MEMORANDUM-DECISION AND ORDER
I. Introduction
In 1978, Congress passed the Public Utilities Regulatory Policies Act (“PURPA”), 16 U.S.C. § 824a-3, as part of a package of legislation 1 entitled the “National Energy Act.” PURPA was designed to promote long-term economic growth by reducing the nation’s reliance on oil and gas, encourage the development of alternative energy sources and thereby combat a nationwide energy crisis. Section 210(a) of PURPA required the Federal Power Commission (“FPC”), now known as the Federal Energy Regulatory Commission (“FERC”), to “prescribe, and from time to time thereafter revise” rules requiring electric utilities to offer both to sell and purchase electric energy from qualifying cogeneration facilities (“QFs”). 2 16 U.S.C. § 824a-3(a). Section 210(b) of PURPA required that the rates utilities paid for power purchased from QFs be “just and reasonable to the electric consumers” and “not discriminate” against QFs. 16 U.S.C. § 824a-3(b). Finally, in Section 210(e), PURPA exempted QFs from federal and state regulatory control in connection with rates and financial organization. See 16 U.S.C. § 824a-3(e). 3
Congress also directed that each state regulatory authority implement the rules prescribed by FERC concerning electric utilities’ obligation to purchase power from QFs. See 16 U.S.C. § 824a-3(f). 4 Pursuant to PURPA, the New York State legislature enacted New York Public Service Law § 66-c, which provided that the defendant New York Public Service Commission (“PSC”) shall require state regulated electrical utilities to enter into long-term contracts for the purchase of electricity from alternative energy sources, including co-generation facilities. See N.Y.Pub.SeRV. Law § 66-c. Furthermore, Section 66-c granted PSC authority to oversee the contracting process and set the purchase rate for long-term power contracts. See id.
PURPA also contains an elaborate enforcement scheme and provisions for judicial review.
See
16 U.S.C. § 824a-3(g)-
Section 210(b) of PURPA declares that “[n]o such rule [promulgated by FERC] ... shall provide for a rate which exceeds the incremental cost to the electric utility of alternative electric energy.” 16 U.S.C. § 824a-3(b). The “incremental cost” to the electric utility of alternative electric energy is defined as “the cost to the electric utility of the electric energy which, but for the purchase from such cogenerator or small power producer, such utility would generate or purchase from another source.” 16 U.S.C. § 824a-3(d). The incremental cost described by Congress in PURPA is defined in the accompanying regulations as “avoided costs,” or those costs which the utility “avoided” incurring itself by purchasing power from a QF. See 18 C.F.R. § 292.101(b)(6).
Plaintiff, New York State Energy
&
Gas Corporation (“NYSEG”), a traditional electrical utility, brings the present action principally to obtain relief from long-term contracts with two QFs, defendants Sara-nac Power Partners, L.P. (“Saranac”)
5
, and Lockport Energy Associates, L.P. (“Lockport”).
6
In each case, NYSEG’s contract requires it to pay for energy purchased from these two companies at a fixed rate equal to its estimated long-run avoided costs (“LRACs”) as calculated — or miscalculated — in 1988 by NYSEG and other public utilities in conjunction with PSC. Unfortunately for NYSEG, its LRACs as estimated at the time it entered into required contracts with Saranac and Lockport are considerably higher than its current LRAC projections. According to two independent analysts retained by NY-SEG, payments under both the Saranac and Lockport agreements will significantly exceed NYSEG’s avoided costs over the terms of the agreements.
7
Based on these
II. Procedural and Regulatory History
A. FERC’s Rulemaking
PURPA required FERC to prescribe regulations to implement the statute “[n]ot later than 1 year after November 9, 1978.” 16 U.S.C. § 824a-3(a). Following public rulemaking proceedings, FERC promulgated regulations governing transactions between utilities and QFs in connection with purchase and sales of electricity.
See Small Power Prod, and Cogeneration Facilities; Regs. Implementing Section 210 of [PURPA],
Order No. 69, 45 Fed.Reg. 12214 (Feb. 25, 1980). In
American Elec. Power Serv. Corp. v. FERC, 675
F.2d 1226 (D.C.Cir.1982)
(“AEP”),
four utilities challenged the legality of the very regulations at issue in this case. There, the court held that FERC failed to adequately explain or justify its adoption of the full avoided cost standard in light of the enabling statute, PURPA, which mandated that rates charged to consumers be reasonable and that rates paid to QFs not exceed utilities’ incremental costs.
See AEP,
In
American Paper Inst, Inc. v. American Elec. Power Serv. Corp.,
B. PSC Proceedings
The PSC adopted rules to implement PURPA in 1982.
See Consol. Edison Co. of New York, Inc.,
PSC Case No. 27574,
PSC then ordered NYSEG to enter into a fifteen-year contract with Loekport’s predecessor in interest, Empire Energy Niagara Limited Partnership (“Empire”). See Order Granting Petition Subject to Conditions, PSC Case No. 88-E-216 (Nov. 3, 1989). 8 Although NYSEG objected to the proposed contract because its 1988 LRAC estimates appeared to be too high and PSC rejected its request for a tracking mechanism or “true up” provision that would reconcile estimated avoided costs with actual avoided costs, NYSEG did not appeal PSC’s order approving the contract.
On March 5, 1991, PSC approved three contracts between Falcon Seaboard Oil Company (“Falcon”), Saranac’s predecessor in interest, and NYSEG.
See Order Approving Contracts Subject to Conditions,
PSC Case Nos. 90-E-0867, 90-E-0865 and 90-E-0860 (Mar. 5, 1991).
9
Again, NYSEG’s request for a reconciliation mechanism was rejected by PSC.
10
In 1992, PSC reduced NYSEG’s estimated LRACs by approximately forty percent. However, NYSEG did not benefit from this revision with respect to its existing contracts, and calculates that the rates it pays under the contracts with Saranac and Lockport are more than triple its actual avoided costs.
C. FERC Proceedings
On February 14, 1995, NYSEG filed a petition with FERC for a declaratory order and request for modification of rates in the Saranac and Lockport PPAs.
11
In its petition, NYSEG complained that PSC forced NYSEG to enter into the agreements with Lockport and Saranac despite NYSEG’s objections that the PPAs did not adequately protect NYSEG’s ratepayers against the risk of payments in excess of avoided costs. NYSEG sought three forms of relief from FERC. First, NYSEG demanded that FERC issue a declaratory order finding that PURPA, and its accompanying regulations
12
prohibit purchase rates in NYSEG’s congressionally mandated PPAs that are in excess of its avoided costs even if such rates were not so excessive at the time the contracts were signed. NYSEG argued that although it voiced its concern that estimated LRACs would prove to be inflated over the course of the long-term agreements with Saranac and Lockport, the aggregate amount of over-payments to these QFs became evident only after NYSEG’s time to appeal the orders of PSC directing the utility to enter into those agreements had elapsed. NY-SEG also requested that FERC either take appropriate action itself under section 210(b) of PURPA to reform the Saranac and Lockport PPAs or, under section 210(h)
13
, direct PSC to relieve NYSEG of its obligation to make payments in excess of avoided costs under these contracts. Finally, NYSEG asked FERC to waive or revise its rules as necessary to grant the requested relief. In support of its petition, NYSEG relied on FERC’s then recent decision in
Connecticut Light & Power Co.,
70 F.E.R.C. ¶ 61,012,
FERC denied NYSEG’s petition in its entirety finding in the first instance that the regulations it enacted pursuant to PURPA do not prohibit rates for PPAs which are based on avoided cost estimates at the time a contract is signed even if they exceed a utility’s avoided costs at the time of delivery.
See NYSEG,
70
In the case in which rates for purchases are based upon estimates of avoided costs over the specific term of the contract or other legally enforceable obligation, the rates for such purchases do not violate this subpart if the rates for such purchases differ from avoided costs at the time of delivery.
Id. 15 FERC recognized when the above regulation was enacted that avoided costs could change over time and attempted to reconcile the requirement that utilities pay no more than their avoided costs for purchases with the need for QFs to enter contractual commitments based “by necessity, on estimates of future avoided costs.” M 16 Indeed, FERC anticipated that if the avoided cost of power was less when delivered than the price in the PPA, the utility would be subsidizing the QF “at the expense of the utility’s other ratepayers.” Id. However, FERC was also:
cognizant that in other eases, the required rate will turn out to be lower than the avoided costs at the time of purchase. The Commission [FERC] does not believe that the reference in [PURPA] to incremental cost of alternative energy was intended to require a minute-by-minute evaluation of costs which would be checked against rates established in long term contracts between [QFs] and electric utilities.
Many commentators have stressed the need for certainty with regard to return on investment in new technologies. The Commission agrees with these latter arguments, and believes that, in the long run, “overestimations” and “underestimations” will balance out_The import of [18 C.F.R. § 292.304(b)(5) ] is to ensure that a [QF] which has obtained the certainty of an arrangement is not deprived of the benefits of its commitment as a result of changed circumstances. This provision can also work to preserve the bargain entered into by the electric utility.
Id.
Based on this regulatory history, FERC declined to issue the declaratory ruling requested by NYSEG stating it was “far too late” for “NYSEG to argue, for the first time, that these particular regulations have legal and policy flaws requiring that we abrogate contracts entered into under these regulations.”
NYSEG,
70 F.E.R.C., at 61,116. Moreover, FERC refused to “second-guess” PSC’s determination of LRACs, finding that PSC’s implementation of its rules and regulations was proper and consistent with PURPA. Id.
17
FERC noted that when PSC mandated the Sara-nac and Lockport contracts, it “specifically addressed and accounted for” the very risk of harm about which NYSEG complained in its petition.
NYSEG,
70 F.E.R.C., at 61,116. Instead of requiring protective
FERC stated that a “second, independent basis for denying NYSEG’s Petition is the Commission’s policy against invalidating contracts for which a PURPA-based challenge was not raised timely and is still not pending.”
Id.
FERC noted that NY-SEG, “believing it had ‘neither a cognizable injury nor a basis to complain further to [PSC] or [FERC],’ chose not to appeal [PSC’s] orders mandating the agreements.”
Id.
(quoting NYSEG’s petition at pp. 3-5, 17, 47). According to FERC, this was unlike the facts in
CL & P
where the utility had been continuously challenging the subject PPA rate — which might have exceeded avoided costs depending upon application of. an alleged unlawful state statute — since the state regulatory authority mandated the contract.
Id.
(citing
CL & P,
70 F.E.R.C., at 61,029,
In this case, Lockport and Saranac (and their investors) invested in these projects in the reasonable belief that, once the deadline for timely challenges had passed, their contracts with NYSEG were lawful and binding under PURPA.... [T]he contracts at issue allocated risks to both the purchaser and the sellers. Like NYSEG, Lockport and Saranac bore risks that their agreements would become uneconomic over time. QFs bear development risks not experienced to the same extent by traditional utilities. As a result, they must rely on their [PPAs] to obtain project financing, and we have recognized the importance of contractual reliance for this purpose, if we were to grant the relief requested by NYSEG and allow the reopening of QF contracts that had not been challenged at the time of their execution, financeability of such projects would be severely hampered. Such a result is not, in our opinion, consistent with Congress’ directive that we encourage the development of QFs.
NYSEG, 70 F.E.R.C., at 61,118 (citations omitted).
NYSEG petitioned for rehearing,
19
on the bases that FERC erred by: 1) relying on PSC’s estimates of LRACs; 2) failing to relieve NYSEG from PPA rates which
Nevertheless, we are not unsympathetic to the concern of utilities that find themselves with legally binding QF contracts that contain rates that currently are above avoided cost. As we have previously explained, we believe that the remedy appropriate to this situation is to allow utilities to buy-out or buy-down such contracts, not to invalidate them. If utilities are prudent in buying out or buying down existing [PPAs], whether or not with QFs, we have indicated that we will permit the recovery in wholesale rates of a pro rata share of the buy-out or buy-down costs.
NYSEG, 72 F.E.R.C., at 61,341 (citing West Penn Power Co., 71 F.E.R.C. ¶ 61,-153, at 61,497, 1995 WL ’ 265343 (1995)).
D. District of Columbia Circuit Decision
NYSEG then petitioned the United States Court of Appeals, District of Columbia Circuit for review of FERC’s denial of its petition.
21
In
NYSEG v. FERC,
The court rejected NYSEG’s argument that judicial review of FERC’s order would not disturb PURPA’s enforcement scheme because FERC could have granted all of the relief NYSEG requested pursuant to the FPA. While acknowledging that NYSEG had requested relief under the FPA, “[FERC’s] denial of that relief was based upon determinations that would, if
At bottom, each of NYSEG’s requests to [FERC] for relief is effectively a challenge to the rates set by ... PSC. In response to these requests [FERC] did nothing more than state why in its opinion the challenged rates comply with PURPA. Under the enforcement scheme set up by the Congress, NYSEG may now bring an enforcement action under § 210(h)(2)(B) of ... PURPA, in which case the district court will assess the merits giving [FERC’s] opinion such consideration as it may deserve.
Id. at 1477.
E. The Present Complaint and Cross-Claim
On August 7, 1997, NYSEG filed a complaint against FERC, PSC and various officials of the PSC, Saranac, and Lock-port. 23 In the first count of the complaint, NYSEG alleges that by failing to take any action with respect to its petition 1) for a declaratory order (that the contracts with Saranac and Lockport violate PURPA); and 2) for modification of rates imposed in the PURPA power purchase agreements with Saranac and Lockport, FERC violated PURPA and the Administrative Procedure Act (“APA”) 24 . NYSEG demands that FERC initiate whatever waivers or rulemaking is necessary to relieve NYSEG from the allegedly illegal obligations of these contracts.
NYSEG also alleges that in its order denying NYSEG’s petition, FERC declared a new administrative rule which it dubs the “Continuous Challenge Rule.”
25
To wit, NYSEG alleges FERC’s denial of its petition on this basis constitutes improper rulemaking under the APA because FERC gave no prior notice of its intent to require parties to continually challenge regulations in order to preserve a claim for relief in subsequent administrative proceedings and did not conduct formal notice and comment procedures in promulgating this alleged new rule.
See Zhang v. Slattery, 55
F.3d 732, 744-45 (2d Cir.1995) (interim rule promulgated by Attorney
In its second and third claims for relief, NYSEG alleges that PSC’s orders which set LRACs and directed NYSEG to enter into the Saranac and Loekport contracts: 1) violated PURPA and its implementing rules; and 2) violated the Supremacy Clause of the United States Constitution. NYSEG’s fourth claim is an enforcement action against PSC pursuant to Section 210(h)(2)(B) of PURPA for failure to implement PURPA properly.
NYSEG’s fifth, sixth and seventh claims run against the QF’s directly and allege illegality of the PPAs, frustration of purpose and mutual mistake under New York contract law. NYSEG requests relief from performance and restitution.
Alied with NYSEG in part, PSC cross-claimed against FERC alleging that FERC violated PURPA when it failed to reform the Saranac and Loekport PPAs. Relying on the FPA from whence PURPA came, PSC alleges that FERC has authority, after giving notice, soliciting comments and conducting public hearings, to modify utility rates in the public interest. PSC also alleges that PURPA itself requires FERC to revisit its regulations from time to time. PSC claims that federal regulations also grant FERC authority to revisit the issue of QF exemption from utility-type rate regulation and limit the exemptions if necessary. According to PSC, FERC can limit or change the exemptions and then modify the contracts prospectively so that going forward, the PPAs no longer violate PURPA’s prohibition against purchase rates which exceed avoided costs. Finally, PSC alleges that FERC’s failure to take any action with respect to the Saranac and Loekport contracts is a violation of the APA.
F. The Present Motions
A1 defendants move pursuant to Fed. R.Civ.P. 12 to dismiss NYSEG’s claims against them. Saranac, Loekport, and FERC also seek dismissal of PSC’s cross-claim. National Power Lenders Forum (“NPLF”) and the Electric Power Supply Association (“EPSA”) filed amicus briefs in support of the positions taken by Saranac, Loekport, and FERC. 26 Aso pending before the Court — but stayed at the present time — are motions for summary judgment or partial summary judgment filed by Sar-anac, PSC and NYSEG. 27
III. Discussion
A. Motions to Dismiss Count I (N.Y.SEG’s Claims Against FERC)
1. Personal Jurisdiction
FERC argues in the first instance that NYSEG’s claims against it should be dismissed for insufficiency of service of process because NYSEG admittedly failed initially to serve a copy of its summons and complaint on the U.S. Attorney’s Office in this district and mail copies of the documents to the Attorney General of the United States as required by Fed.R.Civ.P. 4(i) (governing service of process on the United States and federal agencies). On October 14, 1997, NYSEG complied with this procedural requirement by serving both
2. Subject Matter Jurisdiction
a. Arguments of the Parties
FERC, along with Saranac and Lock-port, argue that this Court lacks subject matter jurisdiction over NYSEG’s claims against FERC. These defendants argue that PURPA’s enforcement scheme does not authorize a direct action against FERC in district court. Rather, they argue, Section 210(h)(2) of PURPA only authorizes FERC or another aggrieved party to bring an action against a state regulatory authority such as PSC or a non-regulated utility in district court. See 16 U.S.C. § 824a-3(h)(2). 28
In response to this argument, NYSEG asserts that the APA provides for judicial review by a district court of FERC’s decision not to take any action with respect to its petition for relief from and modification of the contracts. FERC, Saranac and Lockport argue that APA review by this Court is not authorized because: 1) APA review of an agency determination is only available if an aggrieved party has no place else to go for relief.
See Bowen v. Massachusetts,
Moreover, NYSEG claims entitlement to APA review of FERC’s action in this case because the available remedy against PSC set forth in PURPA’s enforcement scheme is inadequate to provide the utility with all of the relief it seeks herein. In the first instance, NYSEG argues that the Third Circuit’s decision in
Freehold Cogeneration Assoc, v. Bd. of Regulatory Comm’rs. of the State of New Jersey,
FERC insists that NYSEG’s arguments regarding the inadequacies of PURPA’s regulatory scheme are an attempt to extricate itself from the effects of its own ill-considered prior litigation strategy. FERC argues that NYSEG could have, but did not, challenge FERC’s rules and PSC rules which required utilities to enter long term contracts based on estimated LRACs at the time the rules were promul
As to NYSEG’s argument that it seeks review of FERC’s refusal to modify the QF contracts, FERC argues that it has no statutory authority to do so under either PURPA § 210 or FPA § 206(a) because these Acts contain no such explicit authority and, contrary to NYSEG’s arguments, the power to reform PPAs cannot be inferred from PURPA’s statutory mandate that: 1) rates paid to qualifying facilities (“QF’s”) not exceed the “incremental cost to the electric utility of alternative electric energy;” 33 and 2) FERC shall create “and from time to time revise” 34 its rules as necessary to implement the statute. FERC also denies that implied authority to reform the Saranac and Lockport PPAs may derive from Congress’ intent that PURPA contract rates be “just and reasonable to the electric consumers of the electric utility and in the public interest.” 16 U.S.C. § 824a-3(b)(2).
FERC asserts that the FPA likewise provides no avenue for relief because PURPA regulations expressly exempt QFs such as Saranac and Lockport from the FPA section relied on by NYSEG, which allows FERC to prescribe proper rates if it determines a power purchase rate to be unreasonable. See 16 U.S.C. § 824e(a); 18 C.F.R. § 292.601. Saranac argues additionally that the FPA vests exclusive jurisdiction over review of FERC orders implementing the FPA in the Courts of Appeals. 35 Thus, in Saranac’s estimation, this Court has no subject matter jurisdiction to review FERC orders interpreting the FPA.
In response to NYSEG’s argument that FERC must promulgate new avoided cost rules to relieve them from contracts which have become grossly unprofitable, FERC asserts that this claim is not yet ripe because NYSEG’s underlying administrative petition did not formally petition the agency for new rule-making.
36
According to FERC, even if it treated NYSEG’s underlying petition as one for rulemaking, it could not retroactively alter its rules to invalidate the Saranac and Lockport PPAs.
See Bowen v. Georgetown Univ. Hosp.,
b. Analysis
At its core, each of NYSEG’s claims against FERC revolves around the same premise which is that PURPA, an enabling regulatory statute, provides “no rule prescribed [by FERC] ... shall provide for a rate which exceeds the incremental cost of the electric utility of alternative electric energy,” 16 U.S.C. § 824a-3(b). While NYSEG argues that this provision of PURPA prohibits rates which exceed a utility’s avoided costs, the Court interprets it to prohibit enactment of a rule which mandates a PPA rate in excess of avoided costs. Indeed, NYSEG recognizes as much by arguing that “[djefendants focus entirely on FERC’s rules, while ignoring PURPA’s substantive requirement that dictates such rules cannot provide for rates above a utility’s avoided cost.” See Docket 36, Memorandum of Law of NY-SEG in Opposition to Motions to Dismiss (“NYSEG Brief’), p. 25 (emphasis added). Review of PURPA regulations reveals that FERC has never enacted such a rule.
When FERC promulgated regulations pursuant to PURPA, it recognized that purchases between QF’s and utilities might occur as the QF determined it had excess alternative energy to sell in which case rates for purchases would be based on the utility’s avoided costs at the time of delivery of the power. See 18 C.F.R. § 292.304(d)(1). When the purchase occurred by way of a long-term contract, however, FERC gave the QF the option of basing the purchase rate on avoided costs calculated at the time it actually delivered energy to the utility over the course of the contract or as estimated at the time it signed the contract. See 18 C.F.R. § 292.304(d)(2). In neither case, however, do the rules regarding purchases mandate a rate in excess of avoided costs.
FERC obviously anticipated a circumstance where estimated LRACs would differ in some respect from actual avoided costs at the time power was delivered pursuant to a long-term PPA. To wit, FERC ruled that in the event that a purchase rate “differs from avoided costs” at the time energy is delivered pursuant to a long-term PPA, such rate does not violate PURPA. 18 C.F.R. § 292.304(b)(5). The regulatory history associated with this regulation reveals it was enacted to “address[ ] the situation in which a QF has entered into a contract with an electric utility or where the QF has agreed to obligate itself to deliver at a future date energy and capacity to the electric utility.” Small Pmoer Prod, and Cogeneration Facilities; Regs. Implementing Section 210 of [PURPA], Order No. 69, 45 Fed.Reg. at 12224. “The import of this section is to ensure that a QF which has obtained the certainty of an arrangement is not deprived of the benefits of its commitment as a result of changed circumstances.” Id. No fair reading of the regulation can characterize it as mandating a PPA rate in excess of a utility’s avoided cost. 18 C.F.R. § 292.304(b)(5) merely accounts for and forgives the possibility that market fluctuations might cause a PPA rate to be higher than a utility’s actual avoided costs when power is actually delivered over the course of a long-term contract.
NYSEG’s assertion of an action against FERC pursuant to the APA presupposes that it has no adequate alternative remedy, an issue of intense debate between the parties. Defendants point to PURPA’s elaborate enforcement scheme and NY-SEG’s statutory right to sue PSC as an adequate alternative remedy thus precluding judicial review. NYSEG argues that it cannot get full satisfaction by suing PSC alone. To wit, it contends that it cannot obtain review of FERC’s failure to act on its petition or FERC’s alleged promulgation of a new rule in an enforcement action against PSC.
The Court agrees that the inadequacies of which NYSEG complains in connection with PURPA’s enforcement scheme, insofar as it precludes the relief NYSEG now seeks against FERC, are due, in whole or large part, to: 1) NYSEG’s failure to challenge FERC’s rules, specifically 18 C.F.R. § 292.304(b)(5) and/or the exemption provisions in 18 C.F.R. § 292.602, pursuant to the FPA when these regulations were enacted as did the plaintiffs in API; 2) NY-SEG’s failure to have petitioned FERC for amendment or recission of these regulations and then appealed a denial pursuant to the APA as the plaintiffs did in NLRB v. FLRA; 41 and 3) NYSEG’s failure to challenge PSC’s implementation of FERC’s PURPA regulations in orders which set NYSEG’s LRACs and compelled the utility to enter long-term PPAs with Saranac and Lockport.
NYSEG’s failure to appeal from or challenge PSC’s orders implementing PURPA regulations is particularly telling because although NYSEG claims it did not understand the degree to which FERC’s regulations would affect it negatively at the time they were promulgated, it clearly knew when the Saranac and Lockport agreements were being negotiated that 18 C.F.R. § 292.304(b)(5) and/or the exemption regulations might result in its subsidy of the QFs if avoided cost estimates turned out to be wrong. Thus, NYSEG requested and was denied a protective “tracking mechanism” to reconcile actual avoided costs with the contract prices in both PPAs. In lieu of appealing these PSC orders, NYSEG settled for contract rates set at a discount from its estimated LRACs. However, these discounts have proved in
Nevertheless, assuming without deciding, that the previous availability of direct judicial review of the regulations and orders which now constrain NYSEG does not preclude the
possibility
of APA review, NYSEG must still demonstrate that this Court has jurisdiction to review the order at issue. Saranac and Lockport argue that FERC’s decision to deny NYSE G’s administrative petition was merely a non-enforcement determination and is unreviewable as a matter of law pursuant to
Heckler v. Chaney.
Indeed, the Court stated therein that “an agency generally cannot act against each technical violation of the statute it is charged with enforcing.”
NYSEG concedes in one portion of its memorandum of law that FERC’s denial of its petition, insofar as it requested FERC to direct PSC to take action, may be unre-viewable to the extent that it is considered a decision by FERC not to take enforcement action against PSC. However, NY-SEG also argues in the alternative that PURPA contains “meaningful standards” by which FERC’s failure to act against PSC can be measured inasmuch as the statute prohibits rates in excess of avoided costs. As noted by Saranac, PURPA is not self-implementing, it is a “regulatory statute,”
see API,
Because Congress merely announced the goal of promoting the development of alternative energy sources in PURPA and left the details of how to do so to FERC, it cannot be said that PURPA provides “meaningful standards for defining the limits” of FERC’s enforcement discretion.
Heckler v. Chaney,
NYSEG alleges, however, that its claims against FERC are more broad. To wit, it seeks APA review of FERC’s announcement of the “continuous challenge rule” in the context of denying its administrative petition. NYSEG is correct in asserting that generally, agency “rule[sj” must be subjected to a notice and comment period before taking effect. 5 U.S.C. § 553. An agency such as FERC which promulgates a new rule “without observance of procedure required by law” has violated the APA. 5 U.S.C. § 706(2)(D). However, the notice and comment provisions of Section 553(b)(A), do not apply “to interpretive rules [or to] general statements of policy.”
Zhang,
In distinguishing between the two types of rules, the central question is essentially whether an agency is exercising its rule-making power to clarify an existing statute or regulation, or to create new law, rights, or duties in what amounts to a legislative act. Since legislative rule-making involves [an] agency’s delegated power to make law through rules, it is subject to the public participation and debate that notice and comment procedures provide. Legislative rules have the force of law.... Interpretive rules, on the other hand, do not create rights.... A rule is interpretive ... if it attempts to clarify an existing rule but does not change existing law, policy, or practice.
Id.
(internal quotations and citations omitted). No fair view of FERC’s explanation that, as an alternative basis for denying NYSEG’s underlying petition, it would not invalidate PURPA contracts which had not been challenged from the outset could characterize it as “legislative.” FERC neither created nor denied new rights, law or policy with this statement. Indeed, it is clear that the alleged “continuous challenge rule” is no more than FERC’s reiteration of its “general policy ‘against invalidating contracts for which a PURPA-based challenge was not timely raised— that is, before the contracts were executed,’ so as not ‘to upset the settled expectations of parties to, and to invalidate any of their obligations and responsibilities under, such PURPA sales contracts.”
Connecticut Valley Elec. Co. v. FERC,
NYSEG also claims that its APA claims against FERC are not barred by
Heckler v. Chaney
because it seeks review of both FERC’s failure to order PSC to enforce PURPA in the context of NYSEG’s PPAs with Saranac and Lock-port and FERC’s failure to take such action
itself
by way contractual or regulatory amendment. In the Court’s view, whether it disputes FERC’s failure to direct PSC to act or FERC’s own failure to act, NYSEG’s complaint clearly challenges FERC’s failure to “enforce” PURPA’s alleged rate cap, a matter reserved to the agency’s remedial discretion and not reviewable under the APA.
Heckler v. Chaney,
Under the APA, a party “aggrieved” by an agency must show the agency’s action was “arbitrary and capricious, an abuse of discretion, or otherwise not in accordance with law.” 5 U.S.C. § 706(2)(A). At the outset, the Court questions whether PURPA even requires FERC to “enforce” PURPA in the manner asserted by NY-SEG. According to NYSEG, the overriding purpose of PURPA was to ensure reasonable rates for electric consumers and rates not in excess of avoided costs for utilities. Thus, NYSEG argues that FERC’s failure to cap NYSEG’s payment to Saranac and Lockport at avoided costs is a failure to enforce PURPA.
The Supreme Court has disagreed with NYSEG’s characterization of PURPA’s core purpose, stating that the focus of Title II or Section 210 of PURPA is “to encourage the development of cogeneration and small power production facilities” by addressing “problems imped[ing] the development of non-traditional generating facilities.”
FERC v. Mississippi
The Court disagrees with NYSEG’s contention that PURPA requires FERC to take an active role in monitoring its regulations and QF contracts pursuant to
In
Connecticut Valley,
the plaintiff utility made the same arguments that NYSEG makes here, that is, Section 210(b) of PURPA expressly requires FERC to “balance the interests of consumers against those of producers” and ensure PPA rates do not exceed a utility’s avoided costs.
The Court also determined that FERC’s “grandfathering” of Claremont’s PPA with Connecticut Valley in the face of the clear language of the FPA which disqualifies any QF which sells more than its net output was within its discretion. “The breadth of agency discretion is, if anything, at [its] zenith when the action assailed relates primarily not to the issue of ascertaining whether conduct violates the statute, or regulations, but rather to the fashioning of policies, remedies, and sanctions.”
Id.
at 1044 (quoting
Niagara Mohawk Power Corp. v. Federal Power Commission,
Finally, the Court found in
Connecticut Valley
that FERC did not abuse its remedial discretion pursuant to the APA by deciding not to revoke Claremont’s QF status or provide any alternative relief since the relevant statutory purpose of PURPA was to “encourage the develop
Even if this were not true, FERC has no power — under either PURPA or the FPA — -to revise, rescind or otherwise alter the force and effect of the Saranac and Lockport agreements. As discussed above, PURPA does not require or authorize FERC to take an active role in monitoring the rates in QF contracts to ensure they are “just and reasonable.” 16 U.S.C. § 824a-3(b)(l). 44 Indeed, PURPA expressly exempts QFs from this very type of scrutiny associated with rate regulation under the FPA. See 16 U.S.C. § 824a-3(e). 45
NYSEG recognizes as much in arguing that “FERC’s regulations
currently
exempt QFs from FPA section 206, which directs FERC to modify contract rates if it determines that such rates are unjust and unreasonable.” NYSEG Brief, p. 25 (emphasis in original). Nevertheless, NYSEG argues that FERC “can simply change its rules to effectuate Congress’ intent to charge ratepayers only avoided cost for QF power.”
Id.
at p. 27. NYSEG cites a FERC decision in which the agency allegedly noted that “cogeneration no longer needs to be encouraged.” NYSEG Brief, p. 27 (citing
California,
70 F.E.R.C., at 61,675). According to NYSEG, utilities “have taken a back seat to independent power production.” I'd
46
Thus, NYSEG argues PURPA’s mandate that: 1) FERC
The Court does not deem NYSEG’s underlying petition as sufficient to invoke the rulemaking authority of FERC since NYSEG made no reference to Section 553(e) of the APA therein and its requests for modification or waiver of PURPA rules were “too situation specific and too informal” in that they merely requested FERC take action to relieve it of the Saranac and Lockport agreements.
South Hills,
Review of PURPA’s legislative history as well as decisions of courts which have resolved disputes based on PURPA suggests that Congress could not have intended FERC to have the power to revisit its exemption regulations piecemeal on a QF by QF or PPA by PPA basis retrospectively. Thus while the PURPA language on which NYSEG relies might conceivably grant FERC authority to deem FPA exemption for QFs unnecessary “in whole or part,” in the context of general rulemaking proceedings to amend its 1980 regulations, it cannot be reasonably read to authorize FERC to withdraw FPA exemption from individual QFs thereby invalidating rate terms in existing purchase contracts. Nor could FERC revoke FPA exemption from all QFs in a general rule-making and then apply the revised rules retroactively to the Saranac and Lockport agreements. Such action by FERC would fly in the face of PURPA’s core purpose which is to encourage cogeneration.
Moreover, retroactive rule-making by an agency is prohibited unless Congress expressly conveys this power.
See Bowen v. Georgetown Univ. Hosp.,
Contrary to NYSEG’s arguments, retroactive rulemaking is not authorized here based on the patent “illegality” of: 1) 18 C.F.R. § 292.304(b)(5) which allows Saranac and Lockport to collect a rate in excess of avoided costs because it is based on estimated LRACs in a long-term PPA; and 2) the PPA rates themselves because QFs have no ‘Vested interest” in rates which violate PURPA. As discussed above, FERC’s regulations, which account for and forgive a rate in excess of avoided costs in NYSEG’s very circumstances, are not illegal and QFs are entitled to rely on purchase rates in long-term PPAs even if they violate PURPA’s rate cap.
See Connecticut Valley,
In sum, this Court is without subject matter jurisdiction to entertain any of NY-SEG’s claims against FERC. 52
3. Statute of Limitations
Assuming any of NYSEG’s claims is not fatally flawed by an absence of subject matter jurisdiction, FERC, along with Saranac and Lockport, also argue that NYSEG’s action should be dismissed on statute of limitations grounds since the utility failed to seek review of FERC’s avoided cost rules at the time they were promulgated in 1980. According to Saranac and Lockport, an aggrieved party has sixty (60) days to petition for judicial review of a final order of FERC under the FPA
53
and/or six (6) years to challenge an agency rule under the APA.
See Blassingame v. Secretary of Navy,
NYSEG responds that: 1) its claim against FERC was not ripe in 1980 when the regulations were promulgated because it did not know at that time that it would enter into the Saranac and Lockport PPAs based on estimated LRACs which would
FERC argues that NYSEG cannot avoid statute of limitations issues by claiming that its dispute against FERC was not “ripe” until now. Indeed, FERC asserts that its avoided cost rules were challenged by other parties at the time they were promulgated and the D.C. Circuit rejected a related “ripeness” argument. In API, FERC argued that the utilities’ claims were not ripe for review because the avoided cost rule had not yet been applied and it was not clear that the regulation would lead to rates which exceeded avoided costs. The court held that since the FPA required a party to file a petition for review of a FERC order within 60 days, petitioners had standing to challenge the as yet unapplied rules prospectively. Indeed, the court found that if plaintiffs failed to pursue their remedies of judicial review then, they did so “at the peril of losing the right ever to challenge the validity of [FERCj’s regulations.” Id. at 1232, n. 26. The Court finds that NYSEG has done just that insofar as review of FERC’s regulations pursuant to the FPA. There is no legal authority for extending the FPA’s limitation of 60 days for judicial review of FERC orders.
However, the APA’s statute of limitations has been interpreted differently. The Court next addresses NYSEG’s argument that the FPA’s statutory time limit on judicial review does not bar its claim that “changed circumstances” obligates FERC to revise its rules pursuant to the APA.
Geller v. FCC,
This differs drastically from the rule-making power granted to FERC in Section 210 of PURPA whereby the agency is directed to prescribe rules which “encourage cogeneration.” 16 U.S.C. § 824a-3(a). The legislative history of PURPA suggests that while Congress recognized that the full avoided cost rule would not directly provide any rate savings to electric utility consumers, it deemed it “more important that the rule could ‘provide a significant incentive for a higher growth rate’ of co-generation and small power production, and that ‘these ratepayers and the nation as a whole will benefit from the decreased reliance on scarce fossil fuels, such as oil and gas, and the more efficient use of energy.’ ”
API,
Moreover, review of the legislative history accompanying FERC’s PURPA regulations indicates that the very risk about which NYSEG complains herein — that is, the danger that avoided cost estimates would differ from actual avoided costs over time and thus exceed a utility’s avoided costs at the time of delivery of energy by QFs pursuant to a long-term PPA — was expressly identified and accounted for by FERC when it enacted the regulations in 1980. See NYSEG, 70 F.E.R.C., at 61,116 (citing Small Poiuer Prod, and Cogeneration Facilities; Regs. Implementing Section 210 of [PURPA], Order No. 69, 45 Fed.Reg. at 12224, FERC Statutes and Regs., Regs. Preambles 1977-1981, at 30,880). Indeed, FERC specifically found that the regulation, which forgives rates based on estimated LRACS which exceed avoided costs in the case of a long-term PPA, was necessary to protect QFs’ investments in the event of “changed circumstances.” Id. Thus, NY-SEG’s identification of a self-styled “permanent” divergence between actual and estimated avoided costs can hardly be considered “changed circumstances” such to obligate FERC to consider this calculated risk anew. 55
Even if this were not true, it is not at all clear, contrary to NYSEG’s arguments, that the nationwide energy crisis which prompted enactment of PURPA or circumstances in the electrical industry in particular have so changed as to require FERC to revisit those portions of its 1980 regulations which: 1) granted QFs the option of “locking in” PPA rates at LRACs estimated at the time contracts are signed; 2) excused PPA rates which differed from actual avoided costs at the time energy is delivered when estimates were used to set the rate in a long-term PPA; and 3) exempted QFs from regulation pursuant to the FPA. Certainly FERC’s decision in California 56 and its “restructuring of the electric utility industry under FERC Order No. 888” 57 do not mandate such a result. Even if Order No. 888 was somehow applicable to NYSEG’s relationships with Saranac and Lockport, it was not issued until more than one year after FERC denied NYSEG’s underlying administrative petition. Thus, FERC could not have considered Order No. 888 insofar as granting relief to NYSEG based on “changed circumstances.”. .
NYSEG’s final argument in connection with statute of limitations is that it can raise a claim that a regulation conflicts with its authorizing statute at any time relying principally on
NLRB v. FLRA.
There, the court recognized the right to obtain review of agency regulations “by
The second type of claim is that agency regulations “suffer from some substantive deficiency other than the agency’s lack of statutory authority” to issue them. Id. Such a claim may be brought by petitioning the agency for amendment or recission of the rules and then appealing denial of the petition. See id. Denial of a petition in these circumstances would be reviewable as a “final order” pursuant to the APA’s arbitrary and capricious standard. Id. Of course, “review in cases of this kind ... is limited to the narrow issues as defined by the denial of the petition for rulemaking, and does not extend to a challenge of the agency’s original action in promulgating the disputed rule.” Id. (internal quotations and citations omitted).
As discussed previously, NYSEG characterizes its underlying administrative petition before FERC as one which sought a new rulemaking, but review of the petition reveals that NYSEG requested only modification or waiver of rules necessary to provide it alone with the specific relief it was seeking therein — namely, reformation or recission of the Saranac and Lockport PPAs. Thus, NYSEG is in an entirely different stead than the plaintiff union in
NLRB v. FLRA,
which sought a general prospective rulemaking to amend parallel regulations which were allegedly inconsistent with the Federal Labor Relations Act. Here, NYSEG seeks retroactive revision or waiver of FERC rules which is clearly prohibited in the absence of specific Congressional intent.
See Bowen v. Georgetown Univ. Hosp.,
NYSEG’s final argument is that those portions of FERC’s regulations which excuse PURPA purchase rates in excess of avoided costs in a long-term PPA and simultaneously exempt QFs from regulation pursuant to the FPA are
ultra vires
and therefore subject to challenge outside of the statutory limitations period.
See NLRB v. FLRA,
Based on the foregoing, each of NY-SEG’s claims against FERC is untimely assuming they are not barred from the outset by lack of subject matter jurisdiction. The Court observes that NYSEG’s concerns regarding the absence of a remedy against FERC and being victimized in a “regulatory run-around” are valid only in the sense that NYSEG has no current remedy against FERC. NYSEG clearly had a remedy against FERC at the time it prescribed the regulations at issue herein and could have petitioned FERC at any time for prospective amendment or waiver of those regulations which it neglected to do.
B. Motions to Dismiss Counts II, III and IV (N.Y.SEG’s Claims Against PSC)
NYSEG conceded at oral argument before this Court that its “primary” claim herein is against FERC because it believes “those who issue the rules can change them.” Nevertheless, NYSEG also lodges claims against PSC. NYSEG’s second, third, and fourth causes of action allege that: 1) PSC has violated and continues to violate PURPA and FERC’s rules implementing PURPA by establishing policies, enacting regulations and issuing orders which require NYSEG to incur illegal contractual obligations; 2) PSC violated and continues to violate the Supremacy Clause of the United States Constitution by permitting payments to QFs in excess of NY-SEG’s avoided costs; and 3) PSC has failed to comply with a regulation implementing PURPA in violation of Section 210(f). With respect to this claim, NYSEG seeks enforcement of FERC’s regulations under PURPA as authorized by Section 210(h).
PSC, along with Saranac and Lockport, seek dismissal of these causes of action on eight grounds: 1) this Court lacks subject matter jurisdiction because review of PSC’s action implementing PURPA lies exclusively with state courts; 2) NYSEG’s present claims are barred by the doctrines of res judicata and collateral estoppel; 3) the statute of limitations has run on NY-SEG’s claims against PSC; 4) NYSEG’s present claims against PSC are an impermissible collateral attack on agency action; 5) the Court is obligated to dismiss the complaint as a matter of equitable discretion, 6) the complaint is barred by the Tenth Amendment; 7) the complaint is barred by the Eleventh Amendment; and 8) PSC has no authority to modify a previously approved QF contract pursuant to the Third Circuit’s holding in Freehold. See brief discussion at page 229 infra.
1. Subject Matter Jurisdiction
PSC, along with Saranac and Lockport, argue that state courts have exclusive jurisdiction over claims that a state regulatory agency such as PSC has failed properly to implement PURPA as evidenced by Section 210(g) which governs judicial review of orders by state power authorities implementing FERC regulations. See 16 U.S.C. § 824a-3(g)(l). 59 Thus, these defendants argue that this Court is without subject matter jurisdiction to consider NY-SEG’s Section 210(h) enforcement action against PSC. 60
According to PSC, Section 210(h) of PURPA, authorizing an enforcement action against a state agency in district court, applies only if the state agency has failed to act altogether in implementing PURPA.
62
According to PSC, since it did act by fully implementing PURPA, Section 210(g) applies. The Court can discern no such distinction in the statute. Rather, it is clear that section 210(g) of PURPA “applies only to review of proceedings ... designed to implement any requirement of rules promulgated by ... FERC pursuant to Section 210(a).”
Freehold,
With respect to the second cause of action, NYSEG alleges that PSC has violated PURPA by establishing policies, enacting regulations and issuing orders which require NYSEG to pay more than avoided costs for QF purchases. NYSEG also alleges that PSC has failed to change its policies, regulations and orders in violation of PURPA. However, the claim is based expressly on PSC’s “implementation of PURPA and FERC’s rules promulgated thereunder.” NYSEG’s Complaint ¶ 57. “[I]f a case concerns implementation pro-
Finally, the Court notes that NYSEG’s third cause of action against PSC for violation of the Supremacy Clause
63
of the United States Constitution triggers federal question jurisdiction pursuant to 28 U.S.C. § 1331.
See Freehold,
2. Res Judicata and Collateral Estoppel
PSC, along with Saranac and Loekport, argue that since NYSEG did not appeal the orders which set NYSEG’s LRACs and approved the QF contracts at issue herein, those orders are entitled to preclusive effect and bar NYSEG’s present claims against PSC. Claim preclusion or
res judicata
dictates that “a final judgment on the merits of an action precludes the parties or their privies from relitigating issues that were or could have been raised in that action.”
Allen v. McCurry,
Under the full faith and credit doctrine, federal courts must accord final judgments of state courts the same preclu-sive effect such judgments would have in the state courts.
See
28 U.S.C. § 1738. In New York, issue preclusion may arise from the quasi-judicial determinations of administrative agencies.
See Allied Chemical v. Niagara Mohawk Power Corp.,
NYSEG’s response is two-fold. First, argues that it never raised and could not have raised the issues it complains of day before either FERC or PSC at the time the relevant regulations and orders this case were finalized. According to NY-SEG, its speculation that LRAC estimates would prove ineffective in ensuring PURPA’s statutory cap was mere “conjec-
NYSEG’s reliance on
Alabama Elec. Coop., Inc. v. FERC,
These circumstances differ dramatically from those at bar where the risk that estimated LRACs would differ from NY-SEG’s actual avoided costs over the life of the Saranac and Lockport agreements not only existed, but was recognized and reconciled by the parties in the form of a discounted PPA rate, at the time the contracts were signed. NYSEG is now foreclosed from protesting a tide that turned more than anticipated. Indeed, the court in Alabama Electric would have required “good faith objections to projected effects ” of proposed rates to be raised in the course of FERC rate-setting proceedings. Id. at 25 (emphasis added).
NYSEG’s second argument in connection with issue and claim preclusion is far more compelling. To wit, NYSEG asserts that
res judicata
and collateral estoppel do not apply to PSC’s determination of the rates in PURPA contracts because “ratemaking is a legislative and not a judicial activity.” Indeed, prospective rate-making, although it often employs quasi-judicial methods of adjudication, does not have preclusive effect because “the reasonableness of a rate depends upon economic conditions, and numerous policy considerations, all of which invariably change over time, requiring that a utility’s rate be susceptible to reconsideration.”
Allied Chemical,
As noted by Judge Pooler when she heard oral argument in this matter, there is scant case law available to guide the Court in deciding whether orders of public utility commissions which govern PURPA contracts are judicial or legislative in na
Review of PSC’s Opinion and Order Adopting Long-Run Avoided Costs for Major Elec. Utils., reveals that prior to establishing PURPA contract rates for QFs based on utilities’ estimated LRACS, PSC: 1) published notice of its intent to do so; 2) solicited comments from both utility and non-utility parties; 3) “in lieu of formal administrative litigation” conducted “technical meetings ... for the purpose of reaching agreements and identifying areas of disagreement;” 4) subjected the parties’ submissions to questioning, discussion and analysis; 5) solicited further findings including additional data, supporting materials and explanations of previous submissions; 6) allowed the parties to submit objections to its staff report which were considered by the Administrative Law Judge (“ALJ”) who decided the matter; and 7) allowed the parties to lodge exceptions to the ALJ’s report. Furthermore, each interested party to PSC’s proceedings was represented by counsel as reflected in its final order.
In proceedings such as this, there necessarily arises a controversy since, in setting purchase rates, PSC is arguably acting legislatively, yet the procedures by or through which it reaches this result appear judicial or quasi-judicial in nature.
See People ex rel. Joline v. Willcox,
In the case of approving the QF contracts, however, PSC’s procedures were far less elaborate. The agency made its determinations based on: 1) petitions from both Saranac and Lockport which asked PSC to direct NYSEG to enter into long-term PPAs under certain terms; 2) NY-SEG’s reply to each petition; 3) each QF’s response to NYSEG’s reply; and 4) NY-SEG’s surreply to each QF response. Thus, even if PSC acted judicially when it established PURPA contract rates, the Court cannot state that when PSC enter
3. Statute of Limitations
The issue of preclusivity may be moot if NYSEG’s claims against PSC are untimely. PSC, along with Saranac and Lockport, argue that NYSEG’s complaint is barred on the ground of statute of limitations because under New York Civil Procedure Law, Article 78 proceedings to challenge agency action must be commenced within four months of final agency action. See N.Y.C.P.L.R. § 217. PSC promulgated LRAC regulations pursuant to PURPA in 1982 and approved the contracts in this case in 1989. Therefore, defendants argue that the statute of limitations is long expired. 67
NYSEG reiterates that the challenges it makes now are not the same as those it could have made back then. Because of its alleged earlier inability to ascertain the facts underlying its challenge, NYSEG claims that its complaint was not justicia-ble when PSC issued the underlying orders. As discussed above, the Court rejects NYSEG’s claims in this regard and agrees that NYSEG’s unawareness of the degree to which the risk of inaccurate LRAC estimates would affect its QF contracts over time is insufficient to excuse its failure to appeal PSC’s orders.
NYSEG also argues that the Article 78 limitations period is not applicable to its PURPA enforcement claim against PSC because in
NYSEG v. FERC,
the D.C. Circuit specifically directed it to district court for an enforcement proceeding.
See,
Finally, NYSEG argues that since a Section 210(h) enforcement proceeding to ensure that a state regulatory agency properly implements PURPA is a federal claim, it is governed by a federal, rather than state, statute of limitations.
68
However, it is well-settled that if Congress fails to include a statute of limitations in a statute, courts should — with few exceptions — impose a state limitations “most closely analogous” to the federal act in need.
See Reed v. United Transp. Union,
“This case falls squarely inside the rule, not the exception.”
Id.
at 35,
NYSEG’s Supremacy Clause claim is premised on PSC’s alleged violation of federal law — PURPA—in permitting PPA rates which exceed NYSEG’s avoided costs. This, according to NYSEG constitutes “unlawful state regulation of the wholesale sale of electric power in interstate commerce, an area pre-empted by the FPA.” 70 NYSEG’s Complaint ¶ 60. It strikes the Court that a declaratory judgment action with its attendant six-year statute of limitations may be the appropriate procedural mechanism to resolve this type of claim, see N.Y.C.P.L.R. § 213(1), 71 but determination of when the applicable limitations period began to run, if ever, is troublesome based on the alleged continuing nature of the statutory and/or constitutional violation. The Court finds it unnecessary to pass on the merits of this issue (which was not raised by the parties in any event), since NYSEG’s Supremacy Clause claim is subject to dismissal on separate grounds as discussed below.
4. Collateral Challenge to Agency Action
In connection with defendants’ related argument concerning collateral attacks,
It is well-settled that when an agency acts outside its jurisdiction or in a manner not authorized by statute, the rule against collateral attacks doesn’t apply.
See Consol. Edison Co. of New York v. PSC,
5. Equitable Discretion
PSC, along with Saranac and Lockport, also argue that this Court should dismiss NYSEG’s claims against PSC based on equitable discretion, citing
Alabama Public Serv. Comm’n v. Southern Railway Co.,
PURPA and its implementing regulations establish “an extensive federal system to encourage and regulate the sale of electrical energy by QFs.”
Freehold,
By providing that states would implement PURPA by enactment of regulatory programs within prescribed guidelines, Congress “expressed its intention that state law provides the content of and operates as federal law.”
Corcoran v. New York Power Auth.,
6. Tenth Amendment
The Tenth Amendment to the United States Constitution provides: “The powers not delegated to the United States by the Constitution nor prohibited by it to the States, are reserved to the States, respectively, or to the people.” U.S. Const., amend. X. Saranac argues that this Court cannot ignore New York’s statute of limitations for claims against a state agency such as PSC without running afoul of the Tenth Amendment.
73
See Johnson v. Fankell,
7. Eleventh Amendment
PSC, along with Saranac and Lockport, argue that the Eleventh Amendment
74
bars this Court from adjudicating NY-SEG’s claims against PSC in federal court.
See Seminole Tribe of Florida v. Florida,
NYSEG first points to
FERC v. Mississippi
in support of its contention that since Congress could have preempted the entire field of utility regulation, but did not, its grant of some power to the states in this area subject to federal court review is not violative of the Eleventh Amendment.
See
NYSEG also argues that New York’s choice to implement PURPA by regulating certain wholesale power transactions constitutes consent to suit under PURPA in federal court. However, the Supreme Court has stated that “[e]onstructive consent is not a doctrine commonly associated with the surrender of constitutional rights.”
College Savings Bank v. Florida Prepaid Postsecondary Educ. Expense Bd.,
The Supreme Court has expressly held that a state’s participation in or agreement to administer a federal program does not constitute waiver of Eleventh Amendment immunity.
See Florida Dep’t of Health and Rehabilitative Servs. v. Florida Nursing Home Assoc.,
NYSEG also argues that since it seeks to prohibit PSC from violating the Supremacy Clause, Eleventh Amendment sovereign immunity does not apply to PSC.
See Burgio and Campofelice, Inc. v. New York State Dep’t of Labor,
8. PSC’s Ability to Alter Existing Contracts
Although NYSEG’s Supremacy Clause claim has withstood staunch jurisdictional attacks by PSC and the other defendants, it falls ultimately for failure to state a claim upon which relief can be granted. PSC, along with Saranac and Lockport, argue that PSC has no power to alter existing contracts pursuant to the regulatory exemptions granted to QFs via PURPA. Section 210(c) of PURPA required FERC to prescribe rules exempting QF’s from the FPA and state utility-type regulation,
see
16 U.S.C. § 824a-3(e)(l), which directive FERC fulfilled by promulgating 18 C.F.R. §§ 292.601-292.602, which exempt certain QFs, including Sara-nac and Lockport, from traditional utility-type regulation. The Third Circuit held that these provisions together with FERC’s avoided cost regulations, preempt a state regulatory commission from modifying previously approved rates in a PPA to reconcile a significant decline in the utility’s avoided costs, the very situation in which NYSEG now finds itself.
See, Freehold,
And NYSEG’s plight is not unique. Since enactment of PURPA, NYSEG is not the only utility which has found itself bound to PPA contracts which obligate it to pay more than avoided costs for purchases. Yet courts which have examined such predicaments have uniformly refrained from trenching upon Congress’ explicit intent to advance the development of alternative energy producers, even if at the expense of traditional utilities and even if at the expense of ratepayers.
See Connecticut Valley,
NYSEG argues that
Freehold
was wrongly decided because continuing oversight of PURPA contracts by a state agency such as PSC is not the “utility-type” regulation of QF’s prohibited by PURPA, but is required to ensure that utilities are not charged more than avoided costs under the contracts. This oversight is required, NYSEG argues, to comply with PURPA’s dictate that state commissions
NYSEG also points to the D.C. Circuit’s decision in NYSEG v. FERC, in which the court said:
The failure of a state commission to ensure that a rate does not exceed a utility’s avoided cost is a failure to comply with a regulation implementing the PURPA.... The alleged failure of the PSC to set the contested rates at NY-SEG’s avoided cost would ordinarily be challenged through an enforcement action brought in district court under § 210(h) ...
In short, the Supremacy Clause is not implicated by PSC’s “permitting” rates which exceed avoided costs because PURPA’s regulations expressly allow such rates in the case of long-term PPAs based on estimates of LRACs. Moreover, because PURPA and FERC’s regulations implementing PURPA expressly exempt QFs from state rate regulation, PSC’s failure to modify or otherwise interfere with the rates in the Saranac and Lockport PPAs is not a violation of federal law. Rather, such restraint is consistent with PURPA and its regulations in light of Freehold.
Based on the above, each of NYSEG’s claims against PSC is deficient as a matter of law and subject to dismissal pursuant to Fed.R.Civ.P. 12.
C. Motions to Dismiss Counts V, VI and VII (N.Y.SEG’s Claims Against the QFs) 77
In its fifth claim for relief, NY-SEG alleges that the Saranac and Lock-port PPAs are illegal under PURPA. The Court disagrees since, as discussed at length above, FERC regulations expressly forgive rates in excess of avoided costs in long term PPAs based on estimated LRACs. Thus, NYSEG’s illegality of contract claim must be dismissed.
The sixth cause of action alleges that NYSEG is excused from performance under the PPAs because an essential purpose of the agreements — ensuring that ratepayers paid no more than avoided cost — has been frustrated.
78
Finally, the
In In re Schenck Tours, the court clarified respect for commercial contracts as follows:
Sanctity of contract constitutes the most fundamental underpinning of commerce. The community’s legitimate need for the stability of business dealings requires the enforcement of contracts according to their terms. This need finds cogent expression in a strong public policy of upholding the validity of freely negotiated contracts, even unwise ones.
The Court agrees that NYSEG did not “freely” contract in the sense that but for PURPA, it may not have chosen to enter into the PPAs with Saranac and Lockport for the terms as approved by PSC. These agreements are plainly the embodiment of a cooperative federal-state regulatory scheme designed to prevent utilities such as NYSEG from discriminating against QFs, thereby discouraging or even quashing development of the alternative energy industry. But contracting within specific regulatory compliance standards and under supervision of PSC is hardly a new concept for NYSEG, a heavily regulated public utility. Furthermore, the QF agreements were not “contracts of adhesion” which have historically been construed to protect unsophisticated parties with unequal influence over binding terms. The contracts were presented to PSC only after arduous negotiations by sophisticated companies led by aggressive business executives and shrewd counsel. The PPAs are, at bottom, unaffected by fraud, undue influence or overweening bargaining power. Moreover, NYSEG always retained the choice ofi appealing especially egregious contract terms or unlawful coercive action by PSC.
Based on these considerations, the Court rejects NYSEG’s contention that these purchase contracts are especially
Furthermore, to suggest as NYSEG does, without apparently any sense of irony, that the parties were “mutually mistaken” about the risk that PPA rates would exceed avoided costs is paradoxical in light of the extensive attention paid to the need for a “true-up” or tracking mechanism in the contracts. Indeed, this risk was identified, discussed and reconciled by every party or entity even remotely affected by PURPA, including Congress in enacting the statute, FERC in prescribing the regulatory scheme, PSC in implementing it, utilities in forecasting LRACs, and QFs in making investment and other decisions. Consequently, NYSEG’s contract claims against Saranac and Lockport must be dismissed.
D. Motions to Dismiss PSC’S Cross-Claim
PSC alleges in its cross-claim that FERC has violated PURPA by failing to reform the Saranac and Lockport contracts. For support, PSC relies on FPA Section 206(a), which authorizes FERC, after notice and hearing, to modify utility rates when the public interest so dictates, and PURPA Section 210(e), which requires FERC to reconsider QF exemption “from time to time.” 80 PSC claims that FERC’s inaction violates PURPA’s incremental cost limitation and thus under the APA is arbitrary, capricious, an abuse of discretion, not in accordance with law, in excess of statutory authority, and without observance of procedures required by law.
PSC’s position in this litigation is equivocal to say the least. While arguing that: 1) it fully and properly implemented PURPA by allowing Saranac and Lockport to “lock in” fifteen-year contract rates based on estimated LRACs; 2) it has no legal authority or continuing obligation to revise or modify these contracts which it— not FERC — ordered and approved; and 3) the PSC orders which set LRACs and established contract terms are long since final and .unappealable, PSC contends that the contract rates violate PURPA and that FERC must reconcile them to NYSEG’s current actual avoided costs. PSC’s arguments fail on multiple levels, the first of which is subject matter jurisdiction.
To the extent that PSC relies on the jurisdictional predicate of the FPA for its cross-claim, it is precluded from doing so because it never petitioned FERC for a rehearing prior to seeking judicial review under the FPA as required by 16 U.S.C. § 825i(a).
See Town of Norwood, Mass. v. FERC,
Even if this were not true, the District of Columbia Court of Appeals has exclusive jurisdiction over review of FERC actions under the FPA.
See
16 U.S.C. § 825i(b). PSC’s argument that the D.C. Circuit already declined jurisdiction in this matter and directed the parties to district court is just as deficient coming from PSC as from NYSEG. The D.C. Circuit did not conclude that there were, in fact, FPA questions in this case to resolve independent of NYSEG’s PURPA enforcement claim.
See NYSEG v. FERC,
Insofar as PSC’s attempt to couch its cross-claim as an “enforcement” action against FERC, the very notion flies in the face of the statute. Section 210(h) of PURPA allows a cogenerator or utility to petition FERC to bring an enforcement action against a state public service commission for failure to implement PURPA. See 16 U.S.C. § 824a-3(h). If FERC declines to do so, the cogenerator or utility may bring its own enforcement action against the state commission. Here, PSC, a state utility commission, sues FERC for failure to revise contracts which PSC itself ordered in fully and properly implementing PURPA. The “enforcement” contemplated under the statute is enforcement of FERC regulations against non-compliant state commissions. See 16 U.S.C. § 824a-3(f), (h). PSC turns PURPA inside out by seeking to enforce the statute’s alleged rate cap against FERC when the agency already reconciled the “rate cap” with excessive contract rates in long term PPAs based on estimated LRACs in its regulations. See 29 C.F.R. § 292.304(a)(5). Thus, PSC cannot sue FERC under the guise of a Section 210(h) enforcement action. PSC provides no legal support for its vague contention that it seeks enforcement of Section 210 of PURPA “in general” against FERC.
Finally, NYSEG’s contention, on behalf of PSC, that the APA is a jurisdictional avenue to entertain PSC’s cross-claim is flawed for several reasons, the most fatal being PSC’s lack of standing to sue under the APA. PSC is not an “aggrieved party” within the meaning of the APA. See 5 U.S.C. § 702. PSC argues that it has standing, as parens patriae, to intervene in any action concerning New York ratepayers pursuant the Public Service Law which provides:
It shall be the duty of counsel to the commission ... to represent and appear for the people of the state and the commission in all actions and proceedings involving any question under this chapter, or within the jurisdiction of the commission, and, if directed to do so to intervene, if possible, in any action or proceeding in which any such question is involved; to commence and prosecute all actions and proceedings directed or authorized ....
N.Y.Pub.Serv.Law § 12 (emphasis added). The problem with this argument is that PSC no longer has jurisdiction over the Saranac and Lockport contracts.
Freehold
removed any shadow of doubt concerning the power of state public utility commissions to alter, revise or continually monitor PURPA contracts once they have been approved and signed.
See Freehold,
Furthermore, assuming
arguendo
that PSC has standing to proceed in the stead of New York’s ratepayers, FERC’s failure to consider PSC’s alleged request for rule-making in the underlying administrative proceeding does not provide grounds for APA review. Although PSC and NYSEG characterize its Notice of Intervention in the underlying FERC proceedings as requesting new rulemaking, PSC merely “urge[d] the Commission to modify the Lockport and Saranac exemptions under Federal Power Act § 206(a) and examine whether these facilities’ prices continue to serve the public interest.” It is true that PSC seeks only prospective modification of the PPA rates unlike NYSEG which seeks to recoup all monies paid in excess of its actual avoided costs over the life of the Saranac and Lockport contracts. However, PSC’s intervening petition was as insufficient as NYSEG’s underlying attempt to invoke the rulemaking authority of FERC. Like NYSEG, PSC made no reference to Section 553(e) of the APA. Thus, PSC’s request for modification or waiver of PURPA rules, even if prospective only, was “too situation specific and too informal” because PSC merely asked FERC to waive or modify QF rate regulation exemptions to allow reformation of the Sara-nac and Lockport agreements.
South Hills,
Even if none of the above were true, PSC’s cross-claim would still fail for precisely the same ultimate reason as NY-SEG’s claim against FERC — FERC has no authority to alter or waive its regulations or exemptions to the extent of altering, even prospectively, the terms of the Saranac and Lockport PPAS. Everything in PURPA’s legislative and regulatory history supports the Court’s conclusion that these QFs are entitled to the benefit of their bargain, even if at the expense of NYSEG and its ratepayers. The court in
Freehold
emphasized that “Congress intended to exempt qualified cogenerators from state
and federal
utility rate regulations.”
IV. Conclusion
Based on the foregoing, defendants’ motions to dismiss NYSEG’s complaint pursuant to Fed.R.Civ.P. 12(b) are GRANTED in their entirety. Furthermore, the motions by defendants FERC, Saranac and Lockport to dismiss PSC’s cross-claim pursuant to Rule 12(b) of the Fed.R.Civ.P. are likewise GRANTED in their entirely. In light of this ruling, the motions by PSC and Independent Power Producers of New York to intervene as well as the motions for summary judgment or partial summary judgment filed by Saranac, PSC and NY-SEG are denied as moot.
IT IS SO ORDERED.
Notes
. In addition to PURPA, the package included the Energy Tax of 1978, Pub.L. 95-618, 92 Stat. 3174; the National Energy Conservation Policy Act, Pub.L. 95-619, 92-Stat. 3206; the Powerplant and Industrial Fuel Use Act of 1978, Pub.L. 95-620, 92 Stat. 3289; and the Natural Gas Policy Act of 1978, Pub.L. 95-621, 92 Stat. 3351.
See FERC v. Mississippi,
. A qualifying cogeneration facility is defined by PURPA as a small power production facility of “not more than 80 megawatt (“MW”) capacity,” 16 U.S.C. § 824a-3(a), which produces electric energy primarily by use of solar or wind energy, waste or geothermal resources and is owned by a person “not primarily engaged in the generation or sale of electric power (other than electric power solely from cogeneration facilities or small power production facilities).” 16 U.S.C. § 796(17)(A)-(E).
. These requirements were based on Congress’ identification of two problems which impeded the development of non-traditional generational facilities: 1) traditional electrical utilities were reluctant to purchase power from, and sell power to non-traditional facilities; and 2) regulation of non-traditional facilities by state and federal utility authorities imposed undue financial burdens on small alternative energy producers.
See FERC v. Mississippi,
.Section 210(f)(1) of PURPA obligates state regulatory agencies to implement FERC’s rules through their own rulemaking. Prior to the enactment of PURPA, FERC had exclusive authority to regulate wholesale power rates charged by utilities under the Federal Power Act ("FPA”).
See Arkansas Elec. Co-op. v. Arkansas Pub. Serv. Comm'n,
. Saranac owns and operates a cogeneration facility in Plattsburgh, New York.
See NYSEG,
71 F.E.R.C. ¶ 61,027, at 61107,
. Lockport owns and operates a cogeneration facility in Lockport, New York.
See NYSEG,
71 F.E.R.C., at 61107,
.The two analysts retained by NYSEG are Energy Management Associates ("EMA”) and ICF Resources, Incorporated ("ICF”).
See NYSEG,
71 F.E.R.C., at 61,107, n. 18,
See id.
. In approving the contract, PSC acknowledged that "Empire's [fixed pricing] proposal offer[ed] several benefits to ameliorate potentially harmful impacts on ratepayers associated with the large size of the project and the inherent uncertainty of LRAC estimates." Id. at 19. Indeed, PSC noted that Empire's proposal granted NYSEG graduated discounts from the 1988 LRAC estimates. "Some additional features, such as the absence of a front-load and the dispatchability provisions [reducing the purchase rate for up to 45 MW of energy produced by Lockport which NYSEG might opt not to buy based on cost considerations], offset the risk to ratepayers inherent in fixed pricing based on estimates.” Id. at 21. However, PSC rejected Empire’s 20-year fixed pricing proposal in favor of a 15-year term because “[b]eyond the 15-year period, ... the risk of substantial ratepayer overpay-ments is simply too great, should actual avoided costs fall well below estimates.” Id. PSC rejected NYSEG's argument that a tracking and reconciliation mechanism was required, principally because the "remaining terms of the contract were attractive” and such an approach would "treat payments to [QFs] differently from payments to another utility for long-term purchases [which are not reconciled to the utility's avoided costs.]” Id. at 22.
. Falcon subsequently sought approval to consolidate its three projects into one 293.7 MW facility with output to be priced at an increased discount from NYSEG’s 1988 LRAC estimates. See Order Granting Reh'g in Part and Directing Filing of a Contract Supp., PSC Case Nos. 90-E-0867, 90-E-0865 and 90-E-0860 (July 12, 1991). NYSEG objected to the pricing provisions of the proposed consolidated contract and sought a larger discount. PSC granted Falcon’s petition but did allow NYSEG a greater discount based on the savings [Falcon] can expect in constructing one larger facility rather than three smaller ones. Id. at 12. The increased discount was intended to:
[C]ompensate[ ] ratepayers for the risk of overpayments associated with any fixed-price contract of this length for a facility this large coming on-line after substantial delays threaten to render stale the controlling set of [1988] LRAC estimates.... Moreover, because the preliminary results of utility bidding auctions indicate that existing LRAC estimates may be overstated, a discount of this size is needed to protect against that known risk.
Id. at 12-13 (citing Proceeding to Establish Policies & P. for Power Purchases, PSC Case No. 90-E-0675, Opinion No. 91-2 (Feb. 21, 1991)).
.In its order approving the Falcon agreement, PSC noted:
While reconciliation mechanisms reduce ratepayer risk, and so permit approval of a contract upon a lesser discount than that needed to justify an unreconciled fixed-rate schedule, the 7.4% discount [from NYSEG’s 1988 estimated LRACs] ... is sufficientwithout reconciliation. This discount ... exceeds the discounts provided under most reconciled contracts.
Id. (citing Order Approving Contracts Subject to Conditions, PSC Case Nos. 90-E-0867, 90-E-0865 and 90-E-0860, at 16 (citing Niagara Mohawk Power Corp. and Kamine Bng’g, Inc., PSC Case No. 28689 (Mar. 5, 1991)) (Order Approving Contracts Subject to Conditions) (reconciled contracts provided only 5.2% discount)).
. Saranac and Lockport intervened in the FERC proceeding along with PSC. See NY-SEG, 70 F.E.R.C., at 61,108-09.
. Federal regulations provide that a rates for purchases in PPAs mandated by PURPA "[b]e just and reasonable to the electric consumer of the electric utility and in the public interest,” and “not discriminate against [QFs].” 18 C.F.R. § 292.304(a)(1). The regulations also repeat PURPA's prohibition against purchase rates which exceed a utility's avoided costs. See 18 C.F.R. § 292.304(a)(2).
. Section 210(h) of PURPA sets forth procedures and authority for FERC to enforce Section 210(f) (requiring state regulatory authorities to implement FERC’s rules and regulations) against state utility regulatory authorities which fail to comply with PURPA. See 16 U.S.C. § 824a-3(h)(2)(A).
. There, FERC declared that a Connecticut statute, which, as applied, could require electric utilities to purchase power from certain types of QFs (resource recovery facilities owned or operated for the benefit of municipalities) at a rate above avoided cost, was preempted by PURPA.
See CL & P,
70 F.E.R.C., at 61,029,
. Federal regulations provide that QFs are permitted to enter into long-term PPAs in which the purchase rate is based on utilities' avoided costs calculated — at the QF’s option — either at the time the contract is executed or at the time the energy is delivered. See 18 C.F.R. § 292.304(d)(2). A rate calculated on a utility’s avoided costs, determined after consideration of prescribed factors, satisfies the criteria of 18 C.F.R. § 292.304(a) governing rates for purchases. See 18 C.F.R. § 292.304(b)(2).
. (Citing
Small Power Prod, and Cogeneration Facilities; Regs. Implementing Section 210 of [PURPA],
Order No. 69, 45 Fed.Reg. at 12224,
[FERC Statutes and Regs., Regs. Preambles] 1977-1981
¶ 30,128, at 30,880 (1980),
order on reh’g, FERC Statutes and Regs., Regs. Preambles 1977-1981
¶ 30,160 (1980),
aff'd in part and vacated in part, AEP,
.Indeed, NYSEG argued as much before FERC:
In ordering NYSEG to accept the terms of the Lockport and Saranac agreements, the New York Commission was carrying out its statutory mandate under Section 210(f) of PURPA to implement the Commission’s rules ... granting] the states broad authority to determine the specific parameters of QF power purchase agreements.
NYSEG, 70 F.E.R.C., at 61,116 (quoting NY-SEG’s petition at pp. 37-38).
. (citing
Order Approving Contracts Subject to Conditions,
PSC Case Nos. 90-E-0867, 90-E-0865 and 90-E-0860, at 16 (citing
Niagara Mohawk Power Corp. and Kamine Eng’g, Inc., Order Approving Contracts Subject to Conditions,
PSC Case No. 28689,
. Although NYSEG styled its petition as one requesting a rehearing, FERC deemed it to request reconsideration. Citing
Indus. Cogenerators v. FERC,
.The FPA provides that if, after a hearing conducted on its own motion or upon complaint, the commission (FERC) finds that any rate for any transmission or sale subject to its jurisdiction is "unjust, unduly discriminatory or preferential,” the agency shall determine a just rate and "fix the same by order.” 16 U.S.C. § 824e(a).
. Saranac and Lockport also intervened in the District of Columbia Circuit proceedings.
. Under PURPA, FERC may bring an enforcement action in federal district court against any state electrical regulatory authority which fails to implement FERC regulations designed to encourage cogeneration. See 16 U.S.C. § 824a-3(h)(2)(A). Alternatively, a utility or cogenerator may petition FERC to bring such an action and, if the agency declines, may itself sue the state regulatory authority in district court. See 16 U.S.C. § 824a-3(h)(2)(B).
. PSC moved to intervene as a party plaintiff and Independent Power Producers of New York also moved to intervene as a defendant. By order dated February 25, 1998, then U.S. Magistrate Judge David N. Hurd denied these motions without prejudice subject to renewal upon this Court determination of the parties’ dispositive motions.
. The APA, codified at 5 U.S.C. § 551 et seq., prescribes procedures by which federal agencies may promulgate rules and make adjudicative determinations. The APA also establishes a right to judicial review of such rulemaking and agency decisions:
A person suffering a legal wrong because of agency action, or adversely or aggrieved by agency action within the meaning of a relevant statute, is entitled to judicial review thereof.
5 U.S.C. § 702. The APA serves as a default mechanism for review in instances where review procedures are not specified in a governing statute.
See Bowen v. Massachusetts,
.In its order denying NYSEG's petition, FERC noted NYSEG had not continuously challenged the PURPA regulatory scheme from its inception.
See NYSEG,
70 F.E.R.C., at 61,117. Rather, FERC found NYSEG waited until it was aggrieved by the regulations to complain.
See id.
This was unlike the facts in
CL & P,
70 F.E.R.C., at 61,029,
. U.S. District Judge Rosemary S. Pooler (now a Circuit Judge for the Second Circuit Court of Appeals), to whom this matter was originally assigned, denied untimely requests to file amicus briefs in support of NYSEG and PSC from the Energy Association of New York ("EA”) and the New York State Consumer Protection Board ("CPB”) by order dated May 8, 1998.
. Recognizing that a ruling on defendants' dismissal motions might moot the various motions for summary judgment, Judge Pooler granted requests to stay resolution of the latter motions by order dated February 5, 1998.
. Subsection (A) of PURPA Section 210(h)(2) authorizes FERC to enforce state implementation of its regulations against a state regulatory authority or non-regulated utility in district court while subsection (B) allows an electric utility or QF to petition FERC to commence such an action. If FERC declines to do so, the utility or QF may commence its own action to force a state agency or non-regulated utility to comply with FERC’s regulations. See 16 U.S.C. § 824a-3(h)(2). In the present case, NYSEG, an electrical utility, seeks enforcement of the statutory requirements of PURPA as well as select PURPA regulations directly against FERC.
. In
Marlow,
a disabled school teacher filed an administrative complaint with the federal Education Department alleging discriminatory failure to hire by the New York City Board of Education Examiners in violation of the federal Rehabilitation Act.
.This presumption can be rebutted if the substantive statute contains guidelines for the agency to follow in exercising its enforcement powers.
Heckler v. Chaney,
. In the alternative, NYSEG argues that FERC’s refusal to bring an enforcement petition is subject to challenge because PURPA provides clear guidelines for the exercise of FERC's discretionary authority by prohibiting PPA rates which exceed avoided costs.
See
16 U.S.C. § 824a-3(b);
Heckler v. Chaney,
. The APA defines a rule as "the whole or part of an agency statement of general or particular applicability and future effect designed to implement, interpret or prescribe law or policy.” 5 U.S.C. § 5514(4).
. 16 U.S.C. § 824a-3(b).
. 16 U.S.C. § 824a-3(a).
. Under the FPA, a party aggrieved by a FERC order may apply for a rehearing within thirty (30) days of issuance of the order. See 16 U.S.C. § 825/(a). A party may obtain review of the order in the Court of Appeals for the circuit in which the parly is located or has its principal place of business or in the D.C. Circuit Court of Appeals by filing a petition within sixty days after FERC denies rehearing. See 16 U.S.C. § 825Z(b).
. Under Section 4(e) of the APA, any interested person may “petition for the issuance, amendment or repeal of a rule.” 5 U.S.C. § 553(e). In
South Hills Health Sys. v. Bowen,
.According to NYSEG, revision of FERC's regulations would not involve retroactive application in the true sense because the regulations which allow for rates in excess of avoided costs were always invalid or
ultra vires
FERC's statutory authority in light of PURPA which mandates that "no ... rule prescribed ... shall provide for a rate which exceeds” avoided costs. 16 U.S.C. § 824a-3(b). In
Nat'l Labor Relations Bd. v. Fed. Labor Relations Auth.,
. Saranac characterizes FERC's alleged “Continuous Challenge Rulé’’ as an interpretive statement whereby FERC acknowledged its lack of retroactive rulemaking authority while Lockport asserts that it was merely an "administrative restatement of the public policy behind the doctrine of collateral estop-pel.” Both QFs maintain, however, that the alleged “rule” does not pave the way for APA review.
. See 16 U.S.C. § 8257(b) (under FPA, party may petition FERC for rehearing and then petition for judicial review of FERC order within 60 days). This is exactly what the plaintiffs did to obtain review of FERC’s PURPA rules in API.
. The APA provides general authorization for review of agency action, but it "does not duplicate the previously established special statutory procedures relating to specific agencies.”
Bowen
v.
Massachusetts,
.There, the court held that an aggrieved party may obtain judicial review of agency regulations after the statutory time limit restricting judicial review by petitioning the agency for amendment or recission of the regulations and appealing the agency's decision.
See
. There, the plaintiff electric utility ("Connecticut Valley") sued FERC after the Commission refused to take action on its petition to revoke the QF status of Claremont, a small power producer ("SPP"), from whom it was obligated to purchase energy pursuant to a PPA. Claremont was selling its "gross” electrical output to Connecticut Valley utility which is "all electricity produced by the facility,” as opposed to its "net” output which is gross output less the electricity used by Clare-mont in its own operations.
Based on this decision, Connecticut Valley petitioned FERC in 1993 to revoke Clare-mont’s status as a QF, take jurisdiction over its PPA with Claremont pursuant to Sections 205 and 206 of the FPA, and either rescind the contract and retroactively determine just and reasonable rates for past sales or at least prospectively reform the contract to ensure it need only purchase Claremont’s net output going forward.
Connecticut Valley,
. Even if this were not true, the “continuous challenge rule,” to the extent it can be deemed legislative, was "announced” by FERC prior to resolution of NYSEG's underlying petition in California, 70 F.E.R.C., at 61,678 and in CL & P, where FERC stated:
We will not entertain requests as a consequence of this order asking us to invalidate on this basis [preemption of state statute which purported to require PURPA PPA rates in excess of avoided costs] other, preexisting contracts where the avoided cost issue could have been raised. The appropriate time to challenge a state-imposed rate is up to or at the time the contract is signed, not several years into a contract which heretofore has been satisfactory to both parties.
CL & P,
70 F.E.R.C., at 61,029,
. The Third Circuit noted in a footnote in
Freehold
that any problem arising from the competing “consumer protection provision of PURPA and the FERC regulation permitting parties to hold incremental avoided cost at the level it has on the date the PPA is effective” is “matter for FERC.”
. In API, the Supreme Court held:
Simply on the basis of the statutory language, we would be reluctant to infer that Congress intended the terms “just and reasonable,” which are frequently associated with cost-of-service utility ratemaking, see, e.g., NAACP v. FPC,425 U.S. at 666 ,96 S.Ct. 1806 , to adopt a cost-of-service approach in the very different context of co-generation and small power production by nontradilional facilities. The legislative history confirms, moreover, that Congress did not intend to impose traditional ratemaking concepts on sales by qualifying facilities to utilities.
.FERC’s observations in connection with the success of PURPA in combating the problem of electric utilities’ traditional refusal to purchase power from cogenerators are not quite this broad. In
California,
FERC recognized that due in large part to the full avoided cost rate mandated in PURPA contracts, “there is no longer any dominance in the provision of
new
generating capacity.” 70 F.E.R.C., at 61,675,
. 16 U.S.C. § 824a-3(a).
. 16 U.S.C. § 824a-3(e).
. Id.
. The Court notes preliminarily FERC's argument that NYSEG’s challenge to FERC's failure to initiate a rulemaking is premature since NYSEG did not file a petition for a rulemaking pursuant to Section 553(e) of the APA. A "threshold requirement of seeking judicial review of an agency’s refusal to undertake rulemaking is the filing of a rulemaking petition with the relevant agency.”
South Hills,
.DIRECTV, Inc. v. Federal Communications Comm’n ("FCC”),
. The Court disagrees with NYSEG's contention that in
NYSEG v. FERC,
the D.C. Circuit "assumed” that such jurisdiction lies in the district court when it determined it would "usurp the district court's role in [PURPA’s] enforcement scheme" if it considered NY-SEG's request that FERC revise its rules.
. See 16 U.S.C. § 8251(b). A request for rehearing is a condition precedent for judicial review. See id. at § 8251(a).
. In NLRB v. FLRA, the court stated:
[Tjhe statutory time limit restricting judicial review of [agency] action is applicable only to cut off review directly from the order promulgating a rule. It does not foreclose subsequent examination of a rule where properly brought before this court for review of further [agency] action applying it. For unlike ordinary adjudicative orders, administrative rules and regulations are capable of continuing application; limiting the right of review of the underlying rule would effectively deny many parties ultimately affected by a rule an opportunity to question its validity.
. Indeed, the Court in
IEP
found that the “proper remedy for such a situation is to ensure future standard offer contracts contain more flexible pricing mechanisms/'
. See infra note 46.
. NYSEG’s reference to "Order No. 888” refers to FERC's order in Promoting Wholesale Competition Through Open Access Nondiscriminatory Transmission Services by Pub-lie Utilities and Recoveiy of Stranded Costs by Public Utilities and Transmitting Utilities, 61 Fed.Reg. 21,540, FERC Stats. & Regs. 31,036 (1996). The Order opened the wholesale electricity market and directs public utilities to open their transmission lines to competitors. The Order entitles electricity consumers to purchase power from entities other than public utilities but requires utilities to transmit the power, even if purchased elsewhere, over their own lines. The Order also allows utilities to recover stranded costs, that is, costs associated with serving customers who use open access to shift to another power supplier. The Order does not in any fashion address the issue of PURPA contracts, PPA rates set at full avoided costs or QF entitlement to FPA exemption.
. Saranac argues that NYSEG's reliance on
NLRB v. FLRA
is misguided because its holding as well as that of
Functional Music
and its progeny were severely limited by
National Mining Assoc, v. U.S. Dep’t of the Interior,
. Section 210(g) of PURPA provides:
(1) Judicial review may be obtained respecting any proceeding conducted by a Slate regulatory authority.., for purposes of implementing any requirement of a rule under subsection (a) of this section in the same manner.., as judicial review may be obtained under section 2633 of this title....
16 U.S.C. § 824a-3(g). Section 123(a) of PURPA, referenced therein, contains an express jurisdictional limitation over actions arising under Title II of PURPA. See 16 U.S.C. § 2633(a). This Section deprives district courts of jurisdiction and bestows exclusive jurisdiction over such matters on state courts.
. While the parties vigorously debate this Court’s power to adjudicate NYSEG’s enforcement action arising under PURPA Section 210(h), no party addressed the issue of subject matter jurisdiction in connection with
. Of course in IPPNY, while FERC determined that the plaintiff cogenerator had properly invoked its jurisdiction to decide a dispute with a public utility commission, the agency did not decide, nor could it, that federal court was a proper forum for obtaining judicial review of state regulation alleged to be inconsistent with PURPA.
. Section 210(h)(2)(B) provides that
Any electric utility.., may petition the Commission to enforce the requirements of subsection (f) of this section as provided in subparagraph (A) of this paragraph. If the Commission does not initiate an enforcement action under, subparagraph (A) against a State regulatory authority.., within 60 days following the date on which a petition is filed under this subparagraph ..., the petitioner may bring an action in the appropriate United States district court to require such state regulatory authority.., to comply with such requirements, and such court may issue such injunctive or other relief as may be appropriate.... .
16 U.S.C. § 824a-3(h)(2)(B). Section 210(1), which is referenced in Section 210(h)(2), requires the state regulatory authority to make rules implementing the FERC's rules for regulated utilities in that state. See 16 U.S.C. § 824a-3(f).
. According to the Supremacy Clause, the U.S. Constitution and the laws passed pursuant to it are the "supreme laws of the land, binding alike upon the states, courts and the people, anything in the Constitution or Laws of any state to the contrary notwithstanding.”
Testa v. Katt,
. In connection with this issue, Saranac and Lockport argue that NYSEG's claims about "permanent” divergence are illusory. According to these defendants, there is no proof that the rates are of! by as much as NYSEG claims. Furthermore, they assert that NY-SEG’s present claim is based on estimates of divergence which may change over time.
. However, courts in other jurisdictions have found that when a public utility commission promulgates an order "under the guise” of its rulemaking authority,
res judicata
does not apply.
Cincinnati Bell Tel. Co. v. Pub. Util. Comm’n of Ohio,
. There, the court found that an order of PSC which determined proportionate shares of a joint rate to be allotted to competing street railway companies was quasi-judicial. PSC held formal hearings on "various days," the parties were represented by counsel, "evidence was taken, argument had and the matter submitted for determination of the commission.”
. As with subject matter jurisdiction, no party briefed the issue of statute of limitations in connection with NYSEG’s Supremacy Clause claim or for that matter, distinguished between NYSEG's various causes of action against PSC in arguing the issue of timeliness.
. Notably absent from NYSEG’s memorandum of law is reference to the federal limitations period which it deems a “more appropriate vehicle for interstitial lawmaking.”
North Star Steel Co. v. Thomas,
.The fact that NYSEG seeks injunctive relief insofar as "compelling” PSC to comply with PURPA and FERC’s rules implementing PURPA in the context of its Section 210(h) enforcement action does not change this result. Although NYSEG has never petitioned PSC for such relief, nor has PSC ever issued an order, regulation or other final determination i.n connection with such relief, N.Y.C.P.L.R. § 217 still renders the PURPA enforcement claim untimely. "An article 78 proceeding may lie in the absence of a final determination where the relief sought is by wa}' of prohibition or by way of mandamtts to compel performance by an administrative agency of a duty enjoined by law.”
Hamp-tons Hosp. & Med. Ctr., Inc. v. Moore,
. Indeed, Congress can pre-empt the states completely in the regulation of retail sales by electricity and gas utilities and in the regulation of transactions between utilities and co-generators.
See FERC v. Mississippi,
. Of course, the Court is cognizant of the fact that to the extent that resolution of NY-SEG’s alleged rights might have been obtained in an article 78 proceeding, the applicable statute of limitations would still be four months even if the action is styled as one seeking declaratory judgment.
See Bd. of Educ. of the Altmar-Parish-Williamstown Cent. Sch. Dist. v. Ambach,
. Indeed, the New York Court of Appeals recognized in
PSC v. Rochester Tel. Corp.,
that collateral attacks on agency action are sustainable on jurisdictional grounds.
. The Supreme Court rejected a Tenth Amendment challenge to PURPA in
FERC v. Mississippi,
. The Eleventh Amendment provides:
The Judicial power of the United States shall not be construed to extend to any suit in law or equity, commenced or prosecuted against one of the United States by Citizens of another State, or by Citizens or Subjects of any Foreign Stale.
U.S. Const., amend. XI.
.
U.S. West Communications Inc. v. TCG Seattle,
. Because the Court finds that the Eleventh Amendment does not bar NYSEG’s Supremacy Clause claim against PSC, it need not consider the merits of NYSEG’s invocation of the exception to sovereign immunity carved out by the Supreme Court in
Ex Parte Young
whereby the Court could enjoin the individual commissioners of PSC from enforcing an allegedly unconstitutional enactment. See
. The Court notes in the first instance that it retains no required independent jurisdiction over NYSEG’s contract claims in the absence of either diversity or subject matter jurisdiction over the federal claims.
. The doctrine of commercial frustration "is an ancient concept rooted in the common law.”
In re Schenck Tours, Inc.,
1) a contingency — something unanticipated, unforeseeable or unexpected — has occurred; 2) the risk of the unexpected occurrence has not been allocated by agreement or otherwise; and 3) both parties can perform the contract but, as a result of theunforeseeable events, performance by one party would no longer give the other party what induced him to make the bargain in the first place. Thus frustrated, the latter party may rescind the contract.
Id. "Perhaps the most significant factor in the determination as to the applicability of the commercial frustration doctrine is the foreseeability of the contingency that actually occurred." Id.
. The "mutual mistake" defense is properly applied "[wjhere a mistake of both parties at the time a contract was made as to a basic assumption on which the contract was made has a material effect on the agreed exchange of
performances....” In re Schenck Tours,
bears the risk of the mistake when a) the risk as allocated to him by agreement of the parties, or b) he is aware, at the time the contract is made, that he has only limited knowledge with respect to the facts to which the mistake relates but treats his limited knowledge as sufficient....
Id.
“Contract avoidance on the grounds of mutual mistake is not permitted just because one party is disappointed in the hope that the facts accord with his wishes.”
Id.
(citing
Backus v. MacLaury,
. Pursuant to PURPA, FERC has exempted QFs from FPA § 206. See 18 C.F.R. § 292.601(c). PSC insists that FERC can change its regulations to remove QFs' exemption from FPA rate regulation and liten modify the PPAs prospectively.
. See
NYSEG,
72 F.E.R.C., at 61,067,
