Ng Bros. Construction, Inc. v. CranneyNg Bros. Construction, Inc. v. Cranney
The plaintiff, Ng Brothers Construction, Inc. (plaintiff), filed a complaint in the Superior Court, seeking in Count III to enforce its mechanic’s lien rights against the defendants, John Cranney, Naomi Cranney, and Nevena Cranney.
1. Background. We summarize undisputed material facts drawing on the Superior Court judge’s memorandum on the cross motions for partial summary judgment. In March, 1997, the defendants and the plaintiff entered into a written contract for the renovation of the defendants’ home. The plaintiff agreed to act as general contractor in connection with the renovation, with authority to subcontract various aspects of the work; the defendants agreed to pay the plaintiff a fixed fee of $880,000 on a payment schedule. Soon the plaintiff claimed that the defendants continuously breached the agreed-on payment terms and that they sought various modifications necessitating change orders and delays in the work schedule. In the fall of 1997, a dispute arose concerning the plaintiff’s failure to include the framing costs of the project in the contract price. The defendants hired Robert Bross as the owners’ representative to supervise and deal with the plaintiff and (among other duties) to maintain a daily log of its efforts.
In late October, the plaintiff stopped work because of the
On January 26, 1998, the parties sought to settle some of their differences by agreeing to a partial release, and on January 29, the plaintiff filed a notice of dissolution of its lien pursuant
The plaintiff subsequently commenced this lawsuit against the defendants asserting, in Count III, its entitlement to the enforcement of a mechanic’s lien under G. L. c. 254. The defendants moved for summary judgment on Count III arguing that the plaintiff’s second notice of contract and statement of account were untimely filed. The plaintiff filed a cross motion for summary judgment contending that the mechanic’s lien was properly perfected because it had timely complied with the pertinent provisions of
A Superior Court judge allowed the defendants’ motion for summary judgment and deified the plaintiff’s cross motion for summary judgment. Although neither party briefed or argued the issue, the judge concluded that the plaintiff failed to perfect its lien rights because it did not file a notice of substantial completion, a document the judge determined was a condition precedent to the filing of a notice of contract and statement of account, see
2. Statutory framework and ruling of Superior Court judge. The initial issue for decision is whether a notice of substantial completion is a condition precedent to the recording of a valid and enforceable notice of contract and statement of account,
The mechanic’s lien statute provides “that a debt due to a person who performs labor or supplies material for the improvement of real estate by agreement or with the express or implied consent of the owner is secured by a mechanic’s hen.” Hammill-McCormick Assocs., Inc. v. New England Tel. & Tel. Co.,
Although
Further, the express language of
3. Plaintiff’s perfection of its mechanic’s lien. The parties’ summary judgment motions turn on whether the plaintiff perfected its mechanic’s lien within the time periods required by
Summary judgment is granted where there are no issues of genuine material fact, and the moving party is entitled to judg
“[N]ot later than the earliest of: (i) sixty days after fifing or recording of the notice of substantial completion . . . or (ii) ninety days after fifing or recording of the notice of termination ... or (iii) ninety days after such person or any person by, through or under him last performed or furnished labor or materials or both labor and materials.”
“Liens under sections two and four shall be dissolved unless the contractor, subcontractor, or some person claiming by, through or under them, shall not later than the earliest of: (i) ninety days after the filing or recording of the notice of substantial completion under section two A; (ii) one hundred and twenty days after the filing or recording of the notice of termination under section two B; or (iii) one hundred and twenty days after the last day a person, entitled to enforce a lien under section two or anyone claiming by, through or under him, performed or furnished labor or material or both labor and materials . . . file or record ... a statement, giving a just and true account of the amount due or to become due him.”
The plaintiff’s second notice of contract was recorded on March 9, 1999, and its second statement of account on June 3, 1999. Thus, pursuant to
The defendants submitted the following summary judgment materials as evidence that the plaintiff last worked on the project on July 18, 1998, and that it was “off the project” by August 1998: (1) the plaintiff’s own internal time records, payment records, and correspondence concerning the project; (2) the deposition testimony of the plaintiff’s construction supervisor and of
The plaintiff’s internal time cards are weekly records of the time it worked on the project. The last time card was for the week of July 18, 1998, and it states that Jack Ng worked a total of four hours at the defendants’ residence that week. The plaintiff’s payment records indicate that the last payment made to its subcontractors on the defendants’ project was November 20, 1998, and the last payment to its day laborers was September 11, 1998. The plaintiff’s business correspondence, written contemporaneously with the project, states that the plaintiff was off the project as of August, 1998.
In response to the defendants’ summary judgment motion, the plaintiff filed affidavits from its construction supervisor, office manager, and two subcontractors it retained to provide plumbing and electrical services in connection with the defendants’
In his affidavit, the plaintiff’s construction supervisor states that he last remembers meeting employees of one of the subcontractors at the defendants’ residence some time in March, 1999, and that he was there “as part of our management and coordination ... of the Project.” He further states that he continued to supervise the subcontractors’ work from the plaintiff’s office with the assistance of the office manager. The office manager avers that she supervised the project through March 10, 1999, and that the subcontractors worked under the plaintiff’s supervision beyond the date on which the suit was filed (August 30, 1999). The plumbing subcontractor states in his affidavit that he last performed services at the project on February 27, 1999. The affidavit of the electrical subcontractor asserts that he was present at the defendants’ residence on January 22, 1999, when an electrical inspection took place, and that he last visited the residence on March 10, 1999, when he attempted to install a chandelier. Both subcontractors aver that “[tjhroughout this entire period, [they] coordinated [their] work with Ng . . . as general contractor.”
Although both subcontractors claim that they still considered themselves “on [the] job” because they have never received written cancellation from the defendants, neither subcontractor stated that any representative of the plaintiff supervised their work or was present at the site, or that services performed in connection with the subcontract were supervised by the plaintiff.
By contrast, documentary evidence presented by the defendants (the plaintiff’s internal time records, payment records, and related correspondence for the project) indicate that neither the plaintiff, nor its subcontractors, was providing labor or materials after February 3, 1999. The bare assertion to the contrary in the plaintiff’s affidavits raises no genuine issue of material fact. See Community Nat’l Bank v. Dawes,
The plaintiff’s submissions contain only conclusory allegations. They fail to define the scope of the services provided, the exact dates on which the plaintiff provided the labor, and the nature of the alleged supervision it performed during the relevant period. If the plaintiff had specific facts relating to its supervision of the project during the period in question, it did not present them to the motion judge. See id. An adverse party may not manufacture disputes by conclusory factual assertions; such attempts to establish issues of fact are not sufficient to defeat summary judgment.
The plaintiff’s additional arguments are likewise without merit. It argues that the defendants offer no proof that the subcontractors were working for the defendants and not for the plaintiff during the lien perfection period. In view of the evidence submitted by the defendants, the burden is on the plaintiff to present “specific facts which establish that there is a genuine, triable issue, or summary judgment. . . will be entered against [it].” Community Nat’l Bank v. Dawes, supra at 554. The plaintiff cannot defeat summary judgment by claiming that the defendants have not presented evidence sufficient to warrant summary judgment; rather, the plaintiff must provide concrete evidence that supports a contrary determination.
The plaintiff further maintains that the issue whether its construction supervisor was on site in March, 1999, is “ir
The plaintiff contends that Brass’s journal may not be considered to refute the testimony of the subcontractors because it does not relate to any time beyond February 19, 1999. It claims that, because it was working at the site after February 19, 1999, the journal is of no evidentiary significance. The plaintiff again misconceives the burden here. It is the plaintiff that must prove it was supervising the project until at least February 3, 1999. Absence of evidence to the contrary does not constitute evidence that the plaintiff was doing so. Finally, the plaintiff asserts that, even if the subcontractors’ work were minor, this does not undermine the mechanic’s hen. However, we have found no evidence that the subcontractors performed even minor work for the plaintiff during the time period in issue.
4. Conclusion. Accordingly, based on the summary judgment materials before us, the plaintiff has not presented sufficient evidence to defeat the defendants’ motion for summary judgment on Count HI. We affirm the judgment for the defendants.
So ordered.
Notes
The complaint contained two other counts against the defendants, one for breach of contract and the other for unjust enrichment, neither of which was at issue in the summary judgment motion.
“A person entering into a written contract with the owner of any interest in real property ... for the whole or part of the erection, alteration, repair or removal of a building, structure, or other improvement to real property, or for furnishing material or rental equipment, appliances, or tools therefor, shall have a lien upon such real property, land, building, structure or improvement owned by the party with whom or on behalf of whom the contract was entered into, as appears of record on the date when notice of said contract is filed or recorded ... to secure the payment of all labor, including construction management and general contractor services, and material or rental equipment, appliances, or tools which shall be furnished by virtue of said contract. ...”
“Liens under sections two and four shall be dissolved unless the contractor, subcontractor, or some person claiming by, through or under them, not later than the earliest of: (i) ninety days after the filing or recording of the notice of substantial completion under section two A; (ii) one hundred and twenty days after the filing or recording of the notice of termination under section two B; or (iii) one hundred and twenty days after the last day a person, entitled to enforce a lien under section two or anyone claiming by, through or under him, performed or furnished labor or material or both labor and materials or furnished rental equipment, appliances or tools, file or record ... a statement, giving a just and true account of the amount due or to become due him, with all just credits, a brief description of the property, and the names of the owners set forth in the notice of contract. . . . Nothing in this section shall prohibit the filing or recording of a statement under this section prior to the filing or recording of the notices under section two A or two B.”
The summary judgment record includes three such letters from the plaintiff. In response to an invoice from Hatch Cabinet Designs, the plaintiff transmitted the following facsimile message on September 9, 1998: “Jack Cranney took over the rest of job. He is the one responsible to pay. Nothing to do with the plaintiffs.” In a facsimile cover letter dated September 14, 1998, to Paul Santos of the Asian American Bank, the plaintiff’s office manager states that, “we really don’t know how many supply companies [and] subcontractors will ask for money after Jack Cranney took over everything on [August 6, 1998].” Finally, a letter dated November 13, 1998, from the plaintiff to Paul Santos provides, “I hope you can send a letter to Town of Belmont, stated [sic] clearly that as of August 6, 1998, Jack Cranney requested to take over the job from Ng Brothers Construction.”
Both subcontractors continued to work for the Cranneys after August, 1998, to provide additional plumbing and electrical services beyond the scope of their subcontracts with the plaintiff.
The plaintiff claims that the defendants may not raise this issue on appeal because they failed to argue it below. See Dupont v. Dracut,