Fire destroyed a building in Ponce, Puerto Rico, that likely would have been demolished at the owner’s behest absent the fire. The insurance company refused to pay the policy amount, arguing that the owner lacked an insurable interest by virtue of the almost certain plans for demolition. The district court rejected that argument. We affirm on the basis that the owner had not abandoned the building pursuant to an “irrevocable commitment” to demolish it.
I.
Plaintiff The New Ponce Shopping Center (“New Ponce”) is a partnership that owns several commercial properties in Ponce, Puerto Rico. In 1985, New Ponce purchased the Santa Maria Shopping Center, all of which it renovated except for La Bolera Building: La Bolera was under a lease contract to Venancio Santos that would not expire until October 1992. Although Santos attempted to renew the contract, Aaron Sokol, New Ponce’s managing partner, refused— apparently because New Ponce intended to construct a high rise residential condominium building on the site. There is other evidence of New Ponce’s intent to demolish La Bolera at the end of the lease: preliminary permits had been sought and obtained from the proper government agency since September 1992; La Bolera obtained quotations from four persons to demolish the building; and Engineer Lombardo Pérez was engaged by New Ponce to obtain additional necessary permits.
After Santos’ lease ended in October 1992, La Bolera Building was not put to any purpose; rather, the building was broken into severаl times and became a hangout for “undesirables.” Wigberto Morales, General Manager of the shopping center, testified that he did not increase security at the building because he knew it was to be demolished. On January 15, 1993, Pérez submitted documents for permission to demolish La Bolera, including a letter signed by Sokol stating that dеmolition was urgent to avoid vandalism and crime; the letter also mentioned New Ponce’s intent to construct the condominium. Four days later on January 19, La Bolera was destroyed by fire. There is no question that prior to the fire New Ponce intended to proceed with its plans to demolish the budding.
La Bolera Building was insured by Dеfendant Integrand Assurance Company (“Integrand”) for up to $699,750 against, among other things, loss by fire. Integrand immediately hired Benjamin Acosta to investigate and adjust the fire loss. Acosta learned of the demolition plans through meetings with General Manager Morales and Engineer Pérez. It is apparent from Acosta’s subsequent correspondence with New Ponce that he believed New Ponce could change its demolition plans. In a letter to Morales, he stated that if “you decide to repair and/or reconstruct the affected structure, [Integrand] requires that you refrain from demolishing or removing any part of the same since [Integrand] would opt to order that the affected property be put into the same or better conditions than it was at the time of the fire.” The letter continued: “If you decide to proceed with the already projected demolition ..., [Integrand] will understand that it will be free of responsibility____” A fax sent to New Ponce’s insurance broker is to like effect. The fax also stated that, should New
Managing Partner Sokol met with Acosta on February 3, 1993. During that meeting, Sokol confirmed the demolition plans, but said that in light of the option exercised by Integrand, New Ponce had decided to reconstruct La Bolera Building. On February 9, Sokol sent the necessary plans and specifications to Acosta. Engineer Pérez and Integrand’s contractor discussed the scope of the reconstruction and agreed on the work that needed to be done; the parties exchanged correspondence regarding La Bolera’s reconstruction. Integrand’s contractor initially estimated the cost at $1,265,766 if the entire structure required replacement, plus $250,-000 to bring the structure up to code and $55,000 in salvage and demolition expenses. In а revised estimate, the contractor said he could reconstruct for $350,000 plus $200,000 for code compliance. Acosta then stated that New Ponce should pay $283,790 of the cost: $83,790 as a penalty for underinsurance and $200,000 for code compliance.
Sokol again met with Acosta and objected to thе cost figures. Unwavering, Acosta referred Sokol to Joaquin Castrillo, a senior vice-president at Integrand. Castrillo told Sokol that Integrand never exercised an option to rebuild La Bolera and did not intend to do so. He instead offered New Ponce $200,000, which Sokol immediately rejected. In a subsequent letter tо Sokol, Castrillo said that Integrand rejected responsibility under the insurance policy because Sokol misrepresented New Ponce’s plans to demolish La Bolera and withheld the existence of a contract for demolition and of permits for a future condominium.
New Ponce filed suit in district court on May 25, 1993, seeking compensation for the fire loss and damages. A bench trial was held in January and March of 1995. The presiding magistrate judge found in favor of New Ponce, and judgment was entered against Integrand for $594,787.50. That amount represents 80% of the amount of the insurance policy, less 15% pursuant to a vacancy clause in the рolicy. Integrand argues on appeal that it is not responsible for the loss since New Ponce was committed to demolishing the property prior to the fire. Integrand also contests the amount of damages.
II.
Both the district court and the parties fail to specify the jurisdiction that supplies the appliсable legal rules to this case. It is important to do so because a federal court sitting in diversity is not creating general federal common law. Even where the state or territory has no controlling authority, the federal court’s task is limited to predicting what the highest court of that state or territory would decide if рresented with the question.
Nieves v. University of Puerto Rico,
Thus our first task is to determine the controlling law. A federal court sitting in a diversity case must apply the choice of law rules of the forum state.
Klaxon Co. v. Stentor Elec. Mfg. Co.,
Integrand’s principal argument is that New Ponce did not have an insurable interest in La Bolera at the time of the fire because it planned to demolish the building and construct a condominium in its place. We have not uncovered, nor have the parties citеd to us, any applicable Puerto Rico law on the question of insurable interest in a similar context. Given the uniform approach taken in the few reported cases that have addressed the question, we conclude that the Supreme Court of Puerto Rico would adopt the approach of thоse courts.
The insured must have an insurable interest in a property before he may recover damages under an insurance policy for destruction of that property.
Chicago Title & Trust Co. v. United States Fidelity & Guar. Co.,
Several courts have applied the insurable interest requirement in cases where a building is destroyed prior to demolition. The leading case is
Garcy Corp. v. Home Ins. Co.,
A review of the cases decided both before and after
Garcy
will demonstrate that the “irrevocable commitment” requirement is not met in the present case. Mere evidence that the insured contemplated demolition and even took steps in that direction prior to loss does not change his insurable interest in the property. For example, in
American Ins. Co. v. Treasurer, Sch. Dist. No. 37,
Where courts have found no insurable interest, the facts revealеd a stronger commitment to demolition than present here. In
Woodruff v. Southeastern Fire Ins. Co.,
Even the most permissive cases require that the insured has entered a binding contract under circumstances making escape from the contract difficult or unlikely. For example, in
Royal Ins. Co. v. Sisters of Presentation,
[I]f the settled policy of the board of education, that it was legally bound to execute and the performance of which it had definitely entered upon, by the acts of the board itself, had eliminated the possible use of the ... building, they should not be indemnified against its loss to the extent of being paid by insurer its actual going value.
Id.,
In the
present case, there is ample evidence that New Ponce intended to demolish La Bolerа. The company had taken substantial steps in that direction prior to the fire: it had obtained preliminary permits from local authorities and obtained quotations for demolition. But neither these actions nor uneontested evidence of New Ponce’s actual intent to demolish La Bolera constitute an irrevocable commitment to do so. La Bolera was certainly not in the process of demolition when fire destroyed it, and New Ponce had not even entered into a binding contract
for
demolition. Under the reasoning of the cases cited above, New Ponce retained an insurable interest in La Bolerа on January 19, 1993, when it burned. Thus the district
Integrand also argues that the amount of damages awarded by the district court was not supported by the evidence. Integrand has not pointed to any evidence other than its assertion that New Ponce had no insurable interest to contest the court’s award, and we have already disposed of that contention. As the district court fully explained, it was presented with numerous appraisals as high as $1,265,700 for the cost of rebuilding and repairing La Bolera. It reasonably decided that the most objective figure, given the range of appraisals, was the amount of the insurance policy, $699,750, which it found to represent 80% of the value of the building. It then deducted 15% pursuant to a vacancy clause in the policy and entered judgment for $594,787.50. We find no error with the district court’s assessment of damages and Integrand has failed to demonstrate to this Court that the award was not supported by the evidence.
III.
Integrand’s remaining arguments do not merit discussion. For the foregoing reasons, the decision of the district court is AFFIRMED.
