Opinion for the Court filed by Chief Judge SENTELLE.
Pеtitioner, New York Regional Interconnect, Inc. (“NYRI”), is a New York corporation whose sole business is the development, construction, operation, and maintenance of a future high-voltage transmission line in the state of New York. The high-voltage transmission line contemplated by NYRI would be within the jurisdiсtion of the New York ISO — an independent regional transmission organization that operates, but does not own, the power transmission system in New York state. NYRI petitions for review of a series of three Federal Energy Regulatory Commission (“FERC” or the “Commission”) orders that adopted a new transmission planning process for the New York ISO. NYRI, however, does not have standing to seek review of the challenged FERC orders, so we dismiss its petition for review for lack of jurisdiction.
I.
This case, like many petitions to review the Commission’s orders, necessitates a brief review of the regulatory background of federal energy law. In its landmark Order No. 888, the Commission ordered the national deregulation of electricity transmission services and required the vertically-integrated power utilities to unbundle their electricity generation and transmission services.
See Sacramento Mun. Util. Dist. v. F.E.R.C.,
In an additional effort to increase competition in the power transmission market, Order No. 888 encouraged the development of independent system operators (“ISOs”).
See Cal. Indep. Sys. Operator Corp. v. F.E.R.C.,
In accordance with Order No. 888, the bulk power transmission system in the state of New York is operated, but not owned, by an independent, non-profit corporation, the New York Independent System Operator (“New York ISO”). Among its many other duties, the New York ISO is required by the Commission to develop a region-wide OATT, a rate system for all transmission services provided within its jurisdiction. The New York ISO’s OATT is regulated by the Commission and must be consistent with or supеrior to the Commission’s pro forma OATT. Order No. 888 at 21618-19.
In 2007, a decade after Order No. 888 took effect, the Commission promulgated Order No. 890 to address and remedy “opportunities for undue discrimination under the
pro forma
Open Access Transmission Tariff (OATT) adopted in 1996 by Order No. 888.”
Preventing Undue Discrimination and Preference in Transmission Service,
Order No. 890, 72 Fеd.Reg. 12266, 12267(P1) (Mar. 15, 2007),
order on reh’g,
Order No. 890-A, 73 Fed.Reg. 2984 (Jan. 16, 2008),
order on reh’g,
Order No. 890-B,
One of the changes made to the pro forma OATT implemented by Order No. 890 was a requirement “for public utilities to develop cost allocation principles to address the recovery of costs associated with new transmission projects.” Id. at 12335-36 (PP 552-61). The Commission declined to prescribe any specific cost allocation methodology, stating that it would allow “transmission providers and stakeholders to determine their own specific criteria which best fit their own experience and regional needs.” Id. at 12335-36 (PP 557-58). The Commission advised, however, that it would consider three factors when adjudicating any future disputes over cost allocation proposals: (1) whether the proposal “fairly assigns cоsts among participants, including those who cause them to be incurred and those who otherwise benefit from them;” (2) whether the “proposal provides adequate incentives to construct new transmission;” and (3) “whether the proposal is generally supported by State authorities and participants across the region.” Id. at 12336 (P 559).
In response to the cost allocation requirement in Order No. 890, the New York ISO proposed revisions to its OATT “to incorporate an enhanced economic planning process” that established a method by which the costs of new transmission projects — such as the multi-billion dollar, 190-mile, high-voltage transmission line contemplated by NYRI — might be recovered directly from the New York ISO’s transmission customers. Order No. 890 Trans *585 mission Planning Compliance Filing at 1, 14-15, FERC Docket No. OA08-52-000 (Dec. 7, 2007). Under the New York ISO’s proposal, a transmission project approved under the new economic planning process would be implemented and its costs would be allocated to the New York ISO transmission customers who benefit from the project’s construction. Those customers would repay the costs through increases in the rates they pay to the New York ISO for transmission services. The magnitude of each customer’s ratе increase would be proportional to the economic benefits provided to the customer by the new project. Id. at 14-15.
Under the New York ISO’s proposal, however, only some transmission projects would qualify for reimbursement through the OATT. To receive reimbursement, the project must meet two requirements. First, the New York ISO must determine that the project will have a “production cost benefit.” Id. at 14. Under the terms of the proposed planning process, a project has a production cost benefit if the forecasted production cost savings over the first ten years of the project’s in-service life outweigh the project’s costs. Id. Projects with a production cost benefit would be eligible for cost recovery through the OATT, pending the determination of the second criterion, but those determined to have no production cost benefit would be denied mandatory cost allocation.
In addition to having a production cost benefit, new transmission projects must also be approved by a supermajority of the project’s beneficiaries — those entities that would benefit economically from the project and from whom the project’s costs would be recovered. Id. at 14-15. The New York ISO would provide information about the proposed project to the beneficiaries, including estimates of both economic and non-quantifiable benefits, such as environmental impacts and renewable integration. Id. The beneficiaries wоuld then vote to determine whether the proposed project should receive cost allocation, with each beneficiary’s vote weighted to correspond to its share of the project’s benefits and costs. Id. at 15. Projects approved by at least eighty percent of the beneficiaries would be implemented and cost allocation through the OATT would be approved. Id.
NYRI, which presumably wishes to obtain cost allocation for its proposed high-voltage transmission line through the New York ISO’s OATT, opposed the New York ISO’s proposal at every stage of the administrative process. In July 2008, NYRI filed a protest to the New York ISO’s Order No. 890 compliance filing.
See Motion to Intervene and Protest of New York Regional Interconnect, Inc.,
FERC Docket No. OA08-52-000 (July 9, 2008). After the Commission approved the New York ISO’s transmission planning process in the first of the three orders chаllenged by NYRI,
New York Independent System Operator, Inc.,
II.
Before this court can consider the merits of NYRI’s petition, there is a threshold issue that we must resolve. Certain intervenors in this case — the New York ISO and several participants in the New York power market — argue that NYRI lacks standing to petition this court to review the FERC orders because NYRI has not been “aggrieved” by those orders as required by the Federal Power Act.
1
Because standing is an “essential and unchanging part of the case-or-controversy requirement of Article III,”
Lujan v. Defenders of Wildlife,
Section 313 of the Federal Power Act provides that “[a]ny party to a proceeding under this chapter aggrieved by an order issued by the Commission in such proceeding may obtain a review of such order ... in the United States Court оf Appeals for the District of Columbia.” 16 U.S.C. § 825Z(b). Parties are “aggrieved” under the Federal Power Act if they satisfy both the constitutional and prudential requirements for standing.
Exxon Mobil Corp. v. F.E.R.C.,
It is well established “that the irreducible constitutional minimum of standing contаins three elements.”
Lujan,
The intervenors and the Commission argue that NYRI has no standing before this court because it cannоt show that it has suffered an injury in fact. This is so, they contend, because NYRI does not have any active proposals for new transmission projects that would be affected by the challenged FERC orders. Although NYRI previously submitted an application to the New York Public Service Commission for the construction of a new high-voltage transmission line, NYRI admits that it withdrew that application on April 9, 2009. *587 Final Reply Br. of New York Regional Interconnect, Inc. at 19, N.Y. Reg’l Interconnect, Inc. v. F.E.R.C., No. 09-1309 (D.C.Cir. Nov. 9, 2010).
In response, NYRI argues that it has standing to challenge FERC’s orders because it “has suffered injury to a protected interest, i.e., an interest that is “within the zone of intеrests to be protected or regulated by FERC under’ the applicable statute.”
Id.
at 16 (quoting
Moreau v. F.E.R.C.,
NYRI cannot establish constitutional standing because it has suffered no actual or imminent injury in fact to a judicially cognizable interest. Although NYRI argues that the Commission’s rulings have caused it to suffer a concrete injury to its protected interest in “an impartial assessment of its proposed projеct,” this alleged injury rests upon a hypothetical chain of events, none of which is certain to occur. Under NYRI’s theory,
if
NYRI proceeds with a transmission project within the New York ISO’s jurisdiction, and
if
that proposal obtains siting and permitting from the New York Public Service Commission, and
if
NYRI applies for cost allocation through the New York ISO OATT, then NYRI will be harmed because
either
the New York ISO will wrongfully determine that the benefits of the project do not outweigh the costs,
or
the project’s beneficiaries will wrongfully vote against the project. This theory stacks speculation upon hypothetical upon speculation, which does not establish an “actual or imminent” injury.
See Lujan,
NYRI has presented at most an allegation of injury to its procedural rights. It is true that “a plaintiff may have standing if it can show that an agency failed to abide by a procedural requirement that was ‘designed to protect some threatenеd concrete interest’ of the plaintiff.”
Ctr. for Biological Diversity v. U.S. Dep’t of Interior,
Without an active application for a transmission project in the New York ISO, nothing distinguishes NYRI from any other party who might someday wish to build a high-voltage transmission line in New York.
See Lujan,
III.
For the reasons set forth above, we hold that NYRI has no standing to bring this action. The petition for review is dismissed.
Notes
. Although the Commission failed to raise the issue in its brief, at oral argument the Commission joined the intervenors in asserting that NYRI has no standing before this court.