New Port Largo, Inc. (NPL) appeals the district judge’s rejection, after a bench trial, of the claims that Monroe County violated NPL’s rights under the takings clause and the “substantive” component of the Fourteenth Amendment’s due process clause. This case was before us on appeal previously. 1 Today, we affirm the district court’s rejection of NPL’s substantive claims.
I. Background
The facts of this case have been set out in earlier proceedings and will not be repeated here at length. 2 Instead, we present the following background relevant to our disposition of this case.
After the property was rezoned to PA, NPL brought suit in Florida state court in 1986, alleging that the procedures by which the property was rezoned were invalid according to the County’s Major Development Project Ordinance. NPL also contended that the rezoning was a taking and violated due process. NPL prevailed in the effort to invalidate the zoning (as NPL had prevailed in 1984 in a suit by the County contesting the ownership of the property). Here, NPL asserts that, while the title suit was pending, the property was illegally occupied by one LaLonde, the operator of a private airport. NPL contends that LaLonde held over beyond the end of his lease on the advice of the County, during which time he paid to the County, and the County accepted, continued payments for the use of the property. NPL now seeks to recover the value of the land during the time the regulation limiting its use was in effect.
NPL sued a number of defendants on a number of theories. Now, the only remaining defendant is Monroe County, against whom NPL asserts claims for a temporary taking of property in violation of the Fifth Amendment and a deprivation of due process in violation of 42 U.S.C. § 1983. After a bench trial, the district corut granted judgment in full to the County.
II. The Takings Issues
Plaintiff argues several substantive theories in support of its claim that its property has been taken without compensation in violation of the Fifth Amendment. NPL contends that Monroe County (1) effectively deprived NPL of the right to exclude others; (2) physically occupied NPL’s property; (3) deprived NPL of all economically viable uses of its property; and (4) induced NPL to rely in good faith on the existing zoning. We reject each of these contentions in turn. 3
A. Deprivation of the Right to Exclude
NPL argues that the County’s action constitutes a deprivation of the right to exclude.
See generally Kaiser Aetna v. United States,
The County’s act of rezoning the property to private airport was not, in itself, a deprivation of the right to exclude. NPL nowhere contends that, as a matter of law, the rezoning to private airport required it to admit the public. Because the property could have remained dormant, consistent with the PA zoning, NPL cannot argue that the rezoning was a deprivation of the right to exclude in the traditional sense.
Thus, NPL presses a more creative argument. In support of its theory that it was basically forced to invite the public onto its
The Rippley ease is unpersuasive as authority for this particular plaintiff for a number of reasons, but suffice it to say that the Rippley rezoning allowed only public uses (such as school, park, sewage treatment plant, and so on). There, the property would have yielded no revenue unless the City of Lincoln decided to purchase it. Id. at 508. Otherwise, the Rippley plaintiffs could use their property only by allowing the public access free of charge: all residential and commercial uses were prohibited. Id. Here, regardless of Plaintiff’s chances of ever turning a profit, see below Part II.B, Plaintiff remained free to transact some business, for profit, with the public at large. Thus, we reject the argument that the rezoning was a de facto condemnation. The reasoning of Rippley, even were we to conclude it is persuasive, does not require compensation here.
Plaintiff’s analogies to
Nollan v. California Coastal Comm’n,
B. The Physical Occupation
NPL alleges that the County “commandeered” the property by “conspiring” with LaLonde, the airport tenant, to ensure his continued occupation of the property beyond the expiration of his lease, and by accepting rents from LaLonde, thereby exercising dominion over property which was actually NPL’s. We conclude that NPL is, at this time, due no compensation on this “physical occupation” theory.
By now it is beyond question that a permanent physical occupation of private property by the state constitutes a taking for which a landowner must be compensated.
See Lucas v. South Carolina Coastal Council,
And, we decline now to address NPL’s variation on this theory: that the County effected a physical occupation by “conspiring” with LaLonde to ensure LaLonde’s continued presence on NPL’s land and receiving rents on that land.
4
Assuming that the takings clause would mandate com
C. Deprivation of All Economically Viable Uses
In addition to physical invasions of property, the Supreme Court has also accorded “categorical treatment,” invariably requiring compensation, to cases “where regulation denies all economically beneficial or productive use of land.”
Lucas,
We review the facts for clear error.
See Lucas,
NPL contends, however, that a factual finding by the judge in the state court action to invalidate the rezoning should have precluded relitigation of the economically viable uses issue in the federal district court.
5
“It is now well established that ... a federal court must give the same full faith and credit to the records and judicial proceedings of any state court that they would receive in the state from which they arise.”
Gjellum v. City of Birmingham,
Here, NPL has failed (at the least) to satisfy the “necessary and material” element of the issue preclusion analysis. The state court decided that Florida law offered no relief to the victims of temporary regulatory burdens imposed in good faith and that Monroe county did act in good faith.
See NPL I,
D. Good Faith Reliance
NPL argues that it acted “in good faith reliance upon the existing residential zoning,” and, therefore, the County was equitably estopped from rezoning the property to preclude residential development (or required to pay compensation if it did so rezone). NPL relies chiefly on
Wheeler v. City of Pleasant Grove,
NPL’s argument fails. Both
Wheeler
and AA
Profiles
contained a critical element that is missing from the facts of this case. In both cases, the local government took affirmative steps — by granting a permit or passing a specific resolution approving the project later precluded by rezoning — beyond the mere creation of the earlier zoning map. The panel in AA
Profiles
noted,
“Wheeler
is indistinguishable from this case. The original resolution [approving the project] granted appellant a property interest....”
Here, Plaintiff failed to allege any affirmative act by the County sufficient to grant a commensurate “property interest.” Plaintiff merely alleges that it paid a lot of money for property that the zoning plats indicated was suitable for residential development. That in itself is insufficient to invoke the rule of
Wheeler
and A.A.
Profiles. Cf.
A.A
Profiles,
NPL argues the property was so patently unsafe for use as an airport that the rezoning constituted a violation of their “substantive” rights under the due process clause.
8
To prove a due process violation, NPL must show that the rezoning was “clearly arbitrary and unreasonable, having no substantial relation to the public health, safety, morals, or general welfare.”
Village of Euclid v. Ambler Realty Co.,
Nothing clearly arbitrary and unreasonable has been shown about the zoning here. The record at trial established beyond question that, first, the properties in question were created for use as an airport (NPL’s counsel admitted as much at argument), and second, that the strip did in fact function as an airport for some time both before the rezoning (that is, the land’s historical use was as an airport) and after. Knowledge of these facts, which we presume the zoning entities to have had, is sufficient in itself for us to conclude that local officials violated no substantive due process right by the rezoning effort.
See South Gwinnett Venture v. Pruitt,
We note in addition that NPL’s argument — that the airport zoning was irrational because of safety concerns — refers only to the existing, not the possible, uses of the property as an airport. Appellants fail to press the assertion that no safe runway ever could be constructed on the property. For these reasons, judgment on the substantive due process claim was properly awarded to Defendants.
IV. The Jury Trial Issues
NPL contends that contested factual issues required the empaneling of a jury on both the Fifth Amendment takings claim and the Fourteenth Amendment substantive due process claim. We reject these arguments.
No jury trial was required for the substantive due process claim. This court addressed the division of labor between judge and jury on substantive due process claims for zoning cases in
Greenbriar, Ltd. v. City of Alabaster,
NPL, however, cannot complain here that material “subsidiary facts” were improperly decided by the judge, because there were no material facts in contention below. In substantive due process challenges to zoning laws, we recognize, as noted above:
A zoning commission is a quasi-legislative body.... Its actions are entitled to a presumption of validity. The only question which federal district courts may consider is whether the action of the zoning commission is arbitrary and capricious, having no substantial relation to the general welfare.
South Gwinnett Venture v. Pruitt,
On the regulatory takings claim NPL has asserted, but failed to support with any case, the proposition that subsidiary facts must be decided by a jury.
9
We have discovered no indication that the rule in regulatory takings cases differs from the general eminent domain framework, in which issues pertaining to whether a taking has occurred are for the court, while damages issues are the province of the jury. In
United States v. Reynolds,
Because the district court committed no reversible error, the judgment below is AFFIRMED.
Notes
. In
New Port Largo, Inc. v. Monroe County,
. For a fuller explanation of the facts, see
NPL I
and the opinion of the district court on remand, set out at
. We first note that this case, as we determined in the previous appeal, is ripe.
See NPL I,
. We note that the County operates — as an institution of government — through its legislative enactments, such as zoning. The act of "conspiring” with the private occupant of NPL’s land is not the kind of uniquely governmental act that underlies a takings claim, ordinarily at least. Therefore, we question whether acts of "conspiracy” by individual members of a zoning board are governmental acts, for takings purposes; we also doubt that the Fifth Amendment requires compensation for these acts. But, because of the ripeness concern set out in the text, we pass over these issues.
. The state court said that the "The only permitted use in said zoning district is a private airport. ... This rezoning of this property, now determined to be private, to airport, would deprive the owner of any reasonable use.”
. We note also that it is unclear from the state court opinion that the judge was even addressing the takings claim, and so it is doubtful that Plaintiffs could succeed in satisfying the "actually decided” element either. We need not conclusively resolve this issue, in view of the "necessary and material” analysis, but we note that in general a federal court will not confer preclusive effect on a state court order where it is unclear what the state court actually decided.
See Paine-Webber Inc. v. Farnam,
In addition, because we conclude the Florida courts would not accord preclusive effect, it is unnecessary to consider whether an exception to section 1738 would defeat the state law grant of preclusion.
See generally Marrese,
. Because we reject each of Plaintiff's takings arguments on the merits or on ripeness grounds, we need not discuss the contention that the district court erred in its calculation of the applicable takings period. Also, we need not address the controversy over the import of NPL's sale of the property in 1982 to its principals (in what NPL referred to at argument as a "business divorce”). See generally NPL I at 1490-91. The takings period allegedly lasted from 1980 (the rezoning) to 1986 (the invalidation of the rezoning). NPL was the owner during the earlier part of this period and, thus, has standing here. Perhaps the sale of the property could have shortened the takings period for NPL (and so reduced NPL’s potential damages), but we need not address this issue because we conclude that as a matter of law there was no violation of the Fifth Amendment and no damages are to be awarded.
. NPL apparently argued below that its procedural due process rights were violated, but makes no such argument here.
. In fact, counsel for NPL originally represented to the district court that “the issues relating to taking other than damages are for the Court. The damages issue is for the jury.”
