On November 17, 1976 petitioner, New York Telephone
I, PROCEDURE
Initially, petitioner contends that it was denied due process by the manner in which the Commission conducted the hearings and made its decision. Petitioner alleges, and the Commission admits, that the Commission directed its staff to
Telephone companies in this State are required to provide adequate service for a just and reasonable charge (Public Service Law, § 91). The Commission has been charged with the duty of enforcing this requirement in general (Public Service Law, § 94) and with the particular task of ensuring that any proposed rate increase be just and reasonable (Public Service Law, § 97, subd 1; Matter of General Tel. Co. of Upstate N. Y. v Lundy, 17 NY2d 373, 379). We perceive no inherent conflict between this duty and the Commission’s directive that its staff represent the interests of the consumer by taking an adversary position at the hearings. Presumably, the consumers’ interests would be best served by just and reasonable rates which are sufficient to ensure adequate service (see Matter of New York Tel. Co. v Public Serv. Comm. of State of N. Y., 59 AD2d 17, 19, mot for lv to app den 42 NY2d 810). While, as here, staff’s opinion as to the magnitude of the rate increase necessary to achieve such a result may differ significantly from that of the petitioner, this fact, in and of itself, does not deprive the petitioner of due process.
As to the Commission’s communications with members of its staff during deliberations, it must be noted that "[t]he process of rate-making is a legislative function, not a judicial one” (Matter of New York City Housing Auth. v Public Serv. Comm. of State of N. Y., 23 AD2d 277, 278, mod 17 NY2d 246; Staten Is. Edison Corp. v Maltbie, 270 App Div 55, 58-59, affd 296 NY 374). It is also noteworthy that the provision of the State Administrative Procedure Act which prohibits agency members assigned to make decisions in adjudicatory proceedings from communicating with agency staff engaged in investigating or prosecuting the case specifically excluded proceedings involving public utility rates (State Administrative Procedure Act, § 307, subd 2). "Without a showing to the contrary, state administrators 'are assumed to be men of conscience and intellectual discipline, capable of judging a particular controversy fairly on the basis of its own circumstances’ ” (Withrow v Larkin, 421 US 35, 55). Accordingly, petitioner’s unsupported conjecture must be rejected.
Petitioner challenges the Commission’s determination as to the rate of return on common equity required by petitioner, which rate is an element of the over-all allowed rate of return, contending that the Commission arbitrarily failed to consider all but one of the available approaches to determining the rate of return on equity and that the one approach which the Commission did consider reached an adopted rate of return on equity unsupported by the record. We reject both contentions.
The Commission "is not bound to entertain or ignore any particular factor in discharging its primary responsibility to determine rates that are just and reasonable” (Matter of Tele/Resources v Public Serv. Comm. of State of N. Y., 58 AD2d 406, 410). Nor must the Commission’s determination be "wholly free from error in the process, or quite in accord with a judicial view of how the procedure before the commission should be managed in detail” (Matter of City of New York v Public Serv. Comm. of State of N. Y., 17 AD2d 581, 584, mot for lv to app den 13 NY2d 594). "The scope of judicial review in these matters is, of course, very limited * * *. The question before us is whether there is a rational basis for the commission’s finding that the rates in question are just and reasonable” (Matter of Consolidated Edison Co. of N. Y. v New York State Public Serv. Comm., 53 AD2d 131, 133, mot for lv to app den 40 NY2d 803).
Here, interested parties, including petitioner, Commission staff, the Consumer Protection Board and the General Services Administration, presented expert witnesses who gave their opinions as to the rate of return on equity required by petitioner. The various experts employed a total of five different approaches to arrive at their figures, and it is apparent from the Commission’s determination that it relied on the so-called discounted cash flow method to determine the allowed rate of return on common equity. We perceive nothing inherently arbitrary and capricious in such reliance as long as the experts were not precluded from presenting other accepted methods of determining rate of return on equity so that the Commission had the opportunity to consider all methods. Implicit in its reliance on the discounted cash flow method is the conclusion that in this particular case that method is the more reliable and since five of the expert witnesses used that method, either exclusively or in addition to other methods, there is support for this conclusion. Federal Power Comm. v
The question presented, therefore, is whether the Commission’s determination that the required rate of return on common equity is 11.5% has a rational basis (see Matter of New York State Council of Retail Merchants v Public Serv. Comm. of State of N. Y., 62 AD2d 314, 318; Matter of Niagara Mohawk Power Corp. v Public Serv. Comm. of State of N. Y., 59 AD2d 73, 74). If not, petitioner’s right to a fair return as a part of a regulated industry (Matter of Teleprompter of Mohawk Val. v Pumilio, 57 AD2d 69, 73) has been denied, which, in turn, results in rates that are not just and reasonable.
The opinions of the experts who used the discounted cash flow method, upon which the Commission relied, ranged from 11.3% to 12.5%. The expert presented by the Consumer Protection Board arrived at a figure of 11.5% and the expert presented by the General Services Administration used 11.5% as the lower end of his range. Petitioner contends that the Commission relied too heavily on the testimony of the staff witness who arrived at a figure of 11.3%, and challenges the manner in which the Commission determined each of the three components of the discounted cash flow method used by the Commission. We note that several of petitioner’s challenges cannot be rejected as wholly lacking in merit. In particular, the manner in which the Commission reduced the growth rate component from 5.0%, which it initially arrived at, to 4.3% on the theory that petitioner will have to respond to investor preference for dividends over growth appears to be based largely upon surmise. However, since the result reached
III. PROJECTED DATA V. ACTUAL DATA
Since 1972 the Commission, recognizing relentless upward cost spirals caused by ever mounting inflationary pressures, has encouraged the use of a "six and six” test period in all utility rate applications. The petitioner submits actual data for the first six months of the test period and six months of forecast data. During the course of the hearings, actual data can be substituted for the estimates previously submitted.
Here, the petitioner presented operating income and rate base data for the 12-month period ending March 31, 1977. This data was composed of six months’ actual experience and six months of projections. The hearings began on February 28, 1977. On May 20, 1977 the petitioner completed filing with the Commission staff the actual results to be used in lieu of projected information for the last six months of the test period. The Commission rested its presentation on June 16, 1977. The petitioner presented an exhibit marshalling all the actual data for the 12-month test period as part of its rebuttal which began on June 22, 1977. During rebuttal the petitioner offered testimony as to the effect of the actual data upon the forecast data of the last six months and concluded that the realities of the subject test year showed a marked increase in costs over those generated by the projections, resulting in a large reduction in revenues to the petitioner. The Administrative Law Judge refused to accept the actual data. It was his view that the projected information, having been fully tested in the concluded hearings, was preferable. The Judge observed, however, that the unadjusted actual data produced an 11.7 million dollar revenue requirement over that produced by the projected data. The hearings were concluded on August 9,
As noted above, testimony and exhibits in support of the actual data were offered into evidence beginning seven weeks before the close of the hearings and made available to the Commission staff some II-V2 weeks before the hearings were concluded. Given this rather broad time frame within which to analyze the actual data, the Commission’s refusal based on untimeliness is meritless, particularly when measured against the Commission’s receipt of comparable evidence under similar time restraints in the petitioner’s two prior rate proceedings (New York Tel. Co., 13 NY PSC [1973]; New York Tel. Co., 12 NY PSC [1972], affd sub nom. Matter of City of New York v Public Serv. Comm., 42 AD2d 259, app dsmd 33 NY2d 825). Moreover, the record reveals that the Commission in fact used the actual data in a selective manner when it reduced the petitioner’s revenue requirements because the actual data revealed the petitioner’s medical expense plans were less than had been estimated.
The Commission’s second reason for rejection is also merit-less. The unexplained variations between the projected and actual data (and we concede such variations may exist in two instances)
Similarly, the Commission’s contention that extensive use of forecast data is required because it was not only attempting to fix a just rate for the test period ending March 31, 1977, but also for an extended period beyond that date, must also be rejected. Review of the petitioner’s last two rate proceedings clearly shows that post-test period adjustments were made, and, as the Commission itself noted in New York Tel. Co. (15 NY PSC 1719) "Any lesser period would practically assure the almost immediate obsolescence of the rates we set here” (id., p 1723).
IV. LICENSE CONTRACT PRODUCTIVITY ADJUSTMENT
Pursuant to a license contract with the parent corporation (AT & T), the petitioner receives research data, advice and assistance in all phases of its business operations, including customer services, engineering and network services, employment, legal services and regulatory, accounting, financial and tax matters. In return for such assistance and advice the license contract provides that the petitioner pay AT & T a percentage of gross earnings.
However, the petitioner takes the position that the Commission’s rejection of its increased contract costs to AT & T, based upon inflation, constitutes an impermissible double disallowance since the Commission had already made a productivity adjustment of $42.42 million reflecting projected improvements by the operating departments of the petitioner during the first year of the new rates. Accordingly, argues the petitioner, since reason and logic dictate that the inflationary disallowance ($6.89 million) cannot be related solely to nonoperating departments of the petitioner (staff, legal, business, etc.) it necessarily follows that a large portion of the inflationary disallowance is directly related to operations, an area already discounted by the $42.42 million disallowance. The Commission does not directly address this issue in its briefs but, rather, meets it tangentially by focusing on the view that the Commission was not dealing with a test year based solely on hard, objective fiscal facts, such as contracted-for wage increases, tax increases established by government authority and costs of materials. Necessarily, the Commission had to deal with less concrete items, such as attrition and erosion as well as inflation in determining what add-ons to test year results would be fair. In this connection the Commission correctly points to the sums of $65,149,000 and $62,469,000 allowed the petitioner as add-ons to costs for attrition and erosion, factors as speculative as those of inflation. It is the Commission’s point that if the petitioner passively accepts the sum of $127 million as an add-on, it should not be heard to complain when the Commission disallows $6.8 million as an increased inflationary cost between the years 1975-76 based upon the Commission’s conclusion that such increased costs are approximately equal to the increased productivity of the petitioner as a whole as a result of the services received from AT&T. We agree.
V. WESTERN ELECTRIC CONTRACT DISALLOWANCE
Western Electric Company, Inc., a wholly owned subsidiary of A T & T, manufactures, furnishes and installs the bulk of the telecommunications equipment used by the petitioner. The Commission, of course, has. the right to determine the reasonableness of prices charged by affiliated suppliers of a telephone company and to adjust the company’s rate base
Given the Commission’s undoubted power to consider the reasonableness of the prices charged petitioner by its affiliated supplier (Matter of General Tel. Co. of Upstate N. Y. v Lundy, supra, p 381), we conclude that the selection of a method for determining the reasonableness of those prices requires expertise that is precisely within the realm of the Commission, but as with all such matters, its selection must have a sound basis in reason (Matter of Niagara Mohawk Power Corp. v Public Serv. Comm. of State of N. Y., 59 AD2d 73, 75, supra). The Commission did not base its decision to reject the 1975 and 1976 Western Electric rate of return figures on a finding that those figures were anomalies and, therefore, not reflective of Western Electric’s true rate of return. Rather, it appears that the Commission adopted its staff’s theory that inclusion of the 1975 and 1976 figures would be tantamount to guaranteeing a rate of return to Western Electric. We find this reasoning specious at best. The determination of Western Electric’s rate of return is used only to determine whether the prices paid by petitioner to Western Electric are reasonable and to adjust petitioner’s rate base by the amount which represents excessive charges. The determination will, in no way, guarantee that Western Electric will make a profit, nor will it have more than an indirect impact upon petitioner’s actual payments to Western Electric. The fact that the determination may have
Moreover, prior determinations by the Commission, inconsistent with its present posture, tend to support a conclusion that its determination is irrational. Thus, under similar circumstances the Commission determined that singling out the years in which profits were excessive overstates the net excess profits of the manufacturing affiliate, and concluded that a reasonable measure of the excess profits of the manufacturing affiliate should allow below-normal profits during the later years of the relevant period to offset the excess profits earned in the earlier years (Chenango & Unadilla Tel. Corp., 16 NY PSC 810, 816. See, also, Red Hook Telephone Co., 16 NY PSC 226, 227-228). The Commission’s attempt to distinguish these cases upon the ground that the affiliates involved were much smaller than petitioner and Western Electric is not persuasive, particularly in light of the fact that the Commission has used all available post-1969 data for Western Electric in previous rate cases involving petitioner (see New York Tel. Co., 13 NY PSC 1869, 1878-1883; New York Tel. Co., 15 NY PSC 1719, 1746). Accordingly, we conclude that the Commission’s refusal to include the 1975 and 1976 Western Electric data in its excess profits calculation without providing a sound basis in reason for so doing was arbitrary and capricious.
VI. DISALLOWANCE OF SUMMER [1976] OVERTIME EXPENSES
The Commission disallowed $6,644,000 of revenue requirements of the petitioner on the ground that this sum represented overtime expenses incurred during the months of July and August, 1976 in connection with the Bicentennial Celebration and the Democratic National Convention held in New York City.
Unquestionably, the Commission has the right to eliminate abnormal, nonrecurring expenses from the revenue expectations of a utility to avoid a distorted result (see 3 PUR Digest 2d, Expenses, § 11, Abnormal and unusual expenses). Here, the petitioner’s records contained a notation that it experienced unusually high overtime costs in the month of July because of vacations, the 4th of July celebration throughout the State and the National Democratic Convention. A similar notation for the month of August indicated high overtime costs due to hurricanes and vacations. Both the
While the petitioner’s contention that abnormal or nonrecurring expenses should only be disallowed when the over-all amount of such expenses reaches an abnormal or nonrecurring level (Matter of City of New York v Public Serv. Comm., 42 AD2d 259, app dsmd 33 NY2d 825) is correct, that maxim is inappropriate where, as here, there is a complete failure of proof that the utility experienced like expenses in any prior year. Such a showing could have probatively established that the costs herein disallowed were not so abnormal as to warrant disqualification as nonrecurring expenses. This failure of proof cannot be corrected by remitting to the Commission for receipt of evidence submitted after the hearings were closed. The rejected data must be considered self-serving in the absence of any opportunity to test such information by cross-examination. We conclude that the Commission was justified in refusing to consider such evidence. Consequently, in the absence of proof to the contrary, it was reasonable for the Commission to conclude that the unusually high overtime expenses incurred as a result of the Bicentennial Celebration and the Democratic National Convention were abnormal and nonrecurring. Both events were clearly unique, and inordinate costs associated with them are unlikely to occur in the future.
However, we conclude otherwise with respect to the overtime costs incurred during the months of July and August, 1976 not associated with the Bicentennial Celebration and the Democratic National Convention. Summer vacations and summer hurricanes are typically normal in the northeast and expenses incurred in connection with recurring events and phenomena are not so abnormal as to distort the typical operational costs of the petitioner incurred during the summer months. Therefore, on remand we direct that no overtime disallowance be made for the month of August, 1976 and that the disallowance for the month of July, 1976 be limited to overtime expenses that are reasonably related to the Bicentennial Celebration and the Democratic National Convention.
VII. LEGAL EXPENSE DISALLOWANCE
Petitioner contends that the Commission erred in disallowing one half of the expenses incurred by petitioner as the
VIII. TEN-MONTH SUSPENSION PERIOD
Subdivision 2 of section 92 of the Public Service Law provides that no rate increase shall become effective until 30 days after the filing of new tariffs, and the Commission is authorized to suspend the new rates for a period of up to 10 months pending a hearing and final determination as to whether the proposed rates are just and reasonable. In addition, the Commission is authorized to establish temporary rates during the suspension period. In an earlier related appeal, this court concluded that the maximum 10-month suspension period in this case began December 18, 1976 (Matter of New York Tel. Co. v Public Serv. Comm. of State of N. Y., 59 AD2d 17, 20, mot for lv to app den 42 NY 2d 810, supra), and, thus, it would expire October 17, 1977. On October 13, 1977 the Commission authorized petitioner to put into effect, as temporary rates subject to refund, the annual rate increase recommended by the Administrative Law Judge, but directed that the rates not be effective until five days after service of the tariffs on all parties and after approval by the Commission. As a result, the temporary rates did not go into effect until October 27, 1977.
Petitioner contends that the Commission unlawfully extended the suspension period by 10 days. The Commission contends that, pursuant to subdivision 2 of section 92 of the Public Service Law, the temporary rates could not go into effect until 30 days after the tariffs were filed unless the 30-
As we read subdivision 2 of section 92, the 30-day period applies to tariffs seeking to impose new rates proposed by the utility rather than to temporary rates authorized by the Commission during the period that the new rates are suspended pending a hearing and final determination. The statute specifically authorizes the Commission to establish temporary rates, and it would be irrational to construe the statute as requiring that the utility must then give the Commission 30 days’ notice of the rates it has already authorized.
In providing that the Commission may establish temporary rates during proceedings such as this, subdivision 2 of section 92 specifically refers to the authority contained in section 97 of the Public Service Law, which provides that "[i]f it shall be made to appear to the satisfaction of the commission that the public interest requires a change in the rate, charge or rental for telephone * * * service * * * or that such change is necessary for the purpose of providing adequate or sufficient service or for the preservation of the property, the commission may, upon such terms, conditions or safeguards as it deems proper, authorize an immediate, reasonable, temporary increase * * * pending a final determination” (Public Service Law, § 97, subd 1; emphasis added). Accordingly, we conclude that while the 30-day notice requirement of subdivision 2 of section 92 was not applicable to the temporary rates authorized by the Commission, the Commission may, pursuant to subdivision 1 of section 97, impose such terms, conditions or safeguards as it deems proper.
We find, however, that under the circumstances of this case, the conditions imposed were unreasonable. As we view the statutory scheme, petitioner was entitled to have its proposed rates go into effect at the end of the maximum 10-month suspension period unless a final determination had been made or unless temporary rates had been imposed pending a final determination (cf. Matter of Chenango & Unadilla Tel. Corp. v Public Serv. Comm. of State of N. Y., 45 AD2d 409, 412-413, supra). The condition imposed by the Commission upon the temporary rates which it authorized deprived petitioner of this right. The Commission contends that the conditions were necessary in order to give it the opportunity to ascertain whether the tariffs submitted by petitioner cor
The determination should be modified by annulling so much thereof as (1) rejected the actual data submitted for the last six months of the test year; (2) refused to consider Western Electric’s rates of return for 1975 and 1976 in the excess profits calculation employed to determine the amount of petitioner’s payments to Western Electric to be excluded from the rate base; (3) excluded from the operating expenses overtime expenses for July and August, 1976 other than those attributable to the 1976 Bicentennial Celebrations and the Democratic National Convention; and (4) refused to offset the refunds which petitioner is required to pay by the amount which petitioner would have received had the temporary rates gone into effect on October 17, 1977 at the end of the 10-month suspension period, and matter remitted to the Commission for redetermination of the above issues in accordance with this opinion, and, as so modified, confirmed, without costs.
Greenblott, Larkin, Mikoll and Herlihy, JJ., concur.
Determination modified by annulling so much thereof as (1) rejected the actual data submitted for the last six months of the test year; (2) refused to consider Western Electric’s rates of return for 1975 and 1976 in the excess profits calculation employed to determine the amount of petitioner’s payments to Western Electric to be excluded from the rate base; (3) excluded from the operating expenses overtime expenses for July and August, 1976 other than those attributable to the 1976 Bicentennial Celebrations and the Democratic National Convention; and (4) refused to offset the refunds which pe
. As part of the $11.7 million difference between projected and actual data, $2.7 million was chargeable to a 1970 company income tax deficiency and the actual data gave an unjustified smaller amount ($0.7 million) as a credit to N. Y. Tel. from a $6.3 million Federal income tax reduction.
. Since 1974 the petitioner has paid to AT & T an amount equal to its allocated share of the total cost to A T & T in providing the services on a national scale, but said payments could not exceed 2Vi% of gross.