52 S.W.2d 147 | Tenn. | 1932
On rental of equipment, see annotation in 43 L.R.A. (N.S.), 171; R.C.L. Perm. Supp., p. 5242.
As to nature of labor or materials, see annotation in 43 L.R.A. (N.S.), 162; L.R.A., 1915F, 951. Complainant is the owner of a steam boiler which he rented to Baird and Company, for use in the execution of a contract to construct a state highway bridge. The boiler was used to generate power to force water through hollow piles; the water serving to remove the earth beneath the piles, so that they could be lowered to a depth that would permit the operation of an ordinary pile driver. The regular equipment of Baird and Company included a pile driver, operated by a boiler and engine, but the piles being too long to be started by the pile driver, the additional boiler was necessary to operate the water pump. The contract was that complainant, otherwise employed on the bridge construction at aper diem wage, should receive forty cents an hour for the use of the boiler. This rental charge, amounting to $646, is the subject of this suit.
Complainant was awarded a decree by the Chancellor against Baird and Company, but recovery was denied against the surety on the construction bond, on the ground that the bond does not cover the amount due by the contractor for rental of machinery. On complainant's appeal, the decree of the Chancellor was affirmed by the Court of Appeals. We have heretofore granted complainant's petition for the writ of certiorari, to review the decree of the latter court. *92
The bond of the surety, Southern Surety Company, is the statutory bond authorized by Acts 1917, chapter 74. SouthernConst. Co. v. Halliburton,
Complainant contends that the boiler was material used in the construction of the bridge, and that all that was purchased was its use for the requisite number of hours, which was consumed in the execution of the construction contract.
In Southern Const. Co. v. Halliburton, supra, analogy was found between the liability of the surety on this statutory bond and the liability of a property owner under the mechanic's lien statutes, and it was held that the surety is liable only for "material consumable in the use or intended to be consumed in the use." The Court said: "It would be too broad a construction of this statute to fasten such a liability upon the general contractor and the surety for materials which the subcontractor purchased, which were not used up in the job, and remained the property of the subcontractor to be thereafter used by him in other work."
The mechanic's lien statutes, the statutes creating liens on railroads in favor of the furnishers of labor and materials in their construction, and the statutes requiring *93
the execution of bonds by persons engaged in public works, have been found to contain similar provisions with respect to the protection afforded furnishers of materials, and it has been clearly intimated by this Court that a uniform construction and application of the several statutes in this regard is both possible and desirable. Consolidated Engineering Co. v. Wedow Myers,
On the authority of Pittsburg Coal Co. v. So. Asphalt Const. Co.,
In Pittsburg Coal Co. v. So. Asphalt Const. Co., supra, the Court, recognizing the change in methods of constructing buildings and other improvements from time to time, expressed the view that legislation for the protection of materialmen and laborers is not rigid but is flexible, to be enforced in such manner as to afford the protection intended. The Court said: "The statute under consideration was passed for the protection of laborers *94 and the furnishers of material on public works, and the inquiry should not be limited to the method by which the contract is performed."
The essential requirement that materials be consumed in the execution of the principal contract, in order that their cost be secured by a lien on the building constructed, or by the contractor's bond for a public works project, is supported by two obvious reasons. If the material furnished is not consumable in the use, it is furnished on the general credit of the contractor and not merely in aid of the performance of the particular contract. And if on the completion of the building or project the material, still possessing value, remains the property of the contractor, liability for its cost should be and is his liability alone, unless under the conditions recognized in York Lumber Mfg. Co. v. McKnight Mertz,
The fact that this Court has not heretofore been called upon to rule the question presented by complainant's claim should not prejudice its consideration.
In Illinois Surety Company v. John Davis Company,
Royal Indemnity Co. v. Day Maddock Co., ___ Ohio St., ___,
Our cases repudiate the rule, adhered to in some jurisdictions, that materials, to be lienable, must be incorporated into the structure or public work for which the principal contract was executed. Cohn Goldberg v. Construction Co.,
Complainant's boiler was not a part of the regular equipment of the contractor, but was engaged for the particular and special use hereinabove described. The case of Luttrell v. Railroad,
The decree of the Court of Appeals is accordingly reversed, and decree will be rendered here against the Surety Company for the amount claimed, with interest from the date the bill was filed. The cause will be remanded to the Chancery Court of Davidson County for execution, in view of the decree there rendered against Baird and Company, from which there was no appeal. *97