146 N.Y.S. 769 | N.Y. App. Div. | 1914
The plaintiff’s assignor constructed an addition to the defendant’s mill and there is unpaid on the contract price $11,618.96, for which, and for certain alleged extra work, the plaintiff seeks recovery. By the contract, dated May 3, 1905, the work was to be completed September 1, 1905, within three months and twenty-eight days. It was in fact completed July 1, 1906 — thirteen months and twenty-eight days after the date of the contract and ten months after the agreed time. The contract provided $50 per day as liquidated damages to the defendant for each day’s delay in the completion of the work, and that the delays should be apportioned. The defendant, by its coun
This case was before us in 140 Appellate Division, 740, and it is unnecessary to repeat the facts there stated. When the contract was made it was understood that the wheelpit, which lay at the very foundation of the work, was to he lowered one foot or more below the depth specified in the contract, for which the contractor was to receive two dollars and fifty cents per cubic foot, and that the contractor was to be notified of the depth required as soon as a determination was made. We held that until the contractor was so notified the original contract practically remained in suspense and that the time intervening was not a part of the contract time. This was not upon the theory that the owner or the architect had delayed the work, but that the parties had in substance agreed that the work need not be entered upon until the nature of this foundation work was agreed upon. We also held that if this extra work necessarily required extra time for its completion, with reference to the work itself or the extra cofferdam made necessary for it, such extra time was to be added to the contract time. This did not mean that the time which the contractor might spend upon the work, or in experimenting upon the cofferdam, was to be added to the contract time, but that the situation as it actually existed was to. he considered, and if engineers competent for such work, who had full knowledge of the condition of the bed of the lake and the other conditions, with adequate machinery and appliances, proper supervision and working to capacity would be engaged a certain time in the necessary
The important questions for consideration are when the contractor was notified that the wheelpit was to be lowered three and one-half feet, and how much time was added to the contract on that account. It was assumed upon the former appeal that such notice was given July seventh when the blue prints for the work were finished. Upon a careful consideration of the present record it is clear that the contractor had due notice on June eighth and should then have entered upon the work. According to the plaintiff’s theory the contractor had substantially built the cofferdam in which the wheelpit mentioned in the original contract was to be placed; that such work was done in reliance upon the original contract and without expectation that the wheelpit was to be deepened and that the change of plan made necessary a new cofferdam. It is evident that the contractor cannot have an extension of the contract upon the theory that it remained in suspense'awaiting the determination as to the deepened wheelpit and at the same time be credited with the construction of the first cofferdam which he claims was built upon the theory that there was to be no deepening of the wheelpit. The facts do not justify the claim that the first cofferdam was constructed upon the theory that there was to be no change in the wheelpit. Upon May twenty-fourth, twenty-one days after the date of the contract, the architect wrote
We have seen that the contractor was to take all the chances as to the conditions- at the place where the work was to be performed. In fact he made no adequate examination of the place where the cofferdam was to be, either at the time the contract was made or at the time when the first cofferdam was constructed. Neither the contractor nor the defendant or architect in fact had any real knowledge of the actual conditions existing under the water at the place where the cofferdam was to be built. And if they had known none of them had sufficient experience to enable him to appreciate the difficulties. The contractor began the cofferdam with the knowledge that the wheelpit was to be lowered, but he assumed, as did the architect, that the lowering of the wheelpit would not make any difference in the size of the cofferdam or its exact location. This evidently would have been a correct supposition if the lake bottom had been a rock surface, such as they evidently supposed it to be. As matter of fact it was a rock surface, with a gradual slope into the lake, and in a short distance the rock disappeared and broken stone only was found, which furnished no satisfactory anchorage for a cofferdam, with the result that the water came through the bottom and the cofferdam could not be made dry. The contractor, up to July seventh, in a way, was trying to perfect the first cofferdam and prevent its leaking. Up to that time the building of the cofferdam had been in inexperienced hands, and the principal trouble came from the fact that the condition of the bottom of the lake at
It is evident that the first cofferdam was built with the understanding that there was to be a greater depth to the wheel-pit than contemplated in the original contract, for after the actual depth was known the work upon it continued to July tenth. Here is a month and two days lost time clearly chargeable to the contractor. At the trial those in the employ of the contractor seemed to understand that the first cofferdam was entirely useless in making the deeper wheelpit, and unfitted and unsuited for the deeper wheelpit. This knowledge had been gained long after it was arranged to lower the pit. Undoubtedly much work was caused by the lowering of the wheelpit, and great difficulties were found in building the cofferdam. It is nevertheless clear that if the contractor had obtained full
Before the cofferdam was finished much of the brickwork had been done. It is found that the remaining brickwork and the laying of the beams could have been done in a month of favorable weather. If the wheelpit had been finished October fifth there was ample time for doing this work before the winter closed in. There is, therefore, no extension on account of the winter weather. The contractor is responsible for the delays from January 5 to July 1, 1906, 151 days exclusive of Sundays, and the defendant is entitled to receive fifty dollars per day, the liquidated damages therefor.
In the letter of July 6, 1905, in furnishing the revised plans for the wheelpit, the architect stated that there would be a saving of .$480.90 in the structural steel and cast iron, and in other items, making a total of $151.10, a rebate which will be due the owner. And it is urged by the defendant that the trial court erred in not allowing that sum. On August fifth the defendant’s superintendent acknowledged the receipt of the letter and stated they had not received the statements from the iron men and could not check the matter up but that it would have attention. The amount was certified by the architect in- Ins’ final certificate. The court has found that the architect’s certificate was unfair and not binding upon the contractor. All the parties interested were apprehensive that the delay in determining the depth of the wheelpit might cause a delay in getting the iron therefor, and thus delay the job.
At an early date it was discovered that according to the specifications the roof of the addition did not meet the roof of the main building, and it was necessary to make a slight elevation in the new roof to conform to the old at the place where they joined, for which the court has allowed the plaintiff $200 as extra work. The drawings indicated that the roofs joined. The construction of the plans under the contract was left with the architect. It was provided in the specifications that “ should there appear any discrepancy between them and the plans the architect shall explain them and such explanation shall be final and binding upon the contractor, who will make no charge or claim for extra work in consequence of such explanation, and he shall execute the work in accordance therewith.” It was also provided that no extras shall he allowed without a written order from the architect, and that if any other work than shown is required the architect must fix the price of it and the contractor shall abide by it. These conditions were binding and were not waived. This work was not directed as extra work. The architect claimed it was required by the original contract, and his decision as to the meaning of the
The judgment should, therefore, be modified as stated in this opinion, and as modified affirmed, with costs to the appellant.
Judgment modified as per opinion, and as modified unanimously affirmed, with costs.
The court reverses the finding that the defendant is only entitled to $2,350 as liquidated damages, and that there was due, and the architect should have certified to, $11,678.96 to the plaintiff; that the plaintiff performed extra work with reference to the roof of the value of $200; that the plaintiff is entitled to recover $10,899.61, with interest; the ninth finding of fact; the tenth finding of fact; the eleventh finding of fact; the thirteenth finding of fact except the first two sentences thereof. And, in lieu thereof, the court finds that the plaintiff had notice as to the depth of the wheelpit June eighth, and should have then commenced work thereon; that by delay in giving notice as to the change in the wheelpit the contract time was extended one month and five days; that building of' the cofferdam was in the hands of inexperienced, incompetent men, with an inadequate force, who did not know the situation at the place where the cofferdam was to be built, and that a great part of the delay in building the cofferdam and the wheelpit arose from those facts; that, by the contract, the plaintiff was chargeable with knowledge of the situation at the place where the cofferdam was to be built, and competent men, with proper appliances and a sufficient force, should have constructed it in three months’ time, or by September eighth; the deepening of the wheelpit extended the time for the completion of the contract until January 5, 1906, and for all delays after that the plaintiff is responsible, and should be charged with fifty dollars per day liquidated damage for each working day; the change in the wheelpit made a saving to the plaintiff in material, other than steel and iron, of $270.20 which should be allowed to the defendant. The computations may be made pursuant to these findings and the opinion, and incorporated in the order.