New Orleans Channel 20, Inc. v. Federal Communications CommissionNew Orleans Channel 20, Inc. v. Federal Communications Commission
Opinion for the court filed by Circuit Judge BUCKLEY.
Appellants challenge an FCC decision terminating their right to construct and operate a new television station in New Orleans, Louisiana. The FCC awarded the construction permit in 1980. New Orleans Channel 20, Inc. (“NOC”) obtained the permit by assignment in 1983. As of 1985, construction had yet to begin. NOC sought to transfer the permit to LeSea Broadcasting, Inc. (“LeSea”), but the FCC rejected the proposed assignment. The Commission concluded that permit holder NOC had not made a “specific and detailed showing” that the failure to construct the station was due to causes beyond the permittee’s control.
Because the agency’s decision in this case was neither arbitrary or capricious, nor clearly contrary to a line of decisions in other cases, we affirm the FCC’s order and opinion.
I. Background
In October 1980, the FCC awarded the WULT-TY, Channel 20 construction permit to a joint venture known as New Orleans Area Telecasters (“NOAT”). The permit was to expire on April 10, 1982 according to the following terms:
[The permit] shall be automatically forfeited if the station is not ready for operation within the time specified or within such further time as the Commission may allow unless completion of the station is prevented by causes not under the control of the permittee.
Brief for Appellee at 3.
NOAT made absolutely no progress in starting construction. Ultimately, in March 1983, the FCC approved transfer of the permit to the NOC group, which was consummated in June 1983. Notwithstanding two extensions, NOC failed even to begin construction. Consequently, in May 1984, NOC submitted a letter stating that due to the “drain” on its “time and resources” and its “lack of success in finding a suitable [transmitter] site,” it had decided to assign the permit to a better qualified entity, anticipating the assignment application to be filed before May 81, 1984. Joint Appendix (“J.A.”) at 76-77.
Two months later, on July 10,1984, NOC filed its third extension request (the appli
In supplemental filings on December 13, 1984, J.A. at 122, and January 15, 1985, J.A. at 119, LeSea by letter represented that it had actually secured the transmitter site and would soon file an application to modify Channel 20’s permit, placed a contingent $2.5 million equipment order, located a suitable studio site, reached agreements in principle for the station’s Operations Manager and Chief Engineer, and estimated that it would commence operation 210 days following acquisition of the permit. The FCC emphasizes that “[n]o documents were provided by LeSea to support these claims.” Brief for Appellee at 10.
On June 4, 1985, the Commission’s Mass Media Bureau denied NOC’s extension request and, in addition, cancelled the construction permit, deleted the WULT call sign, and dismissed the assignment application as moot.
New Orleans Channel 20, Inc.,
NOC and LeSea appealed to the Commission. The agency rule applicable to NOC’s extension request, though subsequently modified, read in pertinent part:
[An application for extension of construction permit] will be granted upon a specific and detailed showing that the failure to complete was due to causes not under the control of the grantee, or upon a specific and detailed showing of other matters sufficient to justify the extension.
On the first count — NOC’s failure to complete — the Commission concluded that business considerations, not causes beyond NOC's control, explained the inaction:
[NOC’s] continued lack of [a] site was not attributable to the actual, physical unavailability of potential transmitter sites, but to Glazer’s [Mutual’s principal] business decisions to reject sites as undesirable or too expensive and his failure to reach agreements with owners of potential sites____ [Glazer’s] statements detail various business judgments made by [him] in rejecting sites on which WULTTV’s transmitter could have been constructed.
Thus the disposition of this case turns on the FCC’s evaluation of LeSea’s qualifications. Appellants argued that the pendency of the assignment application was an “other matter[ ]” warranting the extension. The FCC catalogued the representations made by LeSea but concluded that the proposed assignee had “provided no information to demonstrate the firmness of [the equipment] order” and no “information to show that its putative transmitter or studio
Assignment of the permit likely would not result in the expeditious construction and operation of WULT-TV, or contribute to an overall environment in which construction permit holders are encouraged to make and fulfill realistic commitments, thereby bringing service to the public at the earliest possible date. In such a situation, it is preferable to cancel the authorization, thereby opening the door for other qualified applicants.
Id.
The Commission rejected appellants’ equal treatment claim by distinguishing on the facts the grant of extensions for new television construction in Tulsa, Oklahoma and Kalamazoo, Michigan and the restoration of broadcast service for a licensed station in Crossville, Tennessee. Appellants claim the factual distinctions articulated by the FCC are illusory.
II. Discussion
We base our analysis of the FCC’s denial of the extension and cancellation of the station’s call letters on a two-step inquiry. First, did LeSea make
“a specific and detailed showing
of other matters sufficient to justify the extension”?
An applicant for waiver [of FCC rules] faces a high hurdle even at the starting gate____ On its appeal to this court, the burden on [the permit holder] is even heavier. It must show that the Commission’s reasons for declining to grant the waiver were so insubstantial as to render that denial an abuse of discretion.
In this case, the regulation requires a petitioner to overcome a high initial hurdle by requiring “a specific and detailed showing.” The showing made by LeSea consisted of representations made in four brief documents: NOC’s initial recitation of the unnamed assignee’s undertakings, J.A. at 82; a two-page sworn statement submitted by Sumrall in August, J.A. at 84-85; his two-page December follow-up, J.A. at 123-24; and NOC’s brief two-paragraph recital in January on LeSea’s behalf, J.A. at 119. In addition, LeSea submitted the engineering specifications for a new transmitter site on FCC Form 301, J.A. at 97-118.
The central deficiency of these filings, as noted by the FCC, is the absence of specificity.
Appellants also claim, and rightfully so, that their representations cannot be discredited by association with NOC’s abysmal record.
See New Television Corp.,
Appellants next argue that they have been denied the same treatment accorded three similarly situated parties who have successfully sought an extension. We reject this argument. The FCC distinguishes these cases on their facts; and at least as to Tulsa and Crossville, we agree that the differences are not trivial. More important, the theory of comparable treatment advanced by appellants would strip the FCC of any flexibility to bring its informed discretion to bear in resolving close cases and accommodating special circumstances. When every exception becomes a rule, administrative rigor mortis sets in.
According to the FCC, in Tulsa, the distinguishing fact was that “alternative transmitter sites were promptly procured, equipment was ordered and construction was proceeding.”
In Crossville, the application dealt with a licensed station not currently broadcasting, but where the
“bona fide
concern to restore ... service had been shown____”
Id.
at 316. In addition, documentary evidence supported the conclusion that the assignee “would proceed diligently with presumption of broadcast operations and complete construction of the station’s proposed permanent facility.” Brief for Appellee at 16 (citation omitted). The FCC also noted that as the Crossville station was licensed, “the failure to construct ... modified facilities would not free the channel for application by other parties.”
In Kalamazoo, the assignee pledged “to construct the station by a fixed date, provided a construction schedule, ordered equipment and placed a substantial down payment on that equipment.”
In arguing that the grant of extension by the FCC in three factually distinguishable cases establishes a baseline for mandatory agency treatment, appellants rely principally on
Melody Music, Inc. v. FCC,
Appellants also cite approvingly to
Garrett v. FCC,
We affirm the standard, but find that it does not extend to the present case and transform isolated grants of construction permit extensions into a rule binding on the agency. Melody Music and its progeny appropriately recognize the importance of treating parties alike when they participate in the same event or when the agency vacillates without reason in its application of a statute or the implementing regulations. But this proposition is distinguishable from the present case, involving as it does a routine request for an extension and an agency denial issued in full conformity with the FCC’s procedural and substantive obligations. No precedent can be cited that has been inexplicably ignored, as in Garrett. The basic transaction is not identical, as in Melody Music. No other special circumstances compel us to augment the WAIT Radio analysis with considerations of unequal treatment.
It bears emphasizing that any party denied a waiver feels aggrieved, but so long as the agency does not display evident disregard for its precedents, no violation occurs. Appellants’ theory would paralyze agency discretion to deal with waiver and extension requests on a case-by-case basis.
WAIT Radio [I] accurately states the pertinent obligations placed upon the agency. Waiver requests constitute “an important member of the family of administrative procedures.” Id. The general obligation of reasoned decisionmaking applies where the party has presented an application “stated with clarity and accompanied by supporting data.” Id. at 1157. As a consequence, “[t]he agency may not act out of unbridled discretion or whim in granting waivers____,” id. at 1159, though it “need not sift pleadings and documents to identify such applications.” Id. at 1157. Furthermore, “[e]ven when an application complies with these rigorous requirements, the agency is not required to author an essay for the disposition of each application. It suffices, in the usual case, that we can discern the why and wherefore.” Id. at 1157 n. 9 (internal citations omitted). Here the FCC subjected appellants’ application to a hard look and, on the merits, found that LeSea failed to submit sufficiently specific information. The inadequacies in LeSea’s submission preclude a finding by the court that the FCC abused its discretion.
III. Conclusion
LeSea failed to submit “specific and detailed” evidence of its commitment to construct Channel 20 in New Orleans, and certainly failed to demonstrate that the FCC’s evaluation of the request for an extension of time was an abuse of agency discretion. The FCC adequately explained its reasoning. The agency did not act contrary to its precedent. Accordingly, the FCC’s order is
Affirmed.