction of the ditch, but were figured and made as though said ditch, from the point of its commencement to the point of termination, was excavated through solid earth, whereas the ditch, at many places, intersected the Nishnabotna Biver, and little or no excavation was required there; that the defendant, as a matter of fact, did not excavate as many cubic yards of earth as shown by the estimates upon which it received payments; that, by reason of the method adopted by the engineer in making the estimates, the defendant received payment for more cubic yards of earth than were actually removed.
In the plans and specifications, it was provided that the ditch should run from a point called Station 1, in the center of the Nishnabotna Biver, to a point called Station 600, in the Nishnabotna Biver, as shown by plats and profile now on file with the county auditor of Pottawattamie County, which were made a part of the specifications.
This case was disposed of on demurrer. The petition discloses the fact that the engineer, in estimating the number of cubic yards for which defendant was entitled to receive compensation from the plaintiff, measured the number of cubic yards appearing in the excavation at the time the estimate was made. The contention of the plaintiff is that the engineer should have based his estimate upon the number of - cubic yards of earth actually removed by the defendant. The engineer was acting for and in behalf of the plaintiff, and was by the contract given the right to construe the contract. The plans and specifications were a part of the contract. The engineer evidently construed the agreement to mean that all the work should be paid for by the cubic yard, at 5.99 cents a cubic yard, measured in the excavation only. It is not claimed that any mistake was made in the measurement, or that any fraud was practiced by the defendant or by the engineer, in making the estimates, when made in this way. The only mistake, if a mistake at
The wording of the plans and specifications, on which the bid was made, is as follows: “All work shall be done and paid for by the cubic yard, measured in the excavation only.” It was the duty of the engineer to make monthly estimates showing the work done the preceding month, and .these estimates were made the basis of compensation, by the contract. The estimates indicated the number of cubic yards for which defendant was entitled to receive pay. The contract fixed the amount that it was entitled to receive for each cubic yard, as shown by such estimates. The contract provided that the board of supervisors should have general supervision of the work, but that the engineer appointed by the board should have charge of it in detail; and it was provided that all questions relating to plans of construction, or carrying on the work, or construing the intent or meaning of the specifications, should be referred to him, and that his decision should be final and binding on both parties. The contract was made on April 7, 1911. It appears that defendant immediately entered upon the work; that, as the work progressed, he was furnished, from time to time, with the estimates of the same by the engineer, and upon these estimates, payments were made. Prior to August 6, 1912, the defendant had been paid, upon the estimates furnished by the engineer, 80 per cent of the total amount shown to be due upon the estimates. On August 6, 1912, the final estimate of the engineer was made, and
Certain facts are apparent from this record: The engineer, in making his estimate of the amount of earth necessary to be removed, to consummate the contract, figured on the same basis pursued by him when making the final estimates of the work done. The original estimate of the amount of earth to be removed, and the monthly estimates of the amount of work actually done under the contract, totaled practically the same. Before the engineer made his estimates of the amount of earth to be removed within the limits of the. ditch designed, the course and distances had been determined upon and marked out, and defendant had before it, at the time it made its bid, the course and direction of the ditch, and all that the plans and specifications showed. In the proposal, it was recited that the defendant had examined the specifications and the form of the contract proposed by the plaintiffs, and he agreed to do the work on the sections designated, in all respects in accordance with the contract and specifications annexed. So we have both parties familiar with the course and length of the ditch, its location, the territory through which it passed, and that some of the ditch lay within the limits of the Nishnabotna River. Defendant had before it the estimates of the engineer as to the number of yards to be removed. Of course, this estimate did not limit, or control, or determine in advance, the number of cubic yards for which defendant was to be paid; but it indicated, before the contract was let, the method adopted by the engineer in estimating the number of cubic yards within the limits of the proposed ditch.
We hold, therefore, that, inasmuch as the parties had a right to make the contract in question, and did, in the contract, provide that the engineer selected should have charge of the detail of the work, and the power to construe the contract and to make the estimates according to the construction placed upon the contract by him, his construction and estimates, in the absence of fraud, are binding upon the plaintiffs, and the demurrer was properly sustained. We further find that the contract was susceptible of the construction placed upon it by the engineer. We therefore find that the demurrer was rightly sustained.