260 Mass. 242 | Mass. | 1927
On August 4, 1909, the defendant entered into a contract with the plaintiff, the lessee of the Boston and Albany Railroad, for the building of a concrete retaining wall approximately seven hundred feet in length along the northerly side of the location of the railroad at Brighton in this Commonwealth. The work was to be done in accordance with plans and specifications prepared by the plaintiff’s engineer, and “All directions, explanations, superintendence, and instructions, spoken of, or required” under the contract also were to be given by the chief engineer or such “Engineers in charge of the work, Assistant Engineers or Inspectors as he may designate in writing,” whose functions and powers were “strictly limited to the supervision of the Contractor’s operations in executing this work.” The contract further provided that such engineers in charge of the work, assistant engineers and inspectors “are . . . expressly prohibited from making, permitting, or authorizing any alterations, changes, or departures in or from the terms and provisions of this contract, or said plans and specifications.” The chief engineer was the only person authorized to make changes and to determine the quality and quantity of the work performed. His interpretation of and decision upon questions in dispute between the parties was to be accepted as conclusive and binding, and “Any omission or failure on the part of the Engineer in charge of the work, or of the Chief Engineer, to disapprove or reject any work or material at the time of a monthly or other estimate, or during the inspection of the work or materials, shall not be construed to be an acceptance of any defective work or material.” The contract contained the following clause of indemnity: “The Contractor agrees to indemnify and save harmless the Company for and from all claims, demands, payments, suits, actions, recoveries and judgments of every name and description, brought or recovered against it, for, or on account of, any injuries or
The present action is brought to recover damages for an alleged breach of the clause of indemnity. It could have been found by the jury that, as the work progressed, the retaining wall extended for a short distance on to the land of one Hermine Szathmary, an abutting owner, who had not assented to the encroachment. It was contended by the defendant that if any trespass had been committed, in the erection of the wall, it was done under the direction, order and approval of the plaintiff and was due to its negligence,
After the introduction of the foregoing documentary evidence and the report of an auditor to whom the case had been referred, the plaintiff rested. During the introduction of testimony by the defendant, and subject to its exception, the judge made the following rulings: “ . . . the question of encroachment upon Szathmary land is conclusively deter
“If the plaintiff in good faith made the settlement on the basis that there was an encroachment there and made what he deemed in good faith was the best settlement that could be made under the circumstances, that although in reaching that settlement he got a deed for an easement in the Szath-mary land, that that came in within the terms of the contract of indemnity, whereby the plaintiff [sic] was obliged to pay the plaintiff, what it paid out to get rid of the encroachment. If the taking of the deed was merely a form or means of reaching a settlement in good faith, that it would not deprive the plaintiff of a right of action against the defendant for an amount paid in good faith, if the real basis of the getting of the deed and the paying of it was to make a final settlement.
“I think it appears if the plaintiff acted as a reasonably prudent man would act under similar circumstances, acting in good faith, then that it may recover the amount it paid, although it turns out and the jury find that the work would have been done for less, if before the settlement the plaintiff notified the defendant that it was considering seriously the question of settlement, and gave some idea as to the approximate amount or some amount that was being spoken of.
“It is open to the defendant in this suit to show that the work of removing the encroachment upon Szathmary land could be done for much less money than the plaintiff paid in settlement of the trespass, and that it is also open to the defendant to show that the money wasn’t paid in good faith, that it was paid after the defendant notified the plaintiff through its counsel that it was ready to do the work of removing the encroachment, if there was an encroachment, for $200, provided it had the right to go on the property of Szathmary so to do.”
The plaintiff, accordingly, must show that the settlement was fair and reasonable in view of the circumstances under the indemnity clause. It was conceded that the plaintiff acted in good faith and the auditor found that the amount paid in settlement was fair and reasonable, and that it was not in excess of what it would have cost to comply with the conditions required by the interlocutory decree of January 10, 1914.
The judge rightly refused to rule that the final decree dismissing the bill was an adjudication that there was no encroachment upon the Szathmary land. But the ruling that the proceedings conclusively established the encroachment was erroneous. The opinion of this court in Szath-mary v. Boston & Albany Railroad, supra, however, is not a part of the record in that case, Snell v. Dwight, supra, and the interlocutory decree therein was vacated by the final decree dismissing the bill. But the portion of the opinion quoted by the trial judge and the interlocutory decree were admissible in this suit for their bearing upon the reasonableness of the settlement. See Hawks v. Truesdell, 99 Mass. 557, 559; Attorney General v. Armstrong, 231 Mass. 196, 202; Carere v. F. W. Woolworth Co. 259 Mass. 238. The instruction given, to which the defendant excepted, that “it was the duty of the defendant to defend the suit and to take the place of the railroad company,” was error. It was optional with the defendant whether it would appear and defend.
But .the defendant’s fifth, sixth "and seventh requests: “If the defendant constructed the retaining wall in accordance with the contract, plans, lines, stakes and directions furnished to it by the plaintiff or its engineers, inspectors and agents, the plaintiff is not entitled to recover in this action”; “If there was an encroachment upon the Szathmary land by the defendant in constructing the retaining wall in accordance with the provisions of its contract with the plaintiff, and such encroachment was due to the act or negligence of the plaintiff, the plaintiff is not entitled to
We have considered all the questions argued by counsel for the defendant and, for the reasons stated, the entry must be
Exceptions sustained.