37 N.J.L. 89 | N.J. | 1874
The opinion of the court was delivered by
The damages for which indemnification is sought in this suit, are the results of the-negligence of another party as well as that of the defendant.. The plaintiff* employed the defendant to oversee, in the capacity of architect, the putting up of a building, and the verdict has established that this structure is defective in workmanship and materials, in consequence of the want of care or want of skill of the contractor engaged to do1 the work, and. of the defendant as architect. The loss comprised in the-present cause of action has arisen, therefore, by reason of the-default of these two persons, the contractor- and the defendant.. The suit is against the latter, solely.
There can be no doubt that when two- or more persons' occasion, proximately, an injury, though not acting in concert,, they are severally liable for the consequences. In this respect there is no difference between wrongs the result of force and
But there is a circumstance which it has been strenuously insisted, individualizes the present subject, and varies it so as to remove it from the operation of the rule just mentioned. This peculiarity is the fact that the plaintiff retains in his hands a part of the price agreed to be paid for the construction of the house in question, and has refused to pay to the contractor this sum, on the ground of the imperfection of the • work and materials. The argument built upon this state of
It must be admitted that, in a suit by the contractor for the residue of the contract price now withheld by the plaintiff, it would be competent to show, in diminutipn of the contract price, that the building has not been built in the manner stipulated. This practice was settled by this court in the ease of Bouker et al. v. Randles, 2 Vroom 335. That was a suit to recover the agreed price of a steam engine, and the decision maintains the right of the vendee, in mitigation ■of damages, to insist on defects in the engine and its want of •correspondence with the agreement. In the present case, therefore, in a suit by this contractor, for the consideration agreed to be paid for the building of this house, these defects for which this verdict has held the defendant responsible, could be set up as a defence pro tanto. And if such action had been brought, and such defence had been interposed, and it had prevailed, it seems to me that the present action would have been barred. The reason is that, although the person; wronged by the negligence of two persons, can bring his! action against both, or either, still he cannot require a double Í satisfaction. That is, in case such person receives an indemj nification by a suit against either of the wrong-doers, he cannot pursue the other wrong-doer for the same cause of action. 2 Hill, on Torts, p. 459, § 20. The consequence is, if the retention of the moneys in question is to be regarded as so much paid, or as a satisfaction for these same damages now recovered, it is clear that the verdict against this defendant is not legal. The plaintiff is not entitled to keep the moneys now in his hands, as a compensation for damages, and then proceed, under process in this action, to levy a corresponding sum for the same damages out of this defendant. That would obviously be a double satisfaction for the same wrong, to which he is not entitled in law nor in justice.
But the weak point in this part of the defence is, that the
The result is, that judgment must be entered in the verdict.