Plaintiff Niagara Mohawk Power Corporation (“Niagara”) is a utility engaged in the business of generating and distributing electric power to consumers in the State of New York. Seeking relief from a number of long-term contracts
Section 210 of PURPA’s Title II, 16 U.S.C. § 824a-3, encourages the development of cogeneration and small power production facilities, which Congress believed would reduce the demand for traditional fossil fuels. Section 210(a), 16 U.S.C. § 824a-3(a), directs FERC, in consultation with state regulatory authorities, to promulgate rules necessary to encourage such power production, including rules requiring utilities to offer to sell electricity to, and purchase electricity from, QFs. Section 210(f)(1) obligates state regulatory agencies such as the PSC to implement FERC rules through their own rulemak-ing, in particular those pertaining to electric utilities’ obligation to purchase power from QFs. 16 U.S.C. § 824a-3(Q(l) (2000).
PURPA and its regulations prohibit FERC from “providing] for a rate which exceeds the incremental cost to the electric utility of alternative electric energy.” 16 U.S.C. § 824a-3(b). An electric utility’s incremental cost is the cost that the utility would incur in generating the electric energy itself or purchasing it from another source. 16 U.S.C. § 824a-3(d). Incremental cost is also referred to as avoided cost. 18 C.F.R. § 292.101(b)(6) (2001).
In 1980, the New York legislature enacted New York Public Service Law § 66-c, which provided that the PSC would require state-regulated electric utilities to
Niagara initiated this action in May 1995. Its First Amended Complaint alleged that the incremental cost limitation contained in PURPA and FERC implementing regulations preempts both the New York legislature’s ability to enact the Six-Cent Law and the PSC’s ability to enforce it. The complaint alleged one claim against the PSC and its commissioners, for violations of PURPA, PURPA regulations, and the Supremacy Clause of the Constitution, U.S. Const, art. VI, cl. 2, and one claim against FERC, for violations of PURPA and the Administrative Procedure Act (the “APA”), 5 U.S.C. § 551 et seq.
Defendants moved to dismiss the complaint pursuant to Fed.R.Civ.P. 12(b)(1) and (6), arguing that there was no federal subject matter jurisdiction over Niagara’s claims and that, in any event, Niagara failed to state a claim upon which relief could be granted. The District Court (Norman A. Mordue, Judge) granted defendants’ motion and dismissed the complaint in its entirety, in part for a lack of subject matter jurisdiction and in part for failure to state a claim. Niagara,
We affirm the District Court’s dismissal of Niagara’s complaint, albeit on slightly different reasoning. We agree with the District Court’s analysis with respect to the claims against FERC, which were properly dismissed with prejudice, and the PURPA claim against the PSC and. its commissioners, which was properly dismissed for, lack of subject matter jurisdiction because of Niagara’s failure to exhaust its administrative remedy by pursuing the claim with FERC in the first instance. We disagree, however, with the District Court’s analysis with respect to the Supremacy Clause claim against the PSC and its commissioners, which also should have been dismissed for lack of subject'matter jurisdiction because of Niagara’s failure to exhaust its administrative remedy.
DISCUSSION
We review the District Court’s dismissal of Niagara’s complaint de novo, accepting all factual allegations contained in the complaint as true and drawing all reasonable inferences in Niagara’s favor. Chambers v. Time Warner, Inc.,
I. Claims Against FERC
Niagara alleges two claims against FERC, one for violation of PURPA and
A. PURPA Claim
As the District Court held, Niagara cannot maintain a claim against FERC under PURPA for the simple reason that no such claim exists. The only private right of action under PURPA arises from § 210(h)(2)(B) of that statute. See 16 U.S.C. § 824a-3(h)(2)(B). That subsection permits “[a]ny electric utility, qualifying cogenerator, or qualifying small power producer” to petition FERC to enforce PURPA “against a State regulatory authority or nonregulated electric utility” and, if FERC does not initiate an enforcement action, to bring an action in district court “to require such State regulatory authority or nonregulated electric utility” to comply with PURPA. Id. Because FERC is neither a “State regulatory authority” nor a “nonregulated electric utility,” Niagara may not sue FERC under PURPA. See Compl. ¶ 9 (stating that “[FERC] is an agency of the United States”); see also N.Y. State Elec. & Gas Corp. v. Saranac Power Partners, L.P.,
B. APA Claim
Niagara also asserts a claim against FERC under the APA. In order to pursue such a claim, Niagara must show that either (1) the FERC action of which Niagara seeks judicial review is “made reviewable by statute” or (2) “there is no other adequate remedy in a court.” 5 U.S.C. § 704 (2000). Niagara does not argue that any statute provides for judicial review of FERC decisions interpreting PURPA and, indeed, no statute so provides. Niagara does argue, however, that it has no other adequate judicial remedy. In particular, Niagara argues that unless it can obtain judicial review of FERC’s ruling under the APA in an action against FERC, “its remedy against the PSC is not adequate.” (Br. for Pl.-Appellant at 51.) We disagree. As the District Court noted, the Court of Appeals for the D.C. Circuit ruled, in a previous stage of this litigation, that a district court “is perfectly capable” of “determinfing] whether [FERC’s] interpretation of [PURPA] is reasonable ... even if [FERC] chooses not to intervene.” Niagara,
Moreover, the complaint itself acknowledged that Niagara may obtain complete relief with respect to all of the contracts at issue if “the minimum rate provision of the Six-Cent law” is declared invalid and Niagara is permitted to “withdraw its SC-6
II. Claims Against the PSC and Its Commissioners
Niagara asserts two claims against the PSC and its commissioners, alleging that these defendants have violated both PURPA (and attendant regulations) and the Supremacy Clause. While these two claims have different labels, however, they share identical legal and factual theories. Niagara alleges, “The PSC, in the ways described, has violated the incremental cost limitation of PURPA, 16 U.S.C. § 824a-3(b), (d), the avoided cost limitation of the regulations issued by FERC pursuant to PURPA, 18 C.F.R. §§ 292.340(a)(2) [sic], 292.101(b)(6), and the Supremacy Clause of the Constitution, Art. VI, Cl. 2.” (Compl-¶ 33.) The District Court assumed that “Niagara’s Supremacy Clause claim is based on PSC’s continued implementation of the Six-Cent Law as grandfathered by amendments to the N.Y. Pub. Serv. Law in spite of the avoided cost limitation set forth in PURPA.” Niagara,
The court dismissed Niagara’s PURPA claim because it “has no subject matter jurisdiction over any claim against PSC based on PURPA in the absence of proof that Niagara complied with the jurisdictional pre-requisites of [§■ 210(h)(2)(B)]” by first petitioning FERC for relief. Niagara,
A. Exhaustion of Administrative Remedy
As discussed in section I. A., supra, PURPA § 210(h)(2)(B) permits an electric utility such as Niagara to maintain a private action against a state regulatory authority such as the PSC, provided the utility first satisfies certain administrative prerequisites. 16 U.S.C. § 824a-3(h)(2)(B). Before Niagara may sue the PSC in district court for a violation of PURPA, Niagara must first petition FERC to enforce PURPA against the PSC. Id. If FERC does not initiate an enforcement action against the PSC within sixty days following Niagara’s petition, Niagara may bring an action in district court to require the PSC to comply with PURPA. Id. Referring to the requirements of § 210(h)(2)(B), the District Court stated, “It is undisputed that Niagara did not follow this procedure prior to commencement of the
The District Court found that Niagara was not required to comply with the exhaustion requirement of § 210(h)(2)(B) before bringing its Supremacy Clause claim. Niagara,
In arguing that it has asserted a viable Supremacy Clause claim, Niagara relies upon the decision of the Third Circuit in Freehold Cogeneration Associates v. Board of Regulatory Commissioners of New Jersey,
In addition to the statutory requirement, there is also a prudential reason for requiring Niagara to exhaust its administrative remedy. Niagara objects to FERC’s decision to apply its ruling in Connecticut Light & Power Co.,
B. Other Issues
The District Court dismissed Niagara’s Supremacy Clause claim as against the PSC on the basis of res judicata, Niagara,
CONCLUSION
Accordingly, we affirm the judgment of the District Court.
Notes
. These long-term contracts are known as “power purchase agreements,’’ or “PPAs.”
. A “cogeneration facility” is:
a facility which produces—
(i) electric energy, and
(ii) steam or forms of useful energy (such as heat) which are used for industrial, commercial, heating, or cooling purposes.
16 U.S.C. § 796(18)(A) (2000). A “qualifying cogeneration facility” is:
a cogeneration facility which—
(i) [FERC] determines, by rule, meets such requirements (including requirements respecting minimum size, fuel use, and fuel efficiency) as [FERC] may, by rule, prescribe; and
(ii) is owned by a person not primarily engaged in the generation or sale of electric power (other than electric power solely from cogeneration facilities or small power production facilities).
Id. § 796(18)(B).
. The D.C. Circuit held that it lacked jurisdiction to review two FERC declaratory orders interpreting PURPA because the orders, which had not been the subject of a district court enforcement action, "do[ ] nothing more than state how the FERC interprets its own regulations” and "ha[ve] no legally binding effect.” Niagara,
