52 Wis. 240 | Wis. | 1881
The learned counsel for tbe appellant insists that tbe court erred —first, in refusing to permit him to give evidence, showing tbe circumstances of tbe parties, and tbe situation of tbe defendant’s land, at tbe time the contract was made, for tbe purpose of aiding in its construction; second, in refusing to permit him to show when and under what circumstances it was agreed that tbe stumps not pulled by plaintiff in 1877 should be pulled; third, in refusing to permit him to show that after tbe plaintiff quit work in 1878 tbe parties met and settled for tbe work already done, and that tbe amount unpaid was not to be paid for one year from May 1, 1878, and that tbe plaintiff agreed to go on and pull tbe remaining stumps after the crops were secured in 1878; fourth, in refusing to give instructions asked by tbe defendant, and in giving those excepted to by him.
We think tbe court should have permitted tbe defendant to show tbe situation and condition of bis. farm at tbe time the contract was made, and the use be was making of tbe lands upon which tbe stumps to be pulled were situated. Tbe contract is entirely silent as to the particular lands of tbe defendant upon which tbe stumps were situated which the plaintiff was to pull. Tbe contract says plaintiff was to pull all tbe stumps on tbe defendant’s land, etc. It in no way locates tbe land; and if it is to have a'broad interpretation, it might mean that plaintiff should pull all tbe stumps on defendant’s land, wherever situated, in or out of the state of Wisconsin, and that plaintiff should pull all tbe hard-wood stumps without compensation on bis land, even though there might not be
The plaintiff could make no case against the defendant at all without going outside of the contract and showing the circumstances under which the contract was made, in order to
The learned counsel for the plaintiff does not insist that the contract must necessarily be construed to authorize the plaintiff 'to continue his work until completion, in the spring and summer of 1878, irrespective of the consequences to the defendant, but that the question of the construction of the contract upon that point was wholly immaterial in determining
There is great force in the argument, and if the defendant did forbid the plaintiff without cause to continue the work at that time or at any other time, and there was no withdrawal on his part from that position, it would be quite immaterial what the construction of the contract should be as to when the work could be lawfully done by the plaintiff. Looking alone at the written notice to quit, given by the defendant, bearing date March 30, 1878, the refusal of .the defendant to permit the plaintiff to do any further work under the contract would be absolute; but there is evidence showing that the plaintiff did work after the notice to quit was given, with the consent of the defendant. The plaintiff admits this in his evidence, but he says that the defendant told him to quit when he had completed pulling certain stumps which had been theretofore marked for pulling by the plaintiff. It also appears that the defendant offered to show that after the written notice was given, and whilst plaintiff was still at work, he told him he did not intend to terminate the contract, but to stop his work until after he got his crops off, and that he could then go on and pull the remainder of the stumps, and that the plaintiff assented to that arrangement.
The evidence offered on the part of the defendant we think should have been admitted, under the pleadings, as tending to show that, notwithstanding the written notice to quit was absolute and unqualified, still the plaintiff was informed before lie
Whether the learned circuit judge erred in refusing to permit the defendant to show that it was expressly agreed be
Where there is any uncertainty or ambiguity in a written contract, the construction put upon it by the parties themselves is always received as evidence tending to aid in its con
The refusal of the court to give the instructions requested by the defendant, and the instructions given, were consistent with the theory upon which the learned circuit judge tried the action, except, perhaps, as to the charge that the plaintiff had an absolute right to recover the $261, the balance of the contract price for the stumps pulled, with interest. The court seems to have tried the case on the theory that the written contract was clear in all its provisions, and that by its terms the plaintiff was authorized to go on with his work and complete the same as rapidly as he could in the spring of 1878, without any regard to the injury he might do to the crops, meadow or pasture lands of the defendant; that the defendant had put an end to the contract absolutely by the notice of March 30, 1878; and that consequently the only question for
We are inclined to think the rule of damages was properly stated by the court; that the rule in case of a breach of contract for doing a specific work for a specified price is the profit the person would have realized had he been permitted to perform the work, and not the difference between the contract price and the sum the contractor actually received from other employments during the time he would have been employed in completing the work. The rule applicable to contracts for personal services does not apply to a case of this kind. 3 Parsons on Contracts, 781; Masterton v. Mayor of Brooklyn, 7 Hill, 61; P., W. & B. R. R. Co. v. Howard, 13 How. (U. S.), 307, 344; Fox v. Hardin, 7 Cush., 516; N. Y. & H. R. R. Co. v. Story, 6 Barb., 419.
The learned counsel for the respondent insists that this court ought not to consider the bill of exceptions in the case, for the reason that it appears to have been served on the respondent’s attorney more than sixty days after service of written notice of the entry of judgment. We cannot consider that question upon the hearing of the appeal. If the respondent claims the bill was not properly in the record, he should have moved either in this court or the court below to strike the same from the record. See Bergenthal v. Fiebrantz, 48 Wis., 435; Oliver v. Town, 24 Wis., 512; Sexton v. Willard, 27 Wis., 465. The bill, having been signed and settled by the trial judge, must be deemed to have been properly settled and signed; and the mere fact that it was settled and signed after the time fixed by section 2876, R. S., does not necessarily show that it is improperly in the record. This court has repeatedly held that a bill may be served and settled after the time limited by said section. And the bill appearing in the record
For the errors of the court in excluding the evidence'offered by the defendant, the judgment must be reversed.
By the Court.— The judgment of the circuit court is reversed, and the cause remanded for a new trial.