23 N.Y.S. 998 | New York Court of Common Pleas | 1893
This action was brought against the defendant to recover upon two causes of action; the first being for the sum of $1,400, which the plaintiff claims the defendant agreed to pay for equipping his factory at Astoria, L. I. with its dry-pipe system of automatic sprinklers, under the terms of a contract between the parties dated September 19, 1889, and also for extra work, labor, and services on defendant's premises at Astoria to the amount of $123.69. The contract provided that the plaintiff should equip the factory in question in accordance with the rules and regulations of the New York Board of Fire Underwriters, and that the price of $1,400 should only be payable “after a certificate of approval shall have been issued by the New York Board of Fire Underwriters.” The plaintiff proved that all the work contemplated by the contract had been done; that the equipment was examined by Mr. Van G-iesen, the inspector of the Board of Fire Underwriters, frequently, both before and after the work was done,
The plaintiff itself, having made the condition precedent that the money for the contract work should not be payable until after a certificate of approval had been issued by the New York Board of Fire Underwriters, was bound by it, and could not maintain the action, as to that, unless it were arbitrarily or unreasonably refused by the board; but, if arbitrarily and unreasonably refused, then it could recover, notwithstanding such refusal. Highton v. Dessau, (Com. Pl. N. Y.) 19 N. Y. Supp. 395; Thomas v. Fleury, 26 N. Y. 33; Bowery Nat. Bank v. Mayor, etc., 63 N. Y. 339; Nolan v. Whitney, 88 N. Y. 650; Smith v. Alker, 102 N. Y. 90, 5 N. E. Rep. 791; Doll v. Noble, 116 N. Y. 232, 22 N. E. Rep. 406; Flaherty v. Miner, (N. Y. App.) 25 N. E. Rep. 418; Thomas v. Stewart, 132 N. Y. 580, 30 N. E. Rep. 577; Crouch v. Gutmann, 134 N. Y. 45, 31 N. E. Rep. 271.
In contemplation of the contract, the certificate ought to have been given when it was fully completed, provided there was no valid reason for the Board of Underwriters refusing the same. The fact that the pump was not of adequate capacity, and that there was no guaranty that steam would be maintained at all times to work it, were conditions over which the plaintiff had no control, and were fully within the control of the defendant, and therefore the refusal of the certificate on that ground would not have shielded the defendant from payment, because he could not take advantage of his own wrong, and thus defeat the payment of a just claim. We do not understand fully the second objection made ,by the board, which was in relation to there being no provision made to supply the pipes with water automatically. There is no sufficient evidence in the case to inform us on that point. The first objection may or may not have been a valid reason for withholding the certificate, according to circumstances and the rules of the Board of Fire Underwriters, which, from the evidence, appear to have been
We also think that the evidence of extra work done, and the authority for doing it, was sufficiently established to require the submission of that question of fact to the jury, and it was error to dismiss the complaint as to it. The judgment should therefore be reversed, and a new trial ordered, with costs to the appellant, to abide the event. All concur.