MEMORANDUM OPINION 1
Currently pending before the Court are the motions to extend the Final Judgments in this action filed by the California Mov-ants and the New York Movants (collectively, the “Moving States”). 2 The Final Judgments arise out of a single civil complaint filed by a group of state plaintiffs on May 18, 1998, alleging antitrust violations by Defendant Microsoft Corporation and asserting claims pursuant to federal and state law. 3 The two Final Judgments are premised upon the same liability finding affirmed by the United States Court of Appeals for the District of Columbia Circuit, and are virtually identical in their substantive provisions. Nevertheless, the two Final Judgments were reached via different paths: the New York Movants’ Final Judgment was the result of a negotiated consent decree settling the remedy portion of this case as to certain state plaintiffs, while the California Movants’ Final Judgment was entered by the Court following a thirty-two day remedy-specific evidentiary hearing.
The Moving States’ motions seek the same objective: the extension of the relevant Final Judgment until November 12, 2012. The Court has conducted a searching and dedicated review of the Moving States’ motions, Microsoft’s Opposition, the Moving States’ Reply, and the exhibits attached to those memoranda. In addition, the Court has requested further targeted briefing from the Moving States and Microsoft, and has reviewed each party’s filings carefully. The Court has also given due consideration to the amicus curiae brief filed by the United States of America, Plaintiff in the related action, United States v. Microsoft Corporation, Civil Action No. 98-1232. 4 Upon a thorough review of all of the foregoing, the relevant statutes and case law, and the entire record herein, the Court shall GRANT-IN-PART and DE NY-IN-PART the Moving States’ motions to extend the Final Judgments.
The Court’s decision in this matter is based upon the extreme and unforeseen delay in the availability of complete, accurate, and useable technical documentation relating to the Communications Protocols that Microsoft is required to make available to licensees under Section III.E of the Final Judgments. The Court concludes that the Moving States have met their burden of establishing that this delay constitutes changed circumstances, which have prevented the Final Judgments from achieving their principal objectives. As such, the Court shall extend until November 12, 2009 those provisions of the Final Judgments that have not yet been extended until that date (collectively the “Expiring Provisions”), 5 thus making all provisions of the Final Judgments coterminous. The Court declines the Moving States’ invitation to extend the entirety of the Final Judgments through 2012 at this point in time, concluding that it is premature to do so.
The Court’s extension should not be viewed as a sanction against Microsoft; to the contrary, the Court commends Microsoft for its willingness to cooperate with the Plaintiffs in this action and in United States v. Microsoft in negotiating solutions to issues as they have arisen throughout the past five years. Indeed, because the parties have negotiated solutions to each of the myriad issues that have arisen regarding the technical documentation, the Court has never been asked to find Microsoft out of compliance with the Final Judgments, and has not deemed a sua sponte finding of non-compliance necessary or fruitful in achieving compliance. Nevertheless, the fact remains that more than five years after the Final Judgments were entered, the technical documentation required by Section III.E is still not available to licensees in a certifiably complete, accurate, and useable form. Further, as a result of the delay, the various provisions of the Final Judgments have not yet been given the opportunity to operate together as the comprehensive remedy the Court and the parties envisioned when the Final Judgments were entered. The Court’s extension should thus be viewed as a means to allow the comprehensive remedial scheme embodied in the Final Judgments the chance to maximize Section III.E’s pro-competitive potential.
The Court cannot know what impact the technical documentation required by Section III.E will have on the market once it is finally available in a complete, accurate, and useable form. The Moving States, however, proffer realistic examples of ways in which the Expiring Provisions of the Final Judgments can yet play a significant role in helping Section III.E achieve its full potential. In the face of these examples, the Court concludes that allowing the Expiring Provisions of the Final Judgments to lapse before Section III.E has even been given a chance to succeed might threaten the ability of the Final Judgments to achieve their full procompetitive impact. The Court therefore concludes that the limited extension it is approving is consonant with the policies of encouraging consent decrees, as well as the Court’s authority to modify court-ordered judgments.
I: BACKGROUND
A. Proceedings Leading to the Remedial Final Judgments
On May 18, 1998, simultaneous with the filing of the complaint in
United States v. Microsoft,
a group of state plaintiffs filed a civil complaint alleging antitrust violations
On Microsoft’s appeal of those rulings, the D.C. Circuit deferred to Judge Jackson’s factual findings, affirmed-in-part and reversed-in-part his findings of liability, and vacated the remedy decree.
Id.
(citing
United States v. Microsoft Corp.,
1. Appellate Findings and Instructions
The D.C. Circuit’s opinion began by affirming the district court’s definition of the relevant market as “the licensing of all Intel-compatible PC operating systems worldwide.”
7
Microsoft,
During the liability phase of this case, Plaintiffs proceeded on the theory that certain kinds of software products, known as “middleware,” could weaken the applications barrier to entry “by serving as platforms for applications, taking over some of the platform functions provided by Windows.” Id. at 90. Middleware has the ability to expose its own APIs, and Plaintiffs posited that “[ultimately, by writing to the middleware API set, applications developers could write applications which would run on any operating system on which the middleware was preset.” Id. 8 In accepting the district court’s definition of the relevant market and Plaintiffs’ theory of Microsoft’s market dominance, the D.C. Circuit concluded that the district court had properly excluded middleware products from the relevant market. Id.
The majority of the D.C. Circuit’s opinion focused on Microsoft’s challenges to the district court’s findings of liability under § 2 of the Sherman Act.
9
The D.C. Circuit addressed each in turn, and ultimately sustained the district court’s findings of liability with respect to the following specific conduct: (1) the license restrictions Microsoft imposed upon manufacturers of PCs, known as OEMs,
Microsoft,
The D.C. Circuit also imposed liability upon Microsoft for the “state law counterparts of’ Plaintiffs’ claims pursuant to § 2 of the Sherman Act. Id. at 46. Beyond these findings, however, the D.C. Circuit did not find Microsoft liable for any additional antitrust violations. In particular, the D.C. Circuit reversed the district court’s conclusion that Microsoft’s “course of conduct” as a whole constituted a separate violation of § 2 of the Sherman Act. Id. at 78. The D.C. Circuit also rejected the district court’s finding of attempted
monopolization and remanded Plaintiffs’ § 1 tying claim for further proceedings at the district court level.
Remedy Opinion,
After reviewing the district court’s conclusions with respect to liability, the D.C. Circuit turned to considering the district court’s choice of remedy, which mandated the divestiture of Microsoft Corporation into two separate entities and included a number of “interim restrictions on Microsoft’s conduct.”
Id.
at 95-96 (quoting
Microsoft,
The D.C. Circuit therefore remanded the case to this Court, with instructions to resolve any factual disputes surrounding a remedy and exercise the Court’s “broad discretion” in imposing the “relief it calculates will best remedy the conduct ... found to be unlawful.”
Id.
at 105. In so doing, the D.C. Circuit “offered specific guidance to this Court regarding the inquiry to be undertaken following remand.”
Remedy Opinion,
2. Remedy Proceedings Before This Court
“Following remand, pursuant to Court Order, the parties in the two consolidated cases entered into intensive settlement negotiations.”
Remedy Opinion,
On November 1, 2002, the Court issued three Memorandum Opinions and related Orders.
16
The first Memorandum Opinion and accompanying Order, issued in
United States v. Microsoft,
involved the Court’s determination, pursuant to the Antitrust Procedures and Penalties Act (“Tunney Act”), 15 U.S.C. § 16(b)-(h), that, with the exception of the provisions relating to the Court’s retention of jurisdiction — which the Court revised to be both more specific and more broadly drawn
17
— the consent decree proposed by the United States and Microsoft was in the public interest.
See generally United States v. Microsoft Corp.,
The Final Judgments approved as to the Settling States and the Litigating States are substantively quite similar. This similarity is not surprising because both the Settling States’ consent decree and the Court-ordered remedy followed upon, and were constrained by, the D.C. Circuit’s specific liability findings, as well as its guidance as to the nature of an appropriate remedy in light of those findings. Each Final Judgment, in keeping with the
B. The Final Judgments
The following description highlights the key provisions that are common to both Final Judgments, and notes the few instances in which the Final Judgments differ. At the outset, the Court notes the following definitions, which are important to understanding the parameters of the Final Judgments:
• The term “Non-Microsoft Middle-ware” incorporates the middleware threats that were the focus of the liability phase, and includes “a non-Microsoft software product running on a Windows Operating System Product that exposes a range of functionality to ISVs through published APIs, and that could, if ported to or made interoperable with, a non-Microsoft Operating System, thereby make it easier for applications that rely in whole or in part on the functionality supplied by that software product to be ported to or run on that non-Microsoft Operating System.” Final Judgments, § VI.M.
• A “Non-Microsoft Middleware Product” is similar to “Non-Microsoft Mid-dleware,” but adds the requirement that “at least one million copies” of the product “were distributed in the United States within the previous year.” Id., § VLN.
• The term “Microsoft Middleware Product” is defined according to a specific set of Microsoft functionalities existing at the time of the Final Judgments, as well as future Microsoft functionality. The existing set of func-tionalities are those provided by “Internet Explorer, Microsoft’s Java Virtual Machine, Windows Media Player, Windows Messenger, Outlook Express and their successors in a Windows Operating System Product.” The future technologies include software included in Windows that provides the functionality of internet browsers, email client software, networked audio/video client software, or instant messaging software. Also included in the definition of “Microsoft Middleware Product” are future functionalities that are both distributed as part of Windows and separately from Windows by Microsoft, trademarked by Microsoft, and which compete with Non-Microsoft Middle-ware Products. Id., § VI.K.
• The term “Microsoft Middleware” is similar to “Microsoft Middleware Product,” but is limited to the software code that is separately distributed and trademarked or marketed as a major version of a Microsoft Middleware Product. Id., § VI.J.
The substantive proscriptions of each Final Judgment are included within Section III, which is entitled “Prohibited Conduct.” Subsections A through C of § III focus on Microsoft’s dealing with OEMs. Section III.A bars Microsoft from retaliating against OEMs for (i) “developing, distributing, promoting, using, selling, or licensing” software or Non-Microsoft Middleware, (ii) shipping a Personal Computer that includes a non-Microsoft Operating System, or (iii) exercising options or alternatives provided by the Final Judgment.
Id.
at § III.A.
19
Section III.A also requires Microsoft to provide Covered OEMs with written notice before terminating their licenses for Windows Operating Systems Products.
Id.
20
In the
Remedy Opinion,
the Court described § III.A as “providing] substantial freedom to OEMs in their configuration of Microsoft’s Windows operating system by lifting Microsoft’s illegal license restrictions.”
Section III.C “seeure[s] for OEMs the general ability to install and display icons, shortcuts and menu entries for middleware ... on the Windows desktop or in the Start menu,” while reflecting “the care with which the appellate court separated anticompetitive restrictions from legitimate license restrictions.”
Remedy Opinion,
The Court’s
Remedy Opinion
described Sections III.D and III.E of the Final Judgments as “explicitly forward-looking remedies,” which “reflect an agreement that effective interoperation between software running on two or more devices will play an integral role in the successful emergence of new software products and platforms.”
Remedy Opinion,
Section III.D requires Microsoft to disclose to ISVs, IHVs, IAPs, ICPs, and OEMs the APIs and related documentation that are used by Microsoft Middle-ware to interoperate with a Windows Operating System Product. Final Judgments, § III.D. Section III.E requires Microsoft — starting nine months after the submission of the Settling States’ Final Judgment to the Court and three months after the entry of the Litigating States’ Final Judgment — to make available for use by third parties “on reasonable and non-discriminatory terms (consistent with Section III.I) any Communications Protocol that is, on or after the date [the] Final Judgment is submitted to the Court, (i) implemented in a Windows Operating System Product installed on a client computer, and (ii) used to interoperate, or communicate, natively ... with a Microsoft server operating system product.” Final Judgments, § III.E. Section III.E describes “native” communications as “without the addition of software code to the client operating system product.” Id.
The Court’s
Remedy Opinion
described § III.E as “[i]n all likelihood” “the
most
forward-looking provision in the Court’s remedy.”
Remedy Opinion,
server operating systems can perform a function akin to that performed by traditional middleware because they provide a platform for applications running ‘for’ use on a PC. The mandatory disclosure of the communications protocols relied upon by Microsoft’s PC operating system to interoperate with its server operating systems will advance the ability of non-Microsoft operating systems to in-teroperate, or communicate, with the ubiquitous Windows PC client. Advancement of the communication between non-Microsoft server operating systems and Windows clients will further the ability of these non-Microsoft server operating systems to provide a platform which competes with Windows itself.
Remedy Opinion,
Sections III.F, III.G, and III.H of the Final Judgments relate to “other participants in the ecosystem,” namely ISVs, IHVs, IAPs, ICPs, and end users.
See Remedy Opinion,
Section III.H requires Microsoft to allow end users and OEMs to enable or remove access to each Microsoft Middle-ware Product or Non-Microsoft Middle-ware Product, by designating a Non-Microsoft Middleware Product to be invoked in place of a Microsoft Middleware Product, i.e., as a default, in certain situations. Final Judgments, § III.H. Section III.H also prohibits Microsoft from designing its Windows Operating System Products so as to induce reconfiguration of an OEM’s or consumer’s formatting of icons, shortcuts, and menu items less than 14 days after the initial boot up of a new PC, or without first seeking confirmation from the user. Id.
Section III.I is closely related to the disclosures mandated by §§ III.D and III.E,
see Settling States Opinion,
2. Compliance, Enforcement, and Termination
While each Final Judgment provides that the relevant “Plaintiffs shall have exclusive responsibility for enforcing this Final Judgment,” Final Judgments, § JV.A, the Final Judgments differ significantly
in
their compliance and enforcement provisions. The Settling States’ Final Judgment provides for the creation of “a three-person Technical Committee (“TC”) to assist in enforcement of and compliance with” that Final Judgment. Settling States Final Judgment, § TV.B.1. The members of the TC are “experts in software design and programming,” who meet requirements demonstrating their independence from Microsoft, and who are selected by a detailed procedure.
Id, §
IY.B.2. The TC is broadly empowered to “monitor Microsoft’s compliance with its obligations under [the] Final Judgment,” and is answerable to the United States and the Settling States, rather than to the public or to the Court.
Id,
§ IV.B.8.a., § TV.B.8.e. Although the TC serves the United States and the Settling States, “Microsoft is responsible for the cost and expense of the service of the committee.”
Settling States Opinion,
The Settling States’ Final Judgment also provides for a Microsoft Internal Compliance Officer, who “is far more closely aligned with Microsoft.” Id. at 254. The Compliance Officer is a Microsoft employee responsible for administering Microsoft’s antitrust compliance program and “helping to ensure compliance” with the Final Judgment. Settling States Final Judgment, § IV.C. The TC and the Compliance Officer both may receive complaints from the United States, the Settling States, and third parties, as well as each other, regarding Microsoft’s compliance with the terms of the Final Judgment. Id, § IV.D. The Final Judgment includes specific provisions as to actions the TC and the Compliance Officer are obliged to take in conjunction with complaints received. Id.
As the Court explained in the
Settling States Opinion,
“ultimately the power to enforce the terms of the decree rests with the government,” i.e., the United States and the Settling States, and the TC was “not intended as a substitute for the enforcement authority of the United States” and the Settling States.
Settling States Opinion,
Unlike the Settling States, during the remedy hearing before this Court, the Litigating States were “unwaveringly critical of Microsoft’s proposal for a technical committee,” and the Court therefore declined to impose a technical committee upon the Litigating States in their remedy.
Remedy Opinion,
Jurisdiction is retained by this Court over this action such that the Court may act sua sponte to issue further orders or directions, including but not limited to orders or directions relating to the construction or carrying out of this Final Judgment, the enforcement of compliance therewith, the modification thereof, and the punishment of any violation thereof.
Final Judgments, § VII. The Court’s
Tunney Act Opinion
and
Settling States Opinion
each specifically conditioned approval of the relevant consent decree on the parties amending their respective consent decrees to include this reservation of jurisdiction.
Settling States Opinion,
In addition to providing for the retention of sua sponte jurisdiction, the Final Judgments provide that:
Jurisdiction is retained by this Court over this action and the parties thereto for the purpose of enabling either of the parties thereto to apply to this Court at any time for further orders and directions as may be necessary or appropriate to carry out or construe this Final Judgment, to modify or terminate any of its provisions, to enforce compliance, and to punish violations of its provisions.
Final Judgments, § VII. It is this provision of the Final Judgments that the Moving States invoke in their motions.
As to the term of the Final Judgments, each provides “[ujnless [the] Court grants an extension, this Final Judgment will expire on the fifth anniversary of the date it is entered by the Court.” Final Judgments, § VI.A. In discussing the appropriate term for the Final Judgment in the remedy proceeding, the Court noted that there was “little dispute that many of the acts which gave rise to the imposition of liability in [the] case ha[d] long since ceased.”
Finally, each Final Judgment describes one specific scenario in which the Final Judgments might be extended by the Court, allowing the Plaintiffs to “apply to the Court for a one-time extension of this Final Judgment of up to two years ... [i]n any enforcement proceeding in which the Court has found that Microsoft has engaged in a pattern of willful and systematic violations.” Id., § VLB. The Final Judgments do not, however, indicate that § VI.B represents the sole scenario in which the Final Judgments might be extended, and the Moving States do not purport to invoke that provision in their motions.
The Commonwealth of Massachusetts alone appealed the Litigating States’ Final Judgment, challenging many of the substantive provisions described above. The D.C. Circuit’s opinion on appeal addressed each challenged provision and “affirm[ed] [this Court’s] remedial decree in its entirety,” finding that the Court’s “reasoning was based upon evidence in the record, was sound, and involved no abuse of discretion.”
Massachusetts v. Microsoft Corp.,
C. Implementation of the Final Judgments
The Court entered the Litigating States’ Final Judgment on November 1, 2002, and entered the Settling States’ Final Judgment Pursuant to Rule 54(b) on November 12, 2002. On May 14, 2003, the Court issued an Order requiring the parties to file joint status reports with the Court every six months regarding Microsoft’s compliance with the Final Judgments and Plaintiffs’ enforcement efforts. That Order provided that status conferences would be scheduled within one month of the Court’s receipt of each status report. Over time, however, in response to various issues, the Court’s practice evolved to include a Joint Status Report (hereinafter “JSR”) — filed jointly by the United States, the New York Group, the California Group, and Microsoft, in both this action and United States v. Microsoft — and a corresponding status conference approximately every three months. In addition, for reasons described below, in January 2006 Microsoft began filing monthly Supplemental Status Reports regarding its compliance efforts in connection with § III.E of the Final Judgments.
The Court has kept abreast of the Plaintiffs’ enforcement efforts and Microsoft’s compliance efforts through the myriad Status Reports filed and status conferences held over the past five years. In order to place the Moving States’ motions in context, the Court briefly summarizes the major developments over the past five years. The Court first addresses those related to provisions of the Final Judgments other
At the outset, the Court commends the members of the TC as well as the California Group’s technical expert, Mr. Craig Hunt, who has worked alongside the TC in many of its compliance efforts related to Section III.E. In the Court’s view, the TC has truly become one of the most successful aspects of the Final Judgments, because it has been invaluable in facilitating the Plaintiffs’ enforcement efforts.
25
As the Court noted when the Final Judgments were entered, the instant case is an “unusually complex” one,
Settling States Opinion,
The TC’s expertise has allowed Plaintiffs to reap another, undoubtedly significant benefit from the Final Judgments: beginning in the Summer of 2004, “Plaintiffs, with the assistance of the TC, [began] discussions with Microsoft concerning the successor operating system to Windows XP,” which was eventually released as Windows Vista. 7/9/04 JSR at 7. Plaintiffs focused on changes in Vista that might implicate Sections III.C and III.H of the Final Judgments, reviewed materials supplied by Microsoft, discussed their concerns with Microsoft, and were actually able to effect changes to Vista in advance of its release, particularly with respect to the methods for setting default middle-ware. See generally id.; 10/8/04 JSR; 10/19/05 JSR at 8-9. Throughout that process, the TC developed a number of testing tools that middleware ISVs used to ensure “Vista-readiness” prior to the shipment of Windows Vista. 10/19/05 JSR at 9-10; 11/21/06 JSR at 5-6; 3/6/07 JSR at 6-7. In addition to their oversight efforts related to Vista, Plaintiffs were also able to “stud[y] the new search feature in Internet Explorer 7 and discussf ] its implications with Microsoft months before it was included in the beta versions released to consumers.” 5/12/06 JSR at 13.
The Court also notes that the enforcement and voluntary dispute resolution mechanisms of the Final Judgments have been a resounding success. Over the past five years, a variety of complaints have been brought to the parties’ attention by third parties, and the parties themselves ■have also identified areas of concern. Through discussions with Microsoft and the TC, the Plaintiffs have determined
Nevertheless, the Court would be remiss in suggesting that the compliance and enforcement road has been altogether smooth, even outside the context of Section IILE’s implementation. It is certainly true that, as Microsoft stresses, it has never been found to be out of compliance with the Expiring Provisions of the Final Judgments. See Memorandum of Points and Authorities of Microsoft Corporation in Opposition to Certain Plaintiff States’ Motions to Extend the Final Judgments (hereinafter “MS Opp’n”) at 11. However, it is also true that, over the years, compliance-related issues have arisen regarding virtually every aspect of Section III that the Plaintiffs have determined merited further investigation and warranted concern with Microsoft’s compliance efforts. See 7/3/03 JSR at 4-6 (describing ongoing questions related to § III.B compliance); 2/8/06 JSR at 10 (describing complaint under § III.C regarding OEM ability to customize first-boot experience); 6/19/07 JSR at 7-8 (describing reports alleging failure to disclose APIs as required by § III.D); 10/8/04 JSR at 7-8, 11 (describing concern .pursuant to § III.F regarding Microsoft contracts for .NET Framework); 10/19/05 JSR (describing issue under § III.G regarding draft specification for promotional CD that included exclusivity requirement); 10/17/03 JSR at 5-6 (describing § III.H issue relating to automatic invocation of IE). In each instance, the parties have— with the assistance of the TC — been able to negotiate a solution that has been acceptable to the parties and the Court. These negotiated solutions have obviated the need for compliance-related litigation and have precluded any possible Court findings of noncomplianee.
D. The Section III.E Saga
By far, the most significant focus of attention and criticism by the parties and the Court over the past five years has been Section III.E of the Final Judgments, which the Court once described as “the
most
forward-looking provision in [its] remedy.”
Remedy Opinion,
Section III.E of the Final Judgments requires Microsoft to license “on reasonable and non-discriminatory terms (consistent with Section III.I) any Communications Protocol” that is “(i) implemented in a Windows Operating System Product installed on a client computer, and (ii) used to interoperate, or communicate, natively ... with a Microsoft server operating system product.” Final Judgments, § III.E. As the California Movants stress, Microsoft was aware that it would be required to produce Communications Protocols and corresponding technical documentation at
When the Court held its first compliance-related Status Conference in this case on July 24, 2003, Microsoft represented that it had “identified more than 100 Communications Protocols encompassed by Section III.E” and developed a program, known as the Microsoft Communications Protocol Program (“MCPP”), under which third parties could license all of the Communications Protocols or a subset thereof. 7/3/03 JSR at 21. Microsoft also advised the Court that it had developed more than 5,000 pages of technical documentation, “produced by approximately ten technical writers working full-time for nine months.” Id. Microsoft began offering licenses under the MCPP in August 2002 and, as of July 2003, four ISVs had signed license agreements with Microsoft. Id. at 22. '
Plaintiffs’ initial § III.E enforcement efforts focused on ensuring that MCPP licenses were offered on reasonable and non-discriminatory terms, as required by §§ III.E and III.I of the Final Judgments. See id. at 6-10. Plaintiffs continued to investigate issues relating to the terms, royalty rates, and structure of the licenses offered under the MCPP into early 2004. See generally 10/17/03 JSR. Throughout that period, Plaintiffs — including the United States, the New York Group, and the California Group — stressed that the delay in Section III.E’s implementation might undermine its “forward-looking” nature. See 7/3/03 JSR at 9. In response, in October 2003 Microsoft reported that it had decided to allow licensees to extend the term of their licenses for an additional five years at any point during the license period. 10/17/03 JSR at 8-9. Still, in January 2004, Plaintiffs jointly advised the Court that, after conducting interviews with most of the then-current MCPP licensees as well as a number of prospective licensees, they were “concerned that the current licensing program has thus far fallen short of satisfying fully the goals of Section III. E.” 1/16/04 JSR at 2-3.
Also in January 2004, Plaintiffs reported to the Court that they had received a complaint regarding the sufficiency and completeness of the technical documentation provided by Microsoft to MCPP licensees, which the TC was investigating. Id. at 9. Plaintiffs reported a second complaint in this vein in April 2004, and informed the Court that the TC had “begun an investigation into this issue.” 4/14/04 JSR at 4-5. “As a result of this investigation and other work performed by the Plaintiffs, [Plaintiffs] concluded that the technical documentation nee[ded] substantial revision in order to ensure that it [would be] usable by licensees across a broad range of implementations as envisioned by Section III. E.” Id. at 5. Thus began the saga of the technical documentation, which continues unresolved to this day.
During the rest of 2004, the parties worked towards collectively developing a standard for completeness to which the technical documentation would be held, with the expectation that the project would be completed by the fall of 2004. 7/9/04 JSR at 5-6. All Plaintiffs — the state plaintiffs as well as the United States— continued to voice their concern that the delayed implementation of Section III.E should not be allowed to “reduce the useful life of the licensed technology to current
Microsoft released its first major revision of the technical documentation in early December 2004. 1/25/05 JSR at 3. While Plaintiffs believed that it represented a “significant improvement” over the previous documentation, they all remained concerned that further work was needed to ensure its completeness, usability, and accuracy. Id. To that end, the parties agreed to a comprehensive plan designed to remedy the deficiencies, which they expected to be completed in one year, i.e., by early 2006. Id. at 3-5. That plan involved two efforts, one to be undertaken by the TC, the other by Microsoft. Id. The TC’s portion of the plan soon began to make extensive progress, 6/1/05 JSR at 2-3, while Microsoft’s portion of the plan— dubbed “Troika” — became mired in difficulties, see generally id. By October 2005, the parties reported that under a “best-case” scenario, the Troika project would be completed in October 2006, ten months later than originally projected, and Microsoft admitted “[qjuite frankly,” that it “did not fully appreciate the scale, complexity, cost, and duration of the project,” and “overestimated the capability of existing technologies to meet the requirements of the effort.” 10/19/05 JSR at 5-6,14.
As the Troika-related problems emerged, the Plaintiffs — particularly those within the California Group — began to question whether Microsoft was devoting the resources necessary to ensure that Section III.E resulted in complete, accurate, and useable technical documentation. See 10/26/05 Status Hrg. Tr. at 20:7-26:19 (expressing the California Group’s opinion that “[ejssentially, Microsoft hasn’t done what it promised to do” and stressing the significance of the technical documentation within the Final Judgments’ overall remedial scheme). The Court likewise stressed the significance of accurate and complete technical documentation during various status conferences, admonishing Microsoft that “if there is an issue of resources, then put them in, whatever it takes to make this work.” Id. at 33:11-14.
In the Fall of 2005, the parties and the Court focused their attention on the Troika project, and the parties developed another four-part plan to address the project delays. 11/18/05 JSR at 2. The parties’ plan called upon the TC to assume responsibility for an increasingly significant portion of the work that Microsoft had previously committed to completing, while Microsoft agreed to “increase the resources dedicated to responding to the TC and to making resulting changes to the technical documentation” in response to Technical Documentation Issues (“TDIs”) identified by the TC. Id. at 2-8. Under the parties’ plan, Microsoft was to respond to TDIs within certain time frames, depending upon their severity, but by January 2006, Plaintiffs reported that Microsoft had fallen significantly behind in meeting those guidelines and that the number of outstanding TDIs was mounting. Pis’ 1/23/06 Resp. to Microsoft Suppl. Status Report. All Plaintiffs jointly condemned this slippage, advising the Court that “Microsoft need[ed] to dramatically increase the resources devoted to responding to technical documentation issues in order to get its performance under the [guidelines] back on track.” Id. at 2.
Based on all Plaintiffs’ sharp criticism of Microsoft, “the frequent delays with the Troika project, [and] Microsoft’s newfound disregard for the [TDI guidelines],” during
Unfortunately, what had seemed sq promising in February 2006 again proved ineffective. Rather than declining, the number of outstanding TDIs continued to rise, and Microsoft remained unable to promptly resolve open TDIs identified by the TC. 5/12/06 JSR at 3-5. By May 2006, the parties’ efforts towards implementing Section III.E reached a crisis point, as the delays stretched on and it became increasingly obvious that the available technical documentation was far from the type of quality product envisioned by Section III.E. Id. In response to mounting pressure from the Court and all of the Plaintiffs, Microsoft finally acknowledged that a new approach to the technical documentation was necessary, along with more resources. Id. at 4. As a result, Microsoft brought in a high-level executive, Robert Muglia, Senior Vice President of Microsoft’s Server and Tools Business, to analyze the lack of success in implementing Section III.E and to “determine the most efficient method for producing technical documentation that is of a sufficiently high quality to assure Plaintiffs and the TC that Microsoft is meeting its obligations to licensees.” Id. at 6. Mr. Muglia “and his team ultimately concluded that the current process of trying to fix issues identified by the TC one at a time was unlikely, in the foreseeable future, to result in [satisfactory] documentation.” Id.
Microsoft therefore determined that “a broader ‘reset’ would be much more effective and efficient, meaning that Microsoft [would] rewrite substantial portions of the documentation,”
id.,
in order to “describe the protocols in a context in which they [would] be implemented by people [with] limited knowledge of Windows,” 5/17/06 Status Hrg. Tr. at 39:9-18. At the May 17, 2006 status conference, which focused on the RESET plan, Microsoft admitted that prior to the RESET plan, it “didn’t have the exact right resources, [and] didn’t have the right process in place.”
Id.
at 39:3-8. Microsoft also acknowledged that it added significant resources to the technical documentation project in early 2006.
Id.
Indeed, while Microsoft originally devoted only ten employees to the technical documentation project,
see
7/3/03 JSR at 22, by May 2006, over 210 employees were involved in Microsoft’s technical documentation efforts, including 150 product team
The RESET plan undertaken in May-2006 was accompanied by the parties’ joint request that the Court extend Section III.E of the Final Judgment and certain related sections until November 12, 2009 to “ensure that all necessary work on the documentation [could] be completed and that current and future MCPP licensees [would] have a substantial period of time to make use of the revised documentation.” Id. at 10-13; see also Joint Motions to Modify the Final Judgments. The parties’ agreed-upon extension, which the Court approved in September 2006, extended Sections I, II, III.E, III.F.l, III.F.3, III.I, III J, IV, V, VI, VII, and VIII of the Final Judgments until November 12, 2009, and incorporated an agreement between Plaintiffs and Microsoft “that Plaintiffs have the right in their sole discretion to request an additional three-year extension of the extended portions of the decree until November 12, 2012, and that Microsoft will not oppose any such request.” NY/MS Joint Mot. to Modify the Final Judgment at 2-3. Along with the extension, Microsoft agreed that “even if the Final Judgments expire[d] completely in November 2009, it [would] continue, through November 11, 2012, to make the protocols included in the MCPP available for license on reasonable and non-discriminatory terms with a term of at least five years,” such that “industry members [would] effectively have the ability to license protocols through at least November 11, 2017.” 5/12/06 JSR at 10.
Since May 2006, the parties have diligently worked toward implementing the RESET plan. The TC has found the rewritten documentation emerging as a result of the RESET plan to be a vast improvement over the previous two forms of technical documentation created by Microsoft, and the Plaintiffs have reported that they are encouraged by this progress. See generally 8/30/06 JSR and 11/21/06 JSR. In addition, as of the parties’ last Joint Status Report, a total of 41 companies were licensing Communications Protocols pursuant to § III.E of the Final Judgments and 13 licensees were shipping products under the MCPP. 8/31/07 JSR at 6. However, even the RESET plan’s path has not been completely without pitfalls. Most significantly, in February 2007, Microsoft reported that it had conducted an internal audit and “determined that there [were] a number of protocols that [had to] be documented in addition to those [Microsoft] originally planned” to document. 3/5/07 JSR at 5. Microsoft projected that the overall time line for the RESET plan would have to be delayed by two months to allow for documentation of those protocols. Id.
Again, Plaintiffs — the United States along with the state plaintiffs — voiced their concern about the delay in Section III.E’s full implementation. At the March 12, 2007 Status Conference, the parties reported another agreement designed to address Plaintiffs’ continuing problems with the delay.
See generally id.;
3/12/07 Status Hrg. Tr. This plan involved two “audits” of Microsoft’s internal audit: one third-party consulting firm would review Microsoft’s audit process, while a second consulting firm would attempt to develop programmatic methods for searching the
As of the last status conference held in this case on September 11, 2007, Microsoft had released all initial versions of the rewritten technical documentation to the TC for testing, but the TC and Plaintiffs were far from concluding that the documentation was “substantially complete.” 8/31/07 JSR. The parties and the TC continue to conduct intensive testing of the technical documentation, and to review the corresponding overview/reference materials that Microsoft makes available to licensees. Id. In addition, while the first consulting firm’s audit of Microsoft’s internal audit is complete, the second consulting firm’s efforts are ongoing. Id. at 4. Further, in its January 15, 2008 Supplemental Status Report, Microsoft reported that it is still in discussions with the TC regarding the overview/reference materials, and that testing of the rewritten documentation continues, with over 900 TDIs outstanding against the new documentation. 1/15/08 MS Suppl. Report at 2-5.
Based on the foregoing history, it is abundantly clear that more than five years after the Communications Protocols and related technical documentation were required to be available to licensees under § III.E, the documentation envisioned by that Section is still not available to licensees in a complete, useable, and certifiably accurate form. Although the technical documentation project is complex and novel, it is clear, at least to the Court, that Microsoft is culpable for this inexcusable delay. To be sure, the delay has developed in stages, and at each step Microsoft commendably has been willing to work with the Plaintiffs and the TC to address their issues and identify a means of resolving them. The parties’ negotiations, in turn, have achieved a worthy goal by obviating the need for compliance-related litigation. 27 Quite simply, because the parties have negotiated solutions to each of the myriad issues arising under Section III.E, the Court has never been asked to find Microsoft out of compliance with Section III.E, and has not deemed a sua sponte finding of non-compliance necessary or fruitful in achieving compliance.
Nevertheless, practically speaking, Microsoft has never complied with Section III.E. Furthermore, Microsoft did not proactively bring the problems with its technical documentation to the Court’s attention. Instead, the majority of the issues relating to Section III.E that have arisen over the years have been identified by the Plaintiffs, through the efforts of the TC. While Microsoft eventually proposed the RESET plan, and has since cooperated in carrying it out, it did so in the face of mounting pressure from all Plaintiffs and the Court. In addition, there is no reason why the type of documentation finally being created under the RESET plan could not have been created from the outset if the necessary resources had been devoted. Clearly, the documentation finally emerg
In considering the Moving States’ motions to extend the Final Judgments, the Court must evaluate the facts as they are at this point in time. To that end, while the Court certainly commends Microsoft for its willingness to cooperate with Plaintiffs and negotiate solutions throughout the past five years, the fact remains that when the Final Judgments were entered, the parties and the Court anticipated that the documentation required under Section III.E would be available, at the latest, by February 2003. Instead, almost five years later, Section III.E, which was meant to be “the
most
forward-looking provision” of the Final Judgment,
Remedy Opinion,
E. The Moving States’ Motions
At the March 13, 2007 status conference in the consolidated cases, the California Group reported to the Court that it intended to undertake an effort to survey MCPP licensees regarding their experiences with, and the impact of, the Final Judgments. 3/13/07 Status Hrg. Tr. at 31:3-32:17. Also during that status conference, the Court requested that all of the Plaintiffs
During the September 11, 2007 status conference, the California Group announced its intent to file a motion asking the Court to extend all provisions of its Final Judgment, other than § III.B, through November 2012. See generally 9/11/07 Status Hrg. Tr. at 27:3-29:10; 36:22-56:13. At that same status conference, the Court indicated that it was reserving all comments on the effectiveness of the Final Judgments until the expected November 2007 expiration of many provisions, but made some observations regarding the “background against which the final judgment was entered,” and indicated that any request to extend the Final Judgments would have to be “for an identifiable purpose.” Id. at 31:5-36:21.
The California Movants filed their Motion to Extend on October 16, 2007, and on October 18, 2007, the New York Movants filed their Motion to Alter Judgment, joining the California Movants’ request for an extension. On October 19, 2007, the United States filed a Report indicating that they would not move to extend the Final Judgment in United States v. Microsoft. Accordingly, the Final Judgment in United States v. Microsoft lapsed on November 12, 2007. On October 23, 2007, the Court held a telephone conference on the record with all parties regarding the need for thorough briefing on the Moving States’ motions. On October 30, 2007, the New York Group, the California Group, and Microsoft filed — and the Court granted — a Joint Motion to extend the Expiring Provisions of the Final Judgments “only for so long as necessary (but no longer than January, 31, 2008) to allow” the Court to properly consider the pending motions to extend. Pursuant to a schedule agreed upon by the parties and the Court, Microsoft filed its Opposition to the Moving States’ motions on November 6, 2007, the United States filed a Motion for Leave to Participate as Amicus Curiae and a proposed amicus brief on November 9, 2007, and the Moving States filed a joint Reply on November 16, 2007.
Having reviewed all of the foregoing filings, on December 10, 2007, the Court issued an Order directing the Moving States and Microsoft to file additional briefing on a “very targeted” issue regarding the relation between Section III.E and the other provisions of the Final Judgments. As ordered, the Moving States filed their additional Memorandum on December 18, 2007, and Microsoft filed its Opposition thereto on December 28, 2007. Finally, on January 8, 2008, the Court ordered the Moving States to file a Reply to Microsoft’s Opposition, addressing a list of pointed questions. The Moving States did so on January 11, 2008. As such, the Moving States’ motions to extend finally are fully ripe for review.
II: LEGAL STANDARD
The Moving States and Microsoft disagree over the appropriate legal standard
As this Court noted in the Settling States Opinion:
The D.C. Circuit [has] made clear that “district courts enjoy no free-ranging ‘ancillary’ jurisdiction to enforce consent decrees, but are instead constrained by the terms of the decree and related order.” Pigford v. Veneman,292 F.3d 918 , 924 (D.C.Cir.2002). The Pigford [v. Veneman] court further explained that the district court’s power over a consent decree, reflecting the hybrid between judicial order and contract, is limited to two sources. A district court may interpret and enforce a decree to the extent authorized by the decree itself or by the related order. Id. at 923. Additionally, a district court may modify a decree pursuant to Rule 60(b)(5) of the Federal Rules of Civil Procedure. Id.
Settling States Opinion,
The resulting “broadly drawn” retention of jurisdiction clause vests the Court with authority to modify any provision of the Final Judgments upon application by any party. Final Judgments, § VII.
29
Indeed, the retention of jurisdiction provisions of the Final Judgments are strikingly different from the provision in
Pigford v. Veneman,
which was “limited by its plain language ... to situations involving decree violations.”
Furthermore, the Court notes Microsoft’s implicit suggestion that the Court’s authority to extend the Final Judgments
The Court may also modify the Final Judgments under its power in “equity to modify a decree of injunctive relief,” which the D.C. Circuit has described as “long-established, broad, and flexible.”
United States v. Western Electric Co.,
The Moving States argue that the Court “is granted broad discretion to modify a decree in order to accomplish its intended result.” CA Mem. at 7. In so arguing, they rely upon
Western Electric,
in which the D.C. Circuit stated that “[a]t the request of the party who sought the equitable relief, a court may tighten the decree in order to accomplish its intended result,”
For its part, Microsoft asserts that the “relevant standard for modifying decrees was articulated by the United States Supreme Court in
Rufo v. Inmates of the Suffolk County Jail,
To be sure,
Rufo
is binding law, which the D.C. Circuit applied to motions to modify consent decrees in
Western Electric
and
Pigford v. Veneman, see generally
The Moving States are correct that the instant situation is qualitatively different from one in which an enjoined party seeks relief from a judgment, and that the Supreme Court cases discussed above suggest that a government enforcer may move to modify a consent decree in order to “accomplish its intended result.”
United Shoe,
In addition, courts in other circuits have recently applied
Rufo
to cases in which the beneficiary of a consent decree sought to extend the decree’s term or sought other modifications to consent decrees.
See Thompson v. U.S. Dep’t of Hous. & Urban Dev.,
In light of the foregoing, Microsoft may well be correct in arguing that
Rufo
applies to the instant case. Ultimately, however, the Court need not resolve this “thorny issue,”
Cook,
Ill: DISCUSSION
The Moving States’ motions seek to extend the Final Judgments until November 12, 2012 — five years beyond their original terms — and proffer a variety of arguments that such a lengthy extension is warranted pursuant to either United Shoe or Rufo. Having carefully reviewed each of the Moving States’ arguments in favor of extension, as well as Microsoft’s Opposition thereto and the United States’ amicus brief, the Court concludes that it is appropriate to extend the Expiring Provisions of the Final Judgments until November 12, 2009 due to the unforeseen delay in the implementation of Section III.E of the Final Judgments.
The Court therefore addresses the parties’ arguments regarding the Section III.E delay first, before turning to the Moving States’ other arguments in favor of extension. Ultimately, the Court rejects the Moving States’ other grounds, finding that their arguments are either foreclosed by the previous opinions of the trial court and the appellate court, or that they require premature speculation that does not meet the Moving States’ burden under United Shoe and/or Rufo.
A. Extension of the Expiring Provisions Through 2009 is Appropriate Due to the Unforeseen Delay in the Implementation of Section III.E
As detailed above, at the time that the Court entered the Final Judgments, all parties involved anticipated that the technical documentation required under Section III.E would be released, at the latest, by February 2003. Instead, five years later, the rewrite of the technical documentation has only recently been completed, the corresponding overview/reference materials are not available to licensees, and the testing of the revised technical documentation is far from finished. As such, no one can deny that licensees do not yet have access to a set of usable, accurate, and certifiably complete technical documentation, as contemplated by Section III.E and by the Court’s various remedy-related opinions.
Nor can it be denied that, as a result of the delay in Section III.E’s implementation, the provisions of the Final Judgments have not yet had the chance to operate together as a comprehensive remedy. As the Moving States repeatedly stress, the Final Judgments were constructed as a unitary framework, with the various provisions intended to complement and reinforce each other.
See
CA Mem. at 13-15; NY Mem. at 6 (quoting United States’ Resp. to Public Comments ¶ 413 (“it is the overall impact of the various decree provisions working together over the course of the five-year term that will restore competitive conditions in the market.”)). Indeed, the Court’s
Settling States Opinion
described the proposed consent decree as “[f]ar from an amalgam of scattered rules and regulations pieced and patched together to restrict Microsoft’s anticompetitive business conduct,” but rather a judgment that “adopts a clear and consistent philosophy such that the provisions form a tightly woven fabric.”
Settling States Opinion,
Rufo
explains that “Modification is [] appropriate when a decree proves to be unworkable because of unforeseen obstacles,”
id.
at 384,
The Court cannot know what impact the technical documentation required by Section III.E will have on the market once it is finally available in a complete, accurate, and useable form. Nevertheless, the Moving States highlight scenarios in which the Expiring Provisions of the Final Judgments might yet play a significant role in helping § III.E achieve its full potential. The Moving States focus on the possibility that an MCPP licensee who writes an application using software hosted on a server will also wish to add “software to the client to take advantage of the functionality that the server provides.” Moving States’ Resp. to the Court’s December 10, 2007 Order (hereinafter “Moving States’ Dec. 10 Resp.”) at 2-3. The Moving States note, and Microsoft agrees, that certain companies, including Apple, Yahoo!, and Google, are already making use of a product approach that involves both server-side and
The Moving States specifically suggest that in the future an MCPP licensee could “creatfe] a media server that uses the [MCPP] media protocols to support Microsoft media formats, while also supporting competing formats.” Moving States’ Dec. 10 Resp. at 4. However, because the “licensee cannot rely on Microsoft’s media player to read all of the formats,” it “must develop its own player for the Windows client, or find third parties to develop compatible players.” Id. The Moving States continue to explain how, in that scenario, the Expiring Provisions would support each other in maximizing the procompeti-tive impact of the server-side application developed using MCPP protocols: § III.A would prevent Microsoft from retaliating against an OEM for distributing the licensee’s media player; § III.C would guarantee OEMs the freedom to place the media player on the Windows desktop and in menus; § III.D would give the licensee access to the APIs needed to create the media player; § III.F would protect the licensee if it sought to have a third-party ISV create the media player; § III.G would prevent Microsoft from entering into agreements aimed at excluding the competing media player; and § III.H would allow the end user to set the competing media player as a default. Id. at 4-5.
Microsoft correctly points out that the development of the client-side product in the Moving States’ examples is “well beyond the scope of Section III. E, ... [and] beyond the scope of the MCPP license itself’ because “[o]nce software is added to the client, the server and the application can communicate directly without the need for the proprietary protocols supported in the Windows client.” MS Opp’n to Moving States’ Dec. 10 Resp. at 5-6 & n. 4. Indeed, because Section III.E only requires the disclosure of Communications Protocols that are “used to interoperate, or communicate, natively (i.e., without the addition of software code to the client operating system product) with a Microsoft server operating system product,” the client-side product in the Moving States’ examples could not make use of protocols disclosed under Section III.E. See Final Judgments, § III.E. But it is nevertheless true that an MCPP licensee could use such protocols to develop a server product, and then seek to maximize the potential of that server product in ways that require the protections of the remaining provisions of Section III. In the face of the Moving States’ realistic examples, allowing the other provisions of the Final Judgments to lapse before Section III.E has even been given a chance to succeed might threaten the ability of the Final Judgments to achieve their full procompetitive impact. Such an outcome would certainly be detrimental to the public interest.
The foregoing discussion also demonstrates that the Section III.E delay has impeded the Final Judgments from “accomplishing their] intended result” and “achieving their] principal objects.”
United Shoe,
Furthermore, the Court’s
Remedy Opinion
makes clear that § III.E represents only one avenue towards achieving the Final Judgments’ overall goals. Microsoft attempts to obscure this fact, arguing that the § III.E delay does not warrant an extension of the other provisions of Section III because “whereas Sections III.A, C, D, F, G, and H all deal with the treatment of middleware products
running on Windows,
Section III.E was designed to encourage development of platform alternatives
running on servers
fie., not running on Windows).” MS Opp’n at 16. While Microsoft is correct that Section III.E focused on servers while the other provisions of Section III focused on client-side applications, its argument demonstrates only that Section III.E took a different approach to achieving the Final Judgments’ overall goals. Microsoft’s argument thus does not negate the fact that the parties and the Court have always viewed Section III.E as just one means to the Final Judgments’ overall ends.
See Settling States Opinion,
To the extent that Microsoft’s argument suggests that Section III.E was forward-looking in nature, while the other provisions of Section III were solely retroactive, that inference is unsupported by either the text of the Court’s remedy-related opinions, or the realities of the Final Judgments. It is certainly the case that the other provisions of Section III aimed to “end Microsoft’s restrictions on potentially threatening middleware,” but those provisions also sought to “prevent it from hampering similar nascent threats in the future, and restore the competitive conditions created by similar middleware threats.”
Massachusetts v. Microsoft,
Microsoft also argues that the Moving States have not carried their burden of demonstrating that the Section III.E delay necessitates an extension of the other provisions of Section III because they
In any event, the Court rejects Microsoft’s suggestion that the other provisions of Section III should not be extended unless Section III.E would be doomed to fail in their absence. MS Opp’n at 14. The Moving States’ Response to the Court’s December 10, 2007 Order concedes that the provisions of Section III are “complementary, not interdependent,” but nevertheless argues that “the Final Judgment would be much less likely to achieve the as yet unfulfilled remedial goals ... if the only provision that remains in effect is § III.E.” Moving States’ Resp. to Dec. 10 Order at 10. For its part, Microsoft does not point to language in any of the Court’s remedy-related opinions suggesting that each of the Final Judgments’ provisions were expected to work in isolation, and the Court is not aware of any such language. To the contrary, the Court’s remedy-related opinions affirm, and the Court continues to agree, that the various provisions of the Final Judgment were expected to work in tandem towards achieving the Final Judgments’ overall goals. It is therefore sufficient that the other provisions support Section III.E, even if Section III.E is not actually fully dependent upon them.
Finally, Microsoft suggests that it is not necessary to extend the Expiring Provisions of the Final Judgments in order to support Section III.E because the “proliferation of Web-based computing has, in effect, accomplished what Section III.E was designed to do, although not exactly in the way that was anticipated in 2001 when Section III.E was created.” MS Opp’n at 16-17. Without drawing conclusions as to the accuracy of Microsoft’s statement, the Court notes only that it does not establish that Section III.E has become irrelevant. The Court recognizes that the goals have been thwarted by the time that has been lost as a result of the delays, attributed solely to Microsoft, in Section III.E’s implementation, and understands that it cannot recreate the opportunities that existed when the Final Judgments were entered.
Microsoft’s arguments thus fail to alter this Court’s decision that an extension of the Expiring Provisions is warranted due to the delay in Section III.E’s implementation and the inexorable conclusion that, as a result, the Final Judgments have yet to operate as a comprehensive whole. The Moving States’ request would be viewed in a different light if eertifiably complete, accurate, and useable technical documentation was already available to and in use by licensees. In that case, the Court would be in a position to evaluate the relevance of the Expiring Provisions to those licensees’ efforts. Due to the delay, of course, that is not the current situation. Instead, Microsoft seeks to let the majority of Section Ill’s protections lapse despite the fact that Section III.E — once described as the
“most
forward-looking provision” of the Final Judgments,
Remedy Opinion,
B. The Moving States’ Other Arguments In Favor of Extension Lack Merit
In light of the Court’s conclusion that the Section III.E delay and its repercussions on the Final Judgments’ implementation warrant an extension of the Expiring Provisions under either Rufo or United Shoe, the Court need not tarry long over the Moving States’ remaining, meritless, arguments for extensions. The Court therefore addresses each very briefly below, albeit not in the order presented by the Moving States.
First, the Moving States highlight the fact that no licensee has, as of yet, developed a general server product under the MCPP, arguing that it constitutes a “changed circumstance” for purposes of the
Rufo
standard.
See
Moving States Reply at 14-15; CA Mem. at 12. In particular, the Moving States note that, according to the results of the California Group’s survey, “MCPP licensees tend to develop products that complement, rather than compete with, Windows features.”
Id.
(citing CA Group Rep. on Remedial Effectiveness; 6/19/07 JSR at 14). The Moving States are correct that the Court concluded that the remedy in this case should encompass server/network computing due to the potential for “non-Microsoft operating systems to provide a platform which competes with Windows itself.”
Remedy Opinion,
The Moving States similarly find a “changed circumstance” in the fact that no major OEM has pre-installed a rival browser to Microsoft’s IE on its new PC systems. CA Mem. at 16-18; Moving States’ Reply at 16-18. The Moving States are correct that this Court and the D.C. Circuit’s remedy opinions projected that allowing “OEMs to disable end-user access to IE, and thereby to avoid the costs of having to support both IE and a rival browser,” would make OEMs “more likely to install a rival browser based upon market determinants, such as consumer demand,” and “that OEMs’ new freedom to respond to market demand would enhance competition between Microsoft and other manufacturers of middleware.”
Massachusetts v. Microsoft,
The Moving States’ focus on the web browser market is also inappropriate for the even more fundamental reason that the web browser market was not the relevant market for purposes of the liability findings. To the contrary, the D.C. Circuit concluded that the Plaintiffs failed, in the liability phase, to establish the existence of a properly defined market for web browsers.
See Microsoft,
The Moving States attempt to gloss over the fact that neither web browsers nor servers were the relevant market for purposes of the liability findings in this case by asserting that Microsoft’s alleged dominance of those markets nevertheless matters because emerging web-centric technologies are “dependent on web browsers and servers for access to consumers,” and “require computer equipment running a client or server operating system.” CA Mem. at 6, 20-22. According to the Moving States, the continuing dominance of IE and Windows offers Microsoft the ability “to use the browser as a chokepoint,” id. at 5, so as “to impede the development of emerging middleware threats with the potential to erode the applications barrier to entry protecting its Windows monopoly,” Moving States’ Reply at 25. The Court notes that the Moving States’ claims in this respect are not undisputed, as one of the expert reports submitted in support of Microsoft’s Opposition argues that Microsoft would have neither the power nor the incentive to limit consumer access to internet technologies. See MS Opp’n, Ex. A (11/6/07 Suppl. Expert Rep. of Marco Ian-siti).
In any event, the Court need not resolve this largely hypothetical factual dispute. As Microsoft acknowledges, if it were to use its alleged dominance in the web browser market in order to stifle competing middleware, “such conduct would [likely] violate § 2 of the Sherman Act, and Microsoft would remain subject to penalty under that statute.” MS Opp’n at 19.
31
This Court’s
Remedy Opinion
previously recognized as much when it stated that “although Plaintiffs
assume
that Microsoft will engage in anticompetitive conduct in the future in conjunction with its participation in this emerging area of technology, this case cannot be used as a vehicle by which to fight every potential future violation of the antitrust laws by Microsoft-”
Remedy Opinion,
Again, the Court concludes that resolution of this factual dispute is unnecessary, and indeed inappropriate. As an initial matter, insofar as the Moving States’ argument is premised on their assertion that “Microsoft’s share of the PC operating system market has been greater than 90% for at least the past 15 years,” CA Mem. at 4, it is entirely misplaced. The Court’s
Remedy Opinion
reiterated that “the monopoly in this case was not found to have been illegally acquired, but only to have been illegally maintained.”
The Moving States’ focus on the “pace of change” in the relevant market likewise cannot support an extension of the Expiring Provisions of the Final Judgments. It is correct that this Court’s selection of a five-year term for the Litigating States’ remedy and approval of the same term in the Settling States’ consent decree turned on an understanding that “the industry at issue in this case is remarkable for its constant and rapid change.”
Remedy Opinion,
C. Microsoft’s Additional Arguments Against Extension
Having addressed the Moving States’ main arguments for extending the Expiring Provisions, the Court now considers the arguments raised by Microsoft against that outcome, to the extent they are not addressed above.
Microsoft asserts that its “compliance with the expiring provisions of the Final Judgment, its history of going beyond its obligations to resolve issues raised by the Plaintiffs and the [TC], and its commitment to adhere to Final Judgment principles on a going-forward basis” are grounds for denying the Moving States’ motions and relieving Microsoft of the burden of “operating under the shadow of a judicial decree.” MS Opp’n at 11 (citing Windows Principles: Empowering Choice, Opportunity, and Interoperability, available at http://www.microsoft.com/about/corporate citizenship/citizenship/businesspractices/ windowsprineiples.mspx (published Aug. 24, 2007)). The Moving States attempt to downplay Microsoft’s claim by asserting that “Microsoft itself should hardly be heard to object to extending the decree” because it “professes to be ‘committed to running its Windows business in accordance’ with [the Windows Principles]” and because it “conceded, in the case brought by the European Commission, that the settlement in this litigation has not ‘had any negative impact on its incentives to innovate.’ ” N.Y. Mem. at 7; CA Mem. at 22 & n. 22.
The Moving States arguments in this regard are not well-taken. Microsoft’s commitment to the Windows Principles is admirable, and certainly should not be held against Microsoft. Furthermore, the Court is well aware that operating under a judicial decree has negative connotations. See MS Opp’n at 11. The Court nevertheless concludes, for the reasons detailed above, that an extension of the Expiring Provisions is warranted due to the delay in Section III.E’s implementation and the impact of that delay on the Final Judgments’ operation.
Microsoft next argues that the New York Movants are on shaky ground because their August 30, 2007 Review of the Final Judgments, filed jointly with the United States, concluded that the Final Judgments had achieved their goals. US Amicus Br. at 5-7; MS Opp’n at 8. The New York Movants address any apparent inconsistency by explaining that their earlier filing was not a “mission accomplished” pronouncement. Moving States’ Reply at 23. According to the New York Movants, while they believe the Final Judgments are “accomplishing their stated goal of fostering competitive conditions ... [t]here is still much work for the Court’s Final Judgments to do.” Id. (quoting N.Y. Group Review of Final Judgments at 6, 8). The Court agrees with the New York Mov-ants that their positions are not inherently inconsistent and that, in any event, their Review of the Final Judgments in no way waived their right under their Final Judgment to seek the additional relief they now believe is warranted.
Microsoft further asserts that, as a party to a negotiated consent decree, the New York Movants should not be able to escape the five-year term of that decree, because the decree should be accorded the weight of a binding contract. MS Opp’n at 8. The United States echoes Microsoft’s argument in its
amicus
brief. US
Amicus
Br. at 5-7. The Court certainly recognizes that modification of a consent decree is an “ex
Just as the consent decree and court-ordered remedy had the same goals, so did their identical Sections III.E play the same role within the two Final Judgments. And, as noted above, the Court’s power to modify an injunction or grant relief from a judgment is the same regardless of whether a consent decree or litigated decree is at issue.
Agostini,
Finally, continuing with its argument that the New York consent decree is a binding contract, Microsoft argues that it “should not be forced to endure more than [it] bargained for,” given its overall compliance with the Expiring Provisions and its cooperation with the Plaintiffs and TC over the past five years. MS Opp’n at 11. According to Microsoft, if the New York Movants are allowed to unilaterally extend the expiring provisions, it will deter parties from negotiating consent decrees and from going “beyond the letter of their decree obligations.”
Id.
at 11-12. The United States and Visa and Weyerhaeuser echo Microsoft’s concern in their respective
am-ici
briefs. US
Amicus
Br. at 7;
see generally
Visa/Weyerhaeuser
Amici
Br. In that regard, the Court notes that
Rufo
considered and rejected an argument that its flexible standard “would deter parties to litigation ... from negotiating settlements.”
The Court is nevertheless sensitive to the policy argument made by Microsoft and
amici,
and therefore stresses that its decision to extend the Expiring Provisions of the Final Judgment must be viewed in the proper, extremely unique, context.
The Court does not dispute that Microsoft has been overwhelmingly cooperative with the Plaintiffs and the TC over the past five years. To the contrary, the Court commends Microsoft for its willingness to address issues as they arose and to negotiate solutions rather than force litigation. In many respects, Microsoft’s conduct has been a model for parties engaged in complex and protracted litigation. But Microsoft’s good citizenship does not erase the fact that, more than five years after the Final Judgments called for the Section III.E Communications Protocols to be available, licensees do not yet have the benefit of a certifiably complete, accurate, and useable set of technical documentation. Nor can the fact that Microsoft has never been found to be out of compliance with the Final Judgments obscure the obvious conclusions that, practically speaking, Microsoft has failed to comply with Section III.E, and that its noncompliance is highly material. Indeed, Microsoft admitted as much when, in May of 2006, it admitted that it “didn’t have the exact right resources [or] the right process in place,” and suggested a massive overhauling of the previous attempts at generating the technical documentation required under Section III.E. 5/17/06 Status Hrg. Tr. at 39:3-8.
As discussed above, neither the parties nor the Court will ever know how the relevant market might have developed if the Section III.E technical documentation had been available five years ago. Nor can the Court project what use may be made of the technical documentation in the future. But the Moving States have proffered realistic examples of ways in which the Expiring Provisions of the Final Judgments can yet play a role in maximizing the impact of products to be developed under Section III.E. In light of Microsoft’s admitted culpability in the Section III.E delay, the Court concludes that it is not inequitable to extend the Expiring Provisions in order to allow the provisions of the Final Judgments to operate together as originally envisioned.
D. The Appropriate Length of the Extension
The sole remaining issue, then, is the length of time for which the California Group and New York Group Final Judgments should be extended. The Moving States seek to extend the entire Final Judgments — the Expiring Provisions as well as Section III.E — until November 12, 2012. Although the Moving States raise a number of arguments in support of this request, the Court ultimately agrees with Microsoft and the United States that it is
The Moving States first attempt to rehash the Litigating States’ argument that “ten years is the standard term for antitrust consent decrees entered into by the Antitrust Division of the United States Department of Justice.”
Remedy Opinion,
The Moving States present a far more compelling argument when they assert that “continued oversight by plaintiffs, the TC, and the Court, is essential to assure the integrity of the MCPP,” as well as “to give prospective licensees the confidence that the [technical documentation] they will get, if they take a license, is complete and accurate.” CA Mem. at 12.
33
The Court is certainly concerned with maximizing the procompetitive impact of the Final Judgments and encouraging continued innovation that serves to eliminate the applications barrier to entry. The Court also recognizes that developing a product under an MCPP license “requires considerable advance planning, capital investment and other expenditure^],”
id.,
and appreciates the significant role the TC plays in ensuring that the technical documentation produced pursuant to Section III.E is of a nature and quality that is attractive and useful to current and prospective licensees. Nevertheless, the Court agrees with Microsoft and the United States that it is premature at this point to extend the Final Judgments through 2012 based on the Moving States’ speculation that the delays in the implementation of Section III.E will persist.
See
CA Mem. at 11. From all reports, it appears that Microsoft has finally committed the resources necessary, and adopted an ap
Moreover, for the time being at least, the oversight of the TC, the Plaintiffs, and the Court is assured, because Section III.E and the other extended provisions do not expire until November 2009. Parties considering licenses should therefore take comfort in the fact that the TC, the Plaintiffs, and the Court’s oversight will continue while the technical documentation is tested and finalized. In addition, as the Moving States note, because “present and future client/server [Communications Protocols] are available for license through November 11, 2012,” Microsoft “will be required to document” any “new [Communications Protocols] in its next major Windows client and server releases.” CA Mem. at 11. Thus, the current oversight period of the Plaintiffs, the TC, and the Court also encompasses the launch of Microsoft’s Windows Server 2008, which is reportedly scheduled for release in February 2008. Id.
Finally, the Moving States argue that “a five-year extension of the existing decree does no more than was originally intended by the parties and by the Court ... [but rather allows] the decree [to] be in effect, together as intended, for five years.” Moving States’ Reply at 18. This argument certainly has appeal, given the Court’s conclusion that an extension of the Expiring Provisions is warranted because the unforeseen Section III.E delay has prevented the provisions of the Final Judgments from working in tandem. Indeed, the
United Shoe
standard suggests that the Court would be justified in extending the entire Final Judgments until November 12, 2012 in order to “accomplish [their] intended result.”
See Western Electric,
The Court thus concludes that the most appropriate approach is to assess the need for continued Court oversight in reasonable incremental periods. Section III.E and the other extended provisions are currently set to expire on November 12, 2009.
See
Modified Final Judgments, Section V.A. That extension was sought jointly by the Plaintiffs and Microsoft in order to ensure that Section III.E be given a full opportunity to succeed.
See
NY/MS Joint Mot. to Modify the Final Judgment at 2. As discussed extensively above, the Final
Nevertheless, the Court’s decision not to extend the Final Judgments beyond November 12, 2009 now does not foreclose the possibility of doing so in the future. Indeed, the mechanisms are already in place to reexamine Section III.E’s implementation and the Final Judgments’ termination in the Fall of 2009. At present, the Final Judgments give Plaintiffs the right “in their sole discretion to request an additional three-year extension of [Sections I, II, III.F.l, III.F.3, III.E, III.I, III.J, IV, V, VI, VII, and VIII] of the decree until November 12, 2012,” with the understanding that “Microsoft will not oppose any such request.” NY/MS Joint Mot. to Modify the Final Judgment at 2-3. 35 Similarly, the door remains open for the Court to reassess the need for continued oversight as the expiration of the Final Judgments in November 2009 approaches. At that point, certifiably complete, accurate, and useable technical documentation will, presumably, be available to licensees, and the Court will be in a far better position to evaluate Section III.E’s implementation, as well as the role that the other provisions of the Final Judgments play in supporting Section III.E.
Based on the showing made by Moving States,
36
the Court concludes that they have met their burden of establishing that the unforeseen delay in Section III.E’s implementation constitutes changed circumstances. The Moving States have further established that the repercussions from the delay have impacted the Final Judgments’ procompetitive potential and
IY: CONCLUSION
For the foregoing reasons, the Court shall GRANT-IN-PART and DENY-IN-PART the Moving States’ motions to extend the Final Judgments, and shall extend the Expiring Provisions of the Final Judgments, with the exception of Section III.B, until November 12, 2009.
Notes
. An Executive Summary of this Memorandum Opinion, which does not represent the official and complete Court findings of fact or conclusions of law, is available on the public docket for this case.
. The California Movants include the States of California, Connecticut, Iowa, Kansas, Minnesota, the Commonwealth of Massachusetts, and the District of Columbia. See Plaintiff States’ Memorandum of Points and Authorities in Support of their Motion to Extend the Final Judgment Until November 12, 2012 (hereinafter "CA Mem.”) at 1. The New York Movants include the States of New York, Maryland, Louisiana and Florida. See Joinder of Plaintiff States of New York, Maryland, Louisiana and Florida in Moving to Extend the Final Judgments (hereinafter “NY Mem.”) at 1. As detailed below, the California Movants and New York Movants each belong to larger groups of state plaintiffs in this action, respectively the “California Group” or "Litigating States” and "New York Group” or “Settling States.”
. A number of states who were Plaintiffs in this action have not moved to extend the Final Judgments. According to the New York Movants, "Plaintiff States Illinois, Kentucky, and Ohio do not object to extending the Final Judgments. Plaintiff States Michigan, North Carolina, and Utah take no position on the decree extension. Plaintiff State Wisconsin does not join in the motion.” NY Mem. at 1 n. 2.
. By separate Order, the Court shall grant the Motion of the United States for Leave to Participate as Amicus Curiae. The Court shall also grant the Motion of Visa, Inc. and Weyer-haeuser Company for Leave to File Brief as Amici Curiae. The Court has reviewed the Visa/Weyerhaeuser amicus brief and notes that it raises an argument also asserted by Microsoft and the United States, which is thoroughly considered below.
. The Court's extension of the Expiring Provisions does not include § III.B, which neither the California Movants nor the New York Movants seek to extend. See CA Mem. at 1; NY Mem. at 8 n. 14.
. The “Plaintiffs” for purposes of the Court’s
Remedy Opinion
included the States of California, Connecticut, Florida, Illinois, Iowa, Kansas, Kentucky, Louisiana, Maryland, Michigan, Minnesota, New York, North Carolina, Ohio, Utah, West Virginia, and Wisconsin, the Commonwealth of Massachusetts, and the District of Columbia.
See
. "PC” is short for "personal computer."
Remedy Opinion,
Operating systems perform many functions, including allocating computer memory and controlling peripherals such as printers and keyboards. Operating systems also function as platforms for software applications. They do this by “exposing” — i.e., making available to software developers — routines or protocols that perform certain widely-used functions. These are known as Application Programming Interfaces, or "APIs.”
Microsoft,
. Plaintiffs focused their attention on "two such middleware threats to Microsoft’s operating system dominance — Netscape Navigator and the Java technologies.”
Remedy Opinion,
. For the sake of clarity, the Court defines a number of acronyms that are used throughout the previous opinions of this Court and the D.C. Circuit, as well as in the Final Judgments: "OEMs” are "original equipment manufacturers;” "IAPs” are Internet access providers; "ISVs” are independent software vendors; "IHVs” are independent hardware vendors; and "ICPs” are internet content providers. See Final Judgments, §§ VI.F-I; VI.O.
. The "Java” technologies are "a set of technologies developed by Sun Microsystems,” which the D.C. Circuit described as "another type of middleware posing a potential threat to Windows’ platforms.”
Microsoft,
. "Intel is a firm engaged principally in the design and manufacture of microprocessors,” and a "segment of Intel’s business develops software.”
Remedy Opinion,
. In addition to the claims described above, Plaintiffs’ complaint originally included a separate claim for "monopoly leveraging” under § 2 of the Sherman Act, on which Judge Jackson granted summary judgment in favor of Microsoft because the claim ran "contrary to both economic theory and the Sherman Act’s plain language.”
Remedy Opinion,
.As noted in this Court’s various remedy-related opinions, "the objective of 'terminating the illegal monopoly,’ is incompatible with the facts of this case [because] [n]either the district court, nor the appellate court concluded that Microsoft had illegally obtained its monopoly,” but only found that Microsoft had illegally maintained its monopoly.
New York v. Microsoft Corp.,
. The Settling States, or New York Group, include the States of New York, Ohio, Illinois, Kentucky, Louisiana, Maryland, Michigan, North Carolina, and Wisconsin.
Remedy Opinion,
. The Litigating States, or California Group, include the States of California, Connecticut, Florida, Iowa, Kansas, Minnesota, Utah, and West Virginia, the Commonwealth of Massa
. The Court entered three Final Judgments in November 2002; two in the instant case, and one in United States v. Microsoft. Because the United States does not seek to extend the Final Judgment in United States v. Microsoft, however, this opinion addresses only the two "Final Judgments” entered in this case.
. As discussed in greater detail below, the Court deemed it “imperative, in this unusually complex case, for the Court's retention of jurisdiction to be clearly articulated and broadly drawn,” and therefore suggested that the parties amend the proposed consent decree to reserve for the Court "the power to
sua sponte
issue orders or directions regarding [ ] the final judgment, including, but not limited to orders regarding the construction or carrying out of the final judgment, the enforcement of compliance therewith, and the punishment of any violation thereof.”
Tunney Act Opinion,
.In a previous Memorandum Opinion, the Court had reviewed the pertinent procedural history and determined that the parties had satisfied the other requirements of the Tunney Act.
See generally United States v. Microsoft Corp.,
. Section III.A of the Litigating States' Final Judgment also prohibits Microsoft from threatening retaliation against OEMs for the same conduct. Litigating States Final Judgment, § III.A.
. “Covered OEMs” are "the 20 OEMs with the highest worldwide volume of licenses of Windows Operating System Products reported to Microsoft in Microsoft’s fiscal year preceding the effective date of the Final Judgment[s].” Final Judgments, § VI.D.
. As noted above, the Moving States do not seek to extend § III.B.
. The Settling States’ Final Judgment provides that Microsoft may not impede an OEM’s ability to automatically launch Non-Microsoft Middleware "if a Microsoft Middle-ware Product that provides similar functionality would otherwise be launched automatically.” Settling States Final Judgment, § III.C.3. In contrast, the Litigating States' Final Judgment narrows further the situations in which Microsoft may impede an OEM’s ability to automatically launch Non-Microsoft Middleware, limiting Microsoft's ability to do so to those circumstances where the Non-Microsoft Middleware "replaces or drastically alters the Windows Operating System Product user interface.” Litigating States Final Judgment, § III.C.3.
.The Settling States' Final Judgment prevents Microsoft from impeding by agreement an OEM’s ability to present its own IAP offer during the initial boot sequence, "provided that the OEM complies with reasonable tech
. Like § III.A, § III.F of the Litigating States’ Final Judgment also prohibits Microsoft from threatening retaliation against ISVs and IHVs. Settling States Final Judgment, § III.F.
. As noted above, because the Litigating States opposed the creation of a technical committee, their Final Judgment included only a Compliance Officer. Over time, however, the Litigating States recognized the ben- , eficial role the TC played in the Settling States’ enforcement efforts. See 9/11/07 Status Conference Hrg. Tr. at 38:14-39:7. In addition, as Section III.E emerged as the main area of compliance-related issues, the Litigating States retained their own expert on communications protocols and technical documentation standards, Mr. Craig Hunt. See 7/9/04 Joint Status Report. Mr. Hunt has since worked alongside the TC, and participated in its activities on behalf of the Litigating States. Practically speaking,- then, the TC’s activities have redounded to the benefit of all of the Plaintiffs, not only the Settling States. Moreover, when the Court refers to the TC henceforth, it intends that term to include Mr. Hunt.
. The insufficiency of the resources Microsoft originally devoted to technical documentation project is clear from Microsoft’s latest Supplemental Status Report, which states that "[approximately 630 Microsoft employees and contingent staff are involved in work on the MCPP technical documentation,” along with Microsoft's protocol documentation efforts for the European Commission, and that "approximately 320 product team engineers and program managers are actively involved in the creation and review of the technical content of the [MCPP] documentation.” 1/15/08 MS Suppl. Report at 6.
. Of course, if the parties had not been able to negotiate the RESET plan when the Section III.E issues reached a crisis point, Plaintiffs would have been entitled — pursuant to Section V.B of the Final Judgments — to commence an enforcement proceeding and, in the event that “the Court found that Microsoft ha[d] engaged in a pattern of willful and systematic violations,” to "apply to the Court for a one-time extension of th[e] Final Judgments] of up to two years,” i.e., until November 12, 2009. See Final Judgments, § V.B.
. Again, the Court notes that while Microsoft now reports that "[alpproximately 630 Microsoft employees and contingent staff are involved in work on the MCPP technical documentation,” with "approximately 320 product team engineers and program managers [ ] actively involved in the creation and review of the technical content of the documentation,” 1/15/08 MS Suppl. Report at 6, it originally devoted only ten employees to the project of creating the necessary technical documentation. See 7/3/03 JSR at 22. Even as of Microsoft’s March 15, 2006 Supplemental Status Report — filed more than three years after the technical documentation was originally anticipated to be released — a total of approximately 83 Microsoft employees worked either full- or part-time on the documentation effort. 3/15/06 MS Suppl. Report at 9-10.
. Each Final Judgment states that it will expire five years after being entered by the Court "[ujnless this Court grants an extension,” Final Judgments, § V.A., and provides that the Court retains jurisdiction to "act sua sponte to issue further orders or directions, including but not limited to orders or directions relating to the construction or carrying out of this Final Judgment, the enforcement of compliance therewith, the modification thereof, and the punishment of any violation thereof,” as well as "for the purpose of enabling either of the parties ... to apply to this Court at any time for further orders and directions as may be necessary or appropriate to carry out or construe [the] Final Judgment, to modify or terminate any of its provisions, to enforce compliance, and to punish violations of its provisions,” id., § VII.
. In addition, as the United States points out, the Moving States "make no showing ... that any conduct by Microsoft (either in violation of the decree or otherwise) has foreclosed the OEM channel to third-party browsers.” US Amicus Br. at 4.
. The Moving States' argument that Microsoft may threaten emerging technologies through its alleged dominance of the web browser market also appears quite similar to an argument raised during the remedy proceeding that certain protections should be included in the remedy to "ensure that Microsoft does not use its control over the browser market to control other technology markets.”
Remedy Opinion,
. To the extent that the Moving States suggest that the key to protecting emerging web-based middleware threats is to ensure that Microsoft “maintains IE as a standards-compliant browser,”
see CA
Mem. at 20-21, that argument is foreclosed by this Court’s
Remedy Opinion.
As Microsoft correctly notes, the Court considered and rejected a "requirement that Microsoft maintain support for industry standards where it has made proprietary
. To this end, the Moving States assert that "there are continuing questions not just about the accuracy of the [technical documentation], but whether the [technical documentation] is complete,” citing the results of the first audit triggered by Microsoft’s conclusion in early 2007 that additional protocols should be added to the MCPP. CA Mem. at 10-11. As Microsoft notes, however, "Microsoft and the TC recently adopted a set of modest recommendations following the TC’s analysis of the [consulting firm's report] that were substantially different from the [firm’s] recommendations.” MS Opp’n at 14 n. 7. Microsoft further asserts that, to the best of its knowledge, "the agreement between Microsoft and the TC resolved the few issues raised by the [consulting firm’s] report that the TC deemed necessary to address.” Id. It therefore appears that any outstanding issues relating to the completeness of the technical documentation are being addressed in an appropriate manner.
. Indeed, in the unlikely event that the proceedings to this point have not provided Microsoft with sufficient incentive to speedily produce certifiably complete, accurate, and useable technical documentation, this extension of the Expiring Provisions of the Final Judgment should certainly spur Microsoft to do so.
. In addition, as noted above, Microsoft has agreed that "even if the Final Judgments expire completely in November 2009, it will continue, through November 11, 2012, to make the protocols included in the MCPP available for license on reasonable and nondiscriminatory terms with a term of at least five years.” 5/12/06 JSR at 10. As a result of this commitment, "industry members will effectively have the ability to license protocols through at least November 11, 2017.” Id.
. The Court is aware that in
Hughes v. United States,