Nicholas v. VanNicholas v. Van
Anthony Nicholas brought this action against the City of Griffin and David and Vicki Van. The city was granted summary judgment on the ground that Nicholas failed to give proper ante litem noticе of his claim within the six-month period prescribed by
The facts are largely undisputed. In September 1996, Nicholas sold a tract of commercial property, which was contiguous to his own remaining property, to David and Vicki Van. 1 The Vans were also granted an easement of ingress and egress, and both parties reserved certain rights to develop their respective properties. On July 30, 1997, the Vans submitted a development plan to the city, which was approved October 27, 1997. Nicholas first saw the plan on Fеbruary 17, 1998. On August 13, 1998, ante litem notice was delivered to the city on Nicholas’s behalf. The letter recited that the city relied on the Vans’ “misinterpretation” of the easеment, which caused access and parking problems related to Nicholas’s property. The letter went on to notify the city of Nicholas’s claim that the сity was negligent in approving the Vans’ development plan and stated the monetary damages suffered by Nicholas at that time. 2 In January 1999, Nicholas filed this action against the Vans and the city, alleging among other things that the city’s approval of the development plan without consultation with Nicholas had deprived him of the usе and enjoyment of his property and constituted a taking without just and adequate compensation. He further alleged that the city’s actions “had the effect of nullifying the agreement between” Nicholas and the Vans.
On motion for summary judgment filed by the city, the trial court concluded that Nicholas presented his claim against the city outside the six-month notice requirement of
Under
It is undisputed that the сity approved the Vans’ development plan on October 27, 1997, and it was this act that constituted the basis of Nicholas’s action against the city. The statutory six-month timе period within which he was required to provide notice to the city therefore began on that date and expired April 27, 1998. Although Nicholas saw the development plan in February 1998, well within the six-month period, the required notice was not delivered to the city until August 13, 1998. Consequently, the trial court correctly concluded that his action аgainst the city is barred.
Nicholas argues that the development plan was approved only after the Vans acquired another parcel, appаrently along the north side of their property, to accommodate extra parking spaces and that pedestrian access to the Vans’ property from these spaces was across his property. He complains that he was not notified of the Vans’ application for development and that the city did not consult with him regarding the development plan before its approval. Based on these facts, Nicholas argues that the six-month notice period was tolled until he became aware of the plan on February 17, 1998.
Nicholas relies heavily on
Nicholas compares this case to a real estate transaction in which a seller fails to disclose latent defects to a buyer, defects that were undiscoverable upon a reasоnable examination. See
Ben Farmer Realty Co. v. Woodard,
We note that the appropriate vehiсle for disposing of the claim is dismissal of the complaint against the city. “In cases where the merits [cannot be] reached because of the failure of the plaintiff to satisfy a precondition, the appropriate action is dismissal of the case on motion.”
Jones v. City of Austell,
Judgment vacated and case remanded with direction.
Notes
It appears that Nicholas’s chiropractic clinic was situated on his property, while the tract sold to the Vans was to be used to accommodate the expansion of their medical facility.
It also appears that approximately оne month before delivery of the ante litem notice to the city, a letter was sent to the city building inspector on behalf of Nicholas, which discussed issues related to parking spaces on the Vans’ property.