DECISION AND ORDER
Before the Court is plaintiffs motion (docket # 7) for summary judgment on its complaint (docket # 1), which alleges that defendants have violated the Telecommunications Act of 1996 and state law by failing to permit Nextel Partners, Inc. (“Nextel”) to add cellular telephone antennae to an existing guyed tower in the Town of Amherst, New York (“Town”). For the reasons stated below, the Court grants Nextel’s motion, and orders the filing of additional information pertinent to Nextel’s motion for a reasonable attorney’s fee and costs pursuant to 42 U.S.C. § 1988.
SUMMARY JUDGMENT STANDARD
The standard for granting summary judgment is well established. Summary judgment may not be granted unless “the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.” Fed. R. Civ. P. 56(c). A party seeking summary judgment bears the burden of establishing that no genuine issue of material fact exists.
See Adickes v. S.H. Kress & Co.,
Once that burden has been met, the burden then shifts to the non-moving party to demonstrate that, as to a material fact, a genuine issue exists. Fed. R. Crv. P. 56(e);
Anderson v. Liberty Lobby, Inc.,
BACKGROUND
“When a party has moved for summary judgment on the basis of asserted facts supported as required by Federal Rule of Civil Procedure 56(e) and has, in accordance with local court rules, served a concise statement of the material facts as to which it contends there exist no genuine issues to be tried, those facts will be deemed admitted unless properly controverted by the nonmoving party.”
Glazer v. Formica Corp.,
Nextel is a wireless telecommunications company that is authorized, pursuant to a license from the Federal Communications Commission, to offer wireless communication services to consumers throughout New York State and the United States. Nextel has a proprietary network that allows it to offer digital cellular communications, data transmission, as well as its Direct Connect feature that allows customers to connect to other Nextel subscribers with a simple push of a button. Given that Nextel’s wireless network is proprietary and uses a different technology than other wireless service providers, Nextel’s customers are not able to “roam” by using another provider’s network in order to access a wireless communications network.
Defendants are the authorized municipal representatives for the Town of Amherst and are responsible for implementing and enforcing zoning regulations, along with granting relief from such regulations when warranted. In addition, defendant Zoning Board of Appeals (“ZBA”), is the body duly authorized by the Town of Amherst Zoning Code to issue special use permits upon demonstrated compliance with applicable standards.
On or about March 25, 2002, Nextel submitted its initial application to collocate its antennae on an existing tower owned by Crown Castle, Inc. and located at 1210 New Road in the Town of Amherst. The application sought a special permit to install Nextel’s antennae at a height of 115 feet and locate an equipment shelter within the leased area on the ground. Nextel’s antennae would have been the fourth set of antennae on this tower (the others belonging to Verizon Wireless, Cricket and Voi-cestream Wireless) and would be located at a height below the three existing providers.
Defendant ZBA held a public hearing on the application on or about May 21, 2002. Subsequently, in a letter dated May 22, 2002, the ZBA informed Nextel that it denied its special use permit request to collocate antennae on the tower at 1210 New Road citing that no need for the facility was established by Nextel. The ZBA subsequently voted to vacate its denial of Nextel’s special use permit application and voted to adjourn the matter to the August 20, 2002 meeting to allow Nextel to submit further documentation on the need for the facility.
Nextel thereafter submitted additional information with a narrative that provided further details regarding the need for Nextel to collocate its antennae on the tower at 1210 New Road. Included in this application were radio frequency (“RF”) propagation studies which provided a visual representation of the areas where Nextel maintained that its service was inadequate and where customers would be unable to connect to Nextel’s wireless network. No other information was submitted to the ZBA contradicting this information or challenging its technological foundation.
A second public hearing was held on the application on August 20, 2002. At this public hearing, Nextel presented evidence explaining that, because of technological differences between its wireless service and that of other providers, Nextel customers do not have the ability to “roam” onto other wireless systems in areas where Nextel’s coverage is inadequate. No other information was submitted to the Zoning
Subsequently, in a letter dated August 21, 2002, the ZBA informed Nextel that it declined issuing a “Negative Declaration” under the New York State Environmental Quality Review Act. There is no dispute that this denial of the negative declaration was tantamount to a denial of Nextel’s special use permit application.
By way of explanation, a “Negative Declaration” is a notice that the ZBA has determined that a proposed action will not have a significant adverse effect on the environment and is issued pursuant to Town of Amherst Local Law # 3-82, and 6 N.Y.C.R.R. Part 617. See, e.g., O’Neil aff. Ex. L. The New York regulation 3 states, in pertinent part,
on the basis of the draft [Environmental Impact Statement], and comments made thereon, the lead agency has determined that the action will not have a significant adverse impact on the environment. A negative declaration must then be prepared, filed and published in accordance with section 617.12 of this Part.
6 N.Y.C.R.R. § 617.9(a)(5)(i)(b) (2003). The August 21, 2002 letter went on to explain that the ZBA was basing its denial of a negative declaration on a suggestion from the Town Planning Department that replacing the existing guyed wire tower with a new monopole tower or other non-lattice structure would “be more closely in harmony with the general purposes and intent of this ordinance.” However, apart from its suggestion regarding replacement of the existing tower, the Planning Department had determined that granting Nex-tel’s application and allowing the placement of the additional antennae on the tower would not have any significant impacts, and, in fact, recommended that issuance of a negative declaration.
Moreover, it is undisputed that at its March 19, 2002 meeting, the ZBA voted to approve a special use permit for VoiceS-tream Wireless to collocate its antennae on the existing tower at 1210 New Road, at a height above that proposed by Nextel. VoiceStream is a competing wireless communications company to Nextel and offers services that are functionally equivalent to those offered by Nextel. The ZBA’s approval included the adoption of a negative declaration finding no significant adverse impacts from the VoiceStream proposal.
DISCUSSION
In its complaint, Nextel raises four causes of action: (1) the ZBA violated Section 704 of the Telecommunications Act of 1996, 47 U.S.C. § 322(c)(7) (2002), by unreasonably discriminating among providers of functionally equivalent wireless services, and by prohibiting wireless services in the Town of Amherst; (2) the ZBA’s refusal to take any further action on Nextel’s special use permit application violates Section 704 of the Telecommunications Act of 1996, 47 U.S.C. § 322(c)(7) (2002), which requires action within a reasonable time, and requires that denials be in writing and supported by substantial evidence contained in a written record; (3) the ZBA acted illegally and in excess of the powers granted to it by New York law in that it has failed to reach a final decision on Nextel’s application for a special use permit; and (4) the ZBA’s failure to comply with the Telecommunications Act of 1996 occurred while the ZBA was acting under color of state law and has deprived Nextel of rights, privileges and immunities secured by the Constitution and laws of the United States and New York, thereby warranting the imposition of money damages “in excess of any jurisdictional limits” pursuant to 42 U.S.C. § 1983 and a rea
The ZBA Unreasonably Discriminated Against Nextel and its Action has the Effect of Prohibiting Services in Violation of the Telecommunications Act of 1996
Nextel advances two arguments in support of this claim. First, Nextel maintains that defendants unlawfully discriminated against it when they denied its second application for a special use permit. Second, Nextel argues that the ZBA’s action amounts to a prohibition of services in the Town in violation of the Telecommunications Act of 1996 (“TCA”).
With regard to the first argument, Nex-tel points out that the ZBA approved Voi-ceStream Wireless’s Special Use Permit application on March 19, 2002, with the only condition being that VoiceStream had to modify its structural analysis to include the adequacy of the foundations of the tower. VoiceStream’s approved application sought to collocate antennae at the 137-foot level of the tower at 1210 New Road, the very same tower at which Nex-tel was seeking to collocate antennae at the 115-foot level. Defendants respond only with an assertion that the zoning ordinance “expresses a clear preference for monopole towers and strongly disfavors lattice towers.” Plunkett aff. ¶ 4.
The TCA, codified at 47 U.S.C. § 151, et seq., is an omnibus overhaul of the federal regulation of communications companies, and intends:
to provide for a pro-competitive, de-regulatory national policy framework designed to accelerate rapidly private sector deployment of advanced telecommunications and information technologies and services ... by opening all telecommunications markets to competition ....
H.R. Conf. Rep. No. 104-458, at 113 (1996),
reprinted in
1996 U.S.C.C.A.N. 124, 124.
Sprint Spectrum, L.P. v. Wil-loth,
Defendants have established a town zoning ordnance regulating telecommunications services. Section 203-8-19 of that ordinance provides in pertinent parts as follows:
8-19.3 The site plan for the proposed Telecommunication Facility shall be reviewed by the Planning Department before a hearing is held by the Zoning Board of Appeals. The Planning Department shall submit a written report to the Zoning Board of Appeals containing its analysis of the proposal under the standards set forth in § 203-9-4-4.1 of this ordinance. Site plan submittal and review under § 203-9-2 of this ordinance shall not be required.
A. Is necessary to meet current or expected demands for the services supported by the telecommunication facility for that applicant’s network;
B. Conforms with all applicable regulations promulgated by the Federal Communications Commission;
C. Is designed and constructed in a manner which minimizes its visual impact to the extent practical;
D. Complies with all other requirements of this ordinance;
E. Is an appropriate site within the technically feasible area for the location of the Telecommunication Facility.
8-19.5 The shared use of existing Telecommunication Facilities or other structures shall be preferred to the construction of new such facilities. Any application for a Special Use Permit or modification of the conditions of a current Special Use Permit shall include proof that reasonable efforts have been made to co-locate with an existing Telecommunication Facility or upon an existing structure....
Code of the Town of Amherst, New York, §§ 203-8-19.4 & 203-8-19.5 (1996), available at http://www.amherst.ny.us/ Govt/govt.htm.
The Section 203.8-19.3 report of the Planning Department Staff, dated August 16, 2002, found that Nextel’s proposed addition of twelve antennae on the existing guyed tower “will be in harmony with the general purposes and intent of this ordinance.” Planning Department Staff memo to Susan K. Jaros, Town Clerk (Aug. 16, 2002) at 1 (attached to O’Neil aff. Ex. H).
In addition, the staff wrote, “[t]he project would be more closely in harmony with the general purposes and intent of this ordinance if the existing lattice tower were replaced with a new monopole tower.” Id. The report concluded that, “[Nextel’s] application is recommended for approval with the recommendation that the existing lattice tower be replaced with a new monopole tower or other non-lattice structure of equal or greater aesthetic appeal.” Id. at 2. The report included a “Negative Declaration” for the ZBA’s use.
Defendants, in opposing Nextel’s application for summary judgment, rely on the
Willoth
case. The discrimination encompassed in that law suit involved a claim by Sprint that the municipality treated its application and that of another wireless services provider, Frontier, differently. Sprint claimed that it was subjected to a lengthy environmental review process, and that Sprint was not afforded the same opportunity as Frontier to build the requisite number of telecommunications facilities to provide wireless service coverage inside buildings throughout the municipality. The Second Circuit in
Willoth
upheld the district court’s rejection of Sprint’s discrimination claim, stating that local governments may reasonably take the location of a telecommunications tower into consideration when deciding whether to require a more intense review of the application, and that they may reject an application based upon its impacts on the environment, or on the character of the community, even though such a denial may result in discrimination between providers of functionally equivalent services.
Willoth,
However, the
Willoth
case is clearly distinguishable from the case at bar. Unlike
Willoth,
which involved applications for three new towers, Nextel here simply sought a special permit to collocate its
I want to say one positive thing. This tower is so remote from all habitation that replacement with a monopole would not have any significant positive impact on the environment. So I don’t think—I think that’s not really an issue.
Transcript of Zoning Board of Appeals meeting (Aug. 20, 2002) at 40 (attached to O’Neil aff. Ex. J).
The facts in this matter more closely align with those in
Smart.
In that case, Nextel sought to modify an existing windmill tower to allow the installation of whip type antennae and place an equipment shelter at the base of the structure. The municipal board denied Nextel’s application based in part on visual, aesthetic and safety concerns.
Smart,
The Court can discern no plausible reason why the ZBA approved the VoiceS-tream application and, approximately two months later, voted to deny a virtually identical application from Nextel. The ZBA offered no reason in its resolution “denying the Negative Declaration.” Planning Department Staff memo to Susan K. Jaros, Town Clerk (Aug. 16, 2002) at 1 (attached to O’Neil aff. Ex. H);
cf. AT & T Wireless PCS, Inc. v. City Council of the City of Virginia Beach,
The Court will now turn its attention to Nextel’s second contention, that the ZBA’s action had the effect of prohibiting service in violation of the TCA. The TCA provides that it is a violation for a municipality to prohibit, or make decisions that have the effect of prohibiting, personal wireless services. 47 U.S.C. § 332(B)(i)(II). The Second Circuit has interpreted this section to mean that local governments may not regulate personal wireless service facilities in such a way as to prohibit remote users from reaching “facilities necessary to make and receive phone calls.”
Willoth,
Willoth
involved applications by Sprint to construct three wireless communications facilities within the Town of Ontario. However, the evidence in that record established that two towers and possibly even a single tower would allow Sprint to provide in-vehicle coverage throughout the town and in-building coverage throughout most of the town.
Willoth,
The situation here is dramatically different and, applying the law to the facts at hand, there is no doubt that Nextel has chosen the least intrusive means for filling a significant gap. Nextel submitted Radio Frequency (“RF”) propagation maps with its application that clearly showed a significant gap in Nextel’s service in the Town of Amherst. Such gaps are clearly substantial and are not limited to rural areas or the interior of buildings in sparsely populated areas. Nextel is seeking to fill existing coverage holes near the intersection of New Road and Tonawanda Creek Road along with providing coverage along Tonawanda Creek Road and providing at least in-vehicle coverage on Routes 263, 78 and 270. O’Neil aff. ¶ 9; Exs. D, Tab 11 and G, Tab 2. Those roads are well traveled and certainly do not qualify as rural areas. Nextel explained in detail at both public hearings the significance of the RF maps and the necessity for adding antennae to the New Road tower. In addition, as Nextel explained in response to the ZBA’s inquiries, that, even if it would be legally appropriate to consider the ability of a its customers to “roam” onto other wireless networks in an area of inadequate coverage, the technical requirements of Nextel’s system make it impossible for Nextel customers to “roam” onto any other system. O’Neil aff. Ex. J at 13-14.
Furthermore, the Court finds that Nex-tel has established that there is no less intrusive means to fill the significant gap in coverage other than to collocate antennae on an existing structure. The existing tower will remain in place regardless of whether Nextel collocates its antennae on the structure or not. The only other alternative would be for Nextel to find a site where it could build a new tower to an adequate height for the sole purpose of placing only its antennae on the structure. The Town’s own telecommunications regulations unequivocally state a strong preference that wireless providers collocate antennae on existing structures and, in any event, the Town’s adoption of a moratorium on any new towers has foreclosed that option. The moratorium, coupled with the ZBA’s denial of Nextel’s collocation application, has left Nextel with no means of filling the significant coverage gap in the Town and clearly has the effect of prohibiting wireless service within the Town in violation of the TCA.
Thus, Nextel is entitled to summary judgment under both theories of its first cause of action.
The ZBA’s Denial of Nextel’s Application Is Not Supported by Substantial Evidence or a Written Decision
The TCA provides that a denial of a request to build wireless facilities must be “in writing and supported by substantial evidence contained in a written record.” 47 U.S.C. § 332(c)(7)(B)(iii) (2002).
The decision by the ZBA to deny Nex-tel’s special permit application is clearly not supported by substantial evidence. Defendants’ own planning staff recommended approval of the application stating that “[t]he proposed project will be in harmony with the general purposes and intent of [§ 203-9-F4.1 of the Town of Amherst Zoning ordinance].” Planning Department Staff memo to Susan K. Jaros, Town Clerk (Aug. 16, 2002) at 1 (attached to O’Neil aff. Ex. H). The report’s suggestion that the guyed tower be replaced with a monopole tower is of no import. The ZBA’s denial of a Negative Declaration “based on the Planning Department’s recommendation that the existing lattice tower be replaced with a new monopole tower or other non-lattice structure of equal or greater aesthetic appeal,” is not supported by the record.
J. Matthew Plunkett, Esq., counsel for the Town of Amherst, in defendants’ sole responding paper, deposes that the ZBA “clearly expressed concern ... that an applicant abide by the Town’s code provisions governing the style of cell tower required by the Town’s ordinance.”
Id.
However, Nextel’s application was not to change the characteristics of the existing tower, or to erect a new tower, but only to add antennae to the existing, previously approved tower.
See Smart,
Clearly, the ZBA’s action with regard to Nextel’s second application is in violation of the TCA provision that a denial of a request to build wireless facilities must be “in writing and supported by substantial evidence contained in a written record.” 47 U.S.C. § 332(c)(7)(B)(iii) (2002). Nextel is entitled to summary judgment on its second cause of action.
The ZBA’s Decision was Arbitrary and Capricious
Nextel’s third claim relates to New York law. More specifically, Nextel
The Court finds, that based upon The Court finds, that based upon the evidentiary proof, Nextel has established that the ZBA’s decision in this case is arbitrary and capricious, an abuse of discretion and not supported by substantial evidence. Defendants’ own staff re-the evidentiary proof, Nextel has established that the ZBA’s decision in this case is arbitrary and capricious, an abuse of discretion and not supported by substantial evidence. Defendants’ own staff report clearly and concisely lays out Nextel’s compliance with the legislative standards put in place by the Town for granting a special permit, including the expressed preference for collocated telecommunication facilities over new tower construction. port clearly and concisely lays out Nextel’s compliance with the legislative standards put in place by the Town for granting a special permit, including the expressed preference for collocated telecommunication facilities over new tower construction. The application submitted by Nextel and the oral testimony given at two public hearings provided further evidence that Nextel complied with the legislative standards for the grant of a special use permit. Although the ZBA was not necessarily The application submitted by Nextel and the oral testimony given at two public hearings provided further evidence that Nextel complied with the legislative standards for the grant of a special use permit. Although the ZBA was not necessarily bound by the staff report, New York law is clear that a municipal board must base its bound by the staff report, New York law is clear that a municipal board must base its decision on evidence in the record that would be sufficient to support a denial of decision on evidence in the record that would be sufficient to support a denial of
the application.
Asma v. Curcione,
In addition, although the ZBA has admitted that its action constituted a denial of Nextel’s application, its resolution to “deny the Negative Declaration” was procedurally deficient under New York law. The New York State Environmental Quality Review Act (“SEQRA”) and the regulations promulgated thereunder, require an agency to make a preliminary determination of potential environmental significance before acting on any land use application. 6 N.Y.C.R.R. § 617.6 (2003). The regulations offer only two alternatives for this determination of significance: the agency adopts a “negative declaration” if it finds no potentially significant environmental impacts, and must adopt a “positive declaration” if it finds that such significant impacts exist. 6 N.Y.C.R.R. § 617.7.
Cf. Willoth,
The law does not provide for a “denial of a negative declaration.” If the ZBA had intended to adopt a positive declaration, it would have been required to identify the specific environmental impacts it found to The law does not provide for a “denial of a negative declaration.” If the ZBA had intended to adopt a positive declaration, it would have been required to identify the specific environmental impacts it found to
Civil Rights Claim
Nextel’s fourth claim is made pursuant to 42 U.S.C. §§ 1983 and 1988. Under this cause of action, Nextel contends that it sustained money damages as a result of the ZBA’s unlawful actions and, as a result, it is entitled to a reasonable attorney’s fee as well. In order to prove a claim under 42 U.S.C. § 1983, a plaintiff must show that a person, acting under color of state law, deprived him of rights secured by the Constitution or the laws of the United States.
Parrott v. Taylor,
With regard to both elements, in
Omnipoint Communications v. City of White Plains,
The Court concurs with the reasoning in the cases holding that a plaintiff has a remedy under Section 1983 for violations of the TCA. As a local zoning board, the ZBA acted under the color of state law.
See West v. Atkins,
An attorney’s fee is recoverable as an element of damages under a Section 1983 claim as provided for under 42 U.S.C. § 1988. The relevant statute reads in pertinent part as follows:
Attorney’s fees. In any action or proceeding to enforce a provision of ... [42 USCS §§ 1981-1983 ... ] ..the court, in its discretion, may allow the prevailing party, other than the United States, a reasonable attorney’s fee as part of the costs....
42 U.S.C. § 1988(b). There can be no dispute that Nextel is a prevailing party here. Given defendants’ disregard of the TCA and New York State law, and the lack of opposition in defendants’ papers, the Court, exercising its discretion, will order a reasonable attorney’s fee.
[11,12] The starting point for the determination of a reasonable fee is the calculation of the lodestar amount.
See Hensley v. Eckerhart,
Nextel is, therefore, directed to provide the Court with sufficient information concerning its claimed attorney’s fee to enable the Court to properly adjudicate its claim for a reasonable attorney’s fee in accordance with the law set forth above. Injunctive Relief
Nextel also seeks a permanent mandatory injunction. The standard for a permanent injunction is similar to the standard for a preliminary injunction: (1) irreparable harjn and (2) success on the merits.
University of Texas v. Camenisch,
Nextel has, on more than one occasion, attended a public hearing on its application for a wireless communications
CONCLUSION
In light of the above, the Court grants Nextel’s application for summary judgment on all the causes of action in its complaint. The Town of Amherst and the Zoning Board of Appeals are hereby ordered to approve Nextel’s application for a special use permit. As to its § 1988 claim, Nextel is directed to submit, by March 14, 2003, an application for the attorney’s fee it is seeking, supported by requisite documentation. 4 Upon receipt, the Court will issue a scheduling order to allow defendants to contest, if they have a basis, plaintiffs attorney’s fee request.
IT IS SO ORDERED.
Notes
. W.D.N.Y. Local Rule 56 states, in pertinent part, "[t]he papers opposing a motion for summary judgment shall include a separate, short, and concise statement of the material facts as to which it is contended that there exists a genuine issue to be tried. All material facts set forth in the statement required to be served by the moving party will be deemed admitted unless controverted by the statement required to be served by the opposing party- •• •”
. Mr. Plunkett was admitted on August 7, 1984 and Mr. Jones on March 3, 1982, according to the Clerk's records.
. Neither party provided the Court with a copy of the local law.
. See
New York State Association for Retarded Children v. Carey,