Niagara Mohawk Power Corp. v. Federal Energy Regulatory CommissionNiagara Mohawk Power Corp. v. Federal Energy Regulatory Commission
Plaintiff Niagara Mohawk Power Corporation (“Niagara”) is a utility engaged in the business of generating and distributing electric power to consumers in the State of New York. Seeking relief from a number of long-term contracts
Section 210 of PURPA’s Title II,
PURPA and its regulations prohibit FERC from “providing] for a rate which exceeds the incremental cost to the electric utility of alternative electric energy.”
In 1980, the New York legislature enacted New York Public Service Law § 66-c, which provided that the PSC would require state-regulated electric utilities to
Niagara initiated this action in May 1995. Its First Amended Complaint alleged that the incremental cost limitation contained in PURPA and FERC implementing regulations preempts both the New York legislature’s ability to enact the Six-Cent Law and the PSC’s ability to enforce it. The complaint alleged one claim against the PSC and its commissioners, for violations of PURPA, PURPA regulations, and the Supremacy Clause of the Constitution,
Defendants moved to dismiss the complaint pursuant to
We affirm the District Court’s dismissal of Niagara’s complaint, albeit on slightly different reasoning. We agree with the District Court’s analysis with respect to the claims against FERC, which were properly dismissed with prejudice, and the PURPA claim against the PSC and. its commissioners, which was properly dismissed for, lack of subject matter jurisdiction because of Niagara’s failure to exhaust its administrative remedy by pursuing the claim with FERC in the first instance. We disagree, however, with the District Court’s analysis with respect to the Supremacy Clause claim against the PSC and its commissioners, which also should have been dismissed for lack of subject'matter jurisdiction because of Niagara’s failure to exhaust its administrative remedy.
DISCUSSION
We review the District Court’s dismissal of Niagara’s complaint de novo, accepting all factual allegations contained in the complaint as true and drawing all reasonable inferences in Niagara’s favor. Chambers v. Time Warner, Inc.,
I. Claims Against FERC
Niagara alleges two claims against FERC, one for violation of PURPA and
A. PURPA Claim
As the District Court held, Niagara cannot maintain a claim against FERC under PURPA for the simple reason that no such claim exists. The only private right of action under PURPA arises from § 210(h)(2)(B) of that statute. See
B. APA Claim
Niagara also asserts a claim against FERC under the APA. In order to pursue such a claim, Niagara must show that either (1) the FERC action of which Niagara seeks judicial review is “made reviewable by statute” or (2) “there is no other adequate remedy in a court.”
Moreover, the complaint itself acknowledged that Niagara may obtain complete relief with respect to all of the contracts at issue if “the minimum rate provision of the Six-Cent law” is declared invalid and Niagara is permitted to “withdraw its SC-6
II. Claims Against the PSC and Its Commissioners
Niagara asserts two claims against the PSC and its commissioners, alleging that these defendants have violated both PURPA (and attendant regulations) and the Supremacy Clause. While these two claims have different labels, however, they share identical legal and factual theories. Niagara alleges, “The PSC, in the ways described, has violated the incremental cost limitation of PURPA,
The court dismissed Niagara’s PURPA claim because it “has no subject matter jurisdiction over any claim against PSC based on PURPA in the absence of proof that Niagara complied with the jurisdictional pre-requisites of [§■ 210(h)(2)(B)]” by first petitioning FERC for relief. Niagara,
A. Exhaustion of Administrative Remedy
As discussed in section I. A., supra, PURPA § 210(h)(2)(B) permits an electric utility such as Niagara to maintain a private action against a state regulatory authority such as the PSC, provided the utility first satisfies certain administrative prerequisites.
The District Court found that Niagara was not required to comply with the exhaustion requirement of § 210(h)(2)(B) before bringing its Supremacy Clause claim. Niagara,
In arguing that it has asserted a viable Supremacy Clause claim, Niagara relies upon the decision of the Third Circuit in Freehold Cogeneration Associates v. Board of Regulatory Commissioners of New Jersey,
In addition to the statutory requirement, there is also a prudential reason for requiring Niagara to exhaust its administrative remedy. Niagara objects to FERC’s decision to apply its ruling in Connecticut Light & Power Co.,
B. Other Issues
The District Court dismissed Niagara’s Supremacy Clause claim as against the PSC on the basis of res judicata, Niagara,
CONCLUSION
Accordingly, we affirm the judgment of the District Court.
Notes
. These long-term contracts are known as “power purchase agreements,’’ or “PPAs.”
. A “cogeneration facility” is:
a facility which produces—
(i) electric energy, and
(ii) steam or forms of useful energy (such as heat) which are used for industrial, commercial, heating, or cooling purposes.
a cogeneration facility which—
(i) [FERC] determines, by rule, meets such requirements (including requirements respecting minimum size, fuel use, and fuel efficiency) as [FERC] may, by rule, prescribe; and
(ii) is owned by a person not primarily engaged in the generation or sale of electric power (other than electric power solely from cogeneration facilities or small power production facilities).
. The D.C. Circuit held that it lacked jurisdiction to review two FERC declaratory orders interpreting PURPA because the orders, which had not been the subject of a district court enforcement action, "do[ ] nothing more than state how the FERC interprets its own regulations” and "ha[ve] no legally binding effect.” Niagara,