OPINION
This matter is before the court on defendant’s Motion to Dismiss. The issues to be decided are whether the government’s contracting officer has issued a final decision as to plaintiffs noncompliance with Cost Accounting Standard (CAS) 415, 48 C.F.R. § 9904.415, and whether there is a claim over which this court has jurisdiction. Plaintiff seeks a judgment that the contracting officer’s determination of noncompliance is erroneous, a denial of the government’s determination of noncompliance, or else a judgment that the government released plaintiff of liability for noncompliance, as well as attorneys’ fees and costs. Defendant argues that plaintiffs complaint should be dismissed for lack of jurisdiction because there was no final decision and there is no claim in dispute.
FACTS
Plaintiff, Newport News Shipbuilding and Dry Dock Company, supplies aircraft carriers, submarines, and other vessels to the United States Navy. Plaintiff is a former subsidiary of Tenneco Inc. (Tenneco), whose Internal Revenue Code 401 (k) qualified savings plan (Thrift Plan) was later adopted by plaintiff. In 1996, the Defense Contract Audit Agency (DCAA) audited Tenneco to evaluate Thrift Plan contributions, made by Tenneco and allocated to plaintiff, from 1993-1994.
On October 9, 1996, the DCAA Resident Auditor sent a draft copy of a Statement of Condition and Recommendations based on
On February 6, 1997, DCAA issued a final audit which rejected plaintiffs arguments and reaffirmed the finding of noncompliance. On February 26, 1997, the ACO issued an Initial Finding of Noncompliance With CAS 415, which adopted the DCAA conclusions. The Initial Finding requested comments from plaintiff on why it was compliant. On April 23, 1997, plaintiff responded by letter, restating its previous arguments. On November 5, 1997, the ACO issued a Determination of Noncompliance With CAS 415.
Plaintiffs Navy contracts contain a “Notification of Changes” clause which call for a bilateral contract modification whereby the parties agree “to the mutual full and final releases for the consequences of their conduct” other than conduct specifically excepted from the release. See Compl. ¶ 32. The contracts also contain a clause requiring CAS compliance and requiring plaintiff to agree to an adjustment of the contract price or cost allowance for failure to comply.
On March 17, 1998, plaintiff filed its complaint in this court, claiming the ACO determination of noncompliance was erroneous in fact and law because CAS 412 applied (Count I), the determination was erroneous because plaintiff had actually complied with CAS 415 (Count II), and the determination is a nullity because bilateral contract modifications executed through the third quarter of 1997 released plaintiff from liability (Count III). On July 17,1998, defendant submitted its Motion to Dismiss, arguing that the ACO had not issued a final decision, and that plaintiff did not submit a claim to the ACO.
DISCUSSION
I. JURISDICTION
A. Whether the ACO Made a Final Decision
This court’s jurisdiction, as expanded by the 1992 amendments to the Tucker Act, includes:
any claim by or against, or dispute with, a contractor arising under section 10(a)(1) of the Contract Disputes Act of 1978, including a dispute concerning... compliance with cost accounting standards, and other nonmonetary disputes on which a decision of the contracting officer has been issued under section 6 of that Act.
28 U.S.C. § 1491(a)(2). Plaintiff seeks non-monetary relief under the Contract Disputes Act of 1978(CDA), 41 U.S.C. § 601 et seq., which permits a contractor to file suit after the contracting officer has made a final decision. See 41 U.S.C. § 609(a)(3). A final decision by the contracting officer is a jurisdictional prerequisite to bringing suit in this court pursuant to the CDA. See Bath Iron Works Corp. v. United States,
Defendant argues no final decision was made because the November 5, 1997 letter was an invitation to negotiate. In support of this view, defendant notes the letter was not designated a “final decision”, and that regulations require the contracting officer to solicit a cost impact assessment for purposes of negotiating a price adjustment. See Def. Reply Br. at 7 (citing 48 C.F.R. § 30.602-2(c)(2)). However, “[w]hether a contracting officer’s letter may be taken as a final expression of the agency’s position on a claim in issue is ultimately to be judged by what the letter says and not by how it is labeled.” Litton Systems, Inc. v. United States,
In the Armed Services Board of Contract Appeals (ASBCA), a final determination of CAS noncompliance has been held to be an appealable final decision of the contracting officer, even absent a determination of monetary impact. See Systron Donner, Inertial Division, ASBCA No. 31148, 87-3 B.C.A. (CCH) ¶ 20,066,
As argued, this case appears to create a tension between two purposes of the 1992 Tucker Act Amendments. First, the Court of Federal Claims should have parallel jurisdiction with the boards of contract appeals. See Garrett v. General Electric Co.,
The Amendment does not authorize contractors to seek declaratory judgments from the Court of Federal Claims in advance of a dispute and final decision, and will not permit contractors to seek injunctions or declaratory judgments that would interfere with the contracting officers’ right to direct the manner of performance under the changes clause. A contracting officer’s final decision under the Contract Disputes Act will remain a jurisdictional prerequisite to review by the Court of Federal Claims.
138 Cong. Ree. S17,799 (daily ed. Oct. 8, 1992).
In fact, the ASBCA precedent may be squared with the finality requirement. The Federal Circuit recently rejected a broad reading of Senator Heflin’s remarks which would have precluded nonmonetary relief pri- or to completion of a contractor’s work under a disputes clause. See Alliant,
The imminent .certainty of harm to plaintiff in this case also distinguishes Sharman v. United States,
Based on the circumstances and content of the November 5,1997 letter, the court agrees with plaintiff. The letter’s requests for information may affect the amount of withholding, but they would not change the ACO’s final determination that plaintiff was in noncompliance — that decision was no longer being negotiated. The government’s argument that the letter is not a final decision because it merely references the ACO’s reasoning why CAS 415 and not CAS 412 applied, ignores the fact that the letter was a determination of noncompliance made after an Initial Finding of Noncompliance. The ACO had already made its request for reasons why plaintiff believed it was in compliance, and then made its determination, which referred back to its Initial Finding and plaintiff’s response, as well as the CAS contract term at issue.
B. Whether a Claim Exists
This court’s jurisdiction pursuant to the CDA requires a valid government or contractor “claim”. See 41 U.S.C. § 605(a). As the Federal Circuit has explained, the term “claim” is not specifically defined in the CDA, and therefore it is necessary to refer to the Federal Acquisition Regulations (FAR). See Garrett,
Plaintiff argues the November 5, 1997 letter constitutes a government claim, not a contractor claim. For support, plaintiff looks to Brunswick Corp., ASBCA No. 26691, 83-2 B.C.A. (CCH) ¶ 16,794,
The government contends that plaintiffs argument fails because plaintiffs choice not to provide the information requested in the letter prevented the ACO from making a specific demand for relief. The government cites Garrett v. General Electric for this proposition. In Garrett, the Federal Circuit held that a Navy directive that General Electric correct or replace defective engines under its contract constituted the “other relief’ referred to above in the FAR definition of a “claim”. See Garrett,
A government claim does not require certification. See Placeway Construction Corp.,
CONCLUSION
The Court holds that the ACO’s letter of November 5, 1997 was a final decision which constituted a government claim. Accordingly, defendant’s Motion to Dismiss is denied as to all Counts.
It is so ORDERED.
Notes
. In this regard, it is worth mention that the government also argued the letter was not final because it did not state whether or not the United States would waive the right to require CAS compliance. This theory amounts to saying the government’s letter is not final if it does not guarantee that it is final. In effect, such an argument is nothing more than a requirement of "magic words”, which are not required by our precedent.
. As a result of the letter's reference to "contracts containing a CAS clause”, see PL Resp., App. at 33, the ACO did reference the pertinent contracts, see 48 C.F.R. § 33.211(a), contrary to the government’s contention. The court finds the only reasonable reading of the letter covers the plaintiff's contracts containing CAS clauses.
