The opinion of the Court was delivered by
This appeal concerns the doctrine of “nullum tempus occurrit regi ” (nо time runs against the king). The question here is whether a general statute of limitations runs against today's sovereign, the State (or one of its agencies), when it asserts a claim in contract. We agree with the Appellate Division that no difference in principle can be found to warrant departure from the general rule in the context of a suit brought by the New Jersey Educational Facilities Authority (NJEFA) and Jersey City State College (JCSC) seeking to redress defective design and construction of a student-center building. The activities performed by NJEFA and JCSC were governmental in nature *69 and the two agencies arе sufficiently identified with the State to warrant application of the doctrine.
However, we believe that despite its different evolution, the doctrine of nullum tempus is but an aspect of sovereign immunity. This Court has previously determined that the doctrine of sovereign or governmental immunity, in the areas of the State’s tort and contract liability, does not accord with notions of fundamental justice applicable to our elected representative form of government. Willis v. Department of Conservation and Economic Dev., 55 N.J. 534, 264 A.2d 34 (1970); P T & L Constr. Co. v. Commissioner, Dep’t of Transp., 55 N.J. 341, 262 A.2d 195 (1970). Because its abolition represented such a clean break with the past, the Court decided that the doctrine would be abolished prospectively, leaving the Legislature ample opportunity to step into the field. The Legislature responded by enacting the Tort Claims Act, N.J.S.A. 59:1-1 to :12-3, and the Contractual Liability Act, N.J.S.A. 59:13-1 to - 10.
Having yielded the greatest aspect of sovereign immunity, immunity from any suit at all, it would be anomalous in the extreme not to conclude that the sovereign who can now be sued should not have to bring its own suit in a timely manner.
Hence, consistent with Willis and P T & L Construction Co., we abrogate the immunity doctrine of nullum tempus insofar as it applies to immunity of the State or its agencies from the application of statutes of limitations in contractual matters. To avoid disruptions of governmental fiscal affairs currently positioned on the continued existence of the doctrine, we make our decision effective December 31, 1991. We commend the matter to the consideration of the Legislature for any modification of this disposition in light of the special needs of governmental agencies.
I
We need not engage in an extended discussion of the merits of the application of the common-law doctrine of
nullum tern-
*70
pus
to the circumstances of this case. The facts and legal principles of decision are well set forth in the reported opinion of the Appellate Division.
New Jersey Educ. Facilities Auth. v. Conditioning Co.,
237
N.J.Super.
310,
Assuming the validity of nullum tempus, we are fully in accord with the Appellate Division’s conclusions on the application of the doctrine to the circumstances of this case. The pivotal issue, of course, is whether the doctrine оf nullum tempus applies to NJEFA and to JCSC. The question arises in the context of a multi-million dollar construction contract to build a student center for JCSC at its campus in Hudson County, New Jersey. NJEFA financed the project and arranged for the construction of the facility through the Division of Building and Construction (DBC) of the State’s Treasury Department. The DBC engaged the Gruzen Partnership as the architects for the project and the Cerami Construction Company as the general contractor. The building was defective in several respects and NJEFA, later joined by JCSC, brought this suit for damages.
The sub-questions for decision are whethеr the subordinate State agencies involved were acting in a governmental rather than a proprietary capacity and whether those agencies were entitled to the same protection as the State itself would be.
See New Jersey Higher Educ. Assistance Auth. v. Carlock,
247
N.J.Super.
471,
On the first point, the Appellate Division concluded, and we agree, that the function involved is governmental. 237
N.J.Super.
at 318,
The history of the agency and its ability to engage in those activities, even in the case of private institutions, is well set forth in
Clayton v. Kervick,
52
N.J.
138,
As to the second question, whether
nullum tempus
should be applied only to the State itself and not to these agencies, we see no reason for that limitation in the circumstances of this ease. In its origin, NJEFA was deemed to be a “political subdivision оf the state established as an instrumentality exercising public and essential governmental functions.”
N.J.S.A.
18A:72A-4(a). In its operation, NJEFA functions as “an arm of state government * * * entitled to assert the doctrine of
nullum tempus.” State v. Scientific Coating Co.,
228
N.J.Super.
320, 324,
In its enabling legislation, NJEFA was given the power “[t]o sue and be sued.”
N.J.S.A.
18A:72A-5(d). Interpreting the enabling statutes of other State agencies, some courts have found that the presence of similar language indicated a legislative intent to waive common-law immunities for those agencies.
See, e.g., Frank Briscoe Co. v. Rutgers,
130
N.J.Super.
493,
In addition, we see no reason why JCSC should not be considered a State agency for this purpose. We recognize that a State university is not considеred the State for all purposes. In
Fuchilla v. Layman,
109
N.J.
319,
II
On the more fundamental question of the continued existence of the doctrine, we agree with the reasons for its demise that are cogently stated in defendant Gruzen’s brief to the Appellate Division. The doctrine of
nullum tempus
is not found in any statute, “nor does it spring from any constitutional provision.” It is strictly a creature of the common law.
Nullum tempus
originated “as one of the royal prerogatives, justified on the ground that the king was too busy lоoking after the welfare of his subjects to sue.”
Developments in the
*75
Law
— Statutes
of Limitations,
63
Harv.L.Rev.
1177, 1251 (1950). But our courts have recognized that although the doctrine “had an identity of its own,” it is “related to the doctrine of sovereign immunity which exempts an entity from suit. As a matter of logic it would seem that an entity which is not protected from suit by sovereign immunity would also not bе entitled to benefit from
nullum tempus.” Board of Trustees v. J.P. Fyfe, Inc., supra,
188
N.J.Super.
at 293, 457
A.2d
83. Defendant Gruzen correctly identifies the doctrine as one of the “legal relics” that should be included among the numerous other immunities that have been abrogated or curtailed by the Court.
See Merenoff v. Merenoff
76
N.J.
535, 547-48,
The policy argument that is advanced in suрport of the continued existence of the doctrine is that society must be protected from the inefficiencies of its public servants. Thus, if a statute of limitations has run on a valid State claim, the public should not have to suffer by reason of the neglect of a governmental employeе. However, that argument would serve as well to reinstate the doctrine of governmental immunity from all claims. If the State has immunity when its employee forgets a deadline for the filing of a claim, then why should the State not have immunity when its employee forgets to engage the emergency brake of a truck, allowing the truck to drive into another’s living room? After all, the public in both instances pays the price for the employee’s neglect. In the context of tort law, we decided that the common law should no longer refuse the citizen a remedy, leaving the Legislature to decide the dimensions of the right.
Willis, supra,
55
N.J.
534,
*76 But we must make this ruling prospective. Whatever may be the weaknesses of the doctrine, it has apparently never been abrogated by judicial decision in this State. Defendant Gruzen argues that the State did not in any sense rely on the doctrine, pointing out that the Director of the DBC wrote to an Assistant Attorney General suggesting that a complaint “should be filed now to beat the statute of limitations.” Yet that does not detract from the fact that retroactive abolition of nullum tempus would constitute a clean break with the past and would expose the government to unanticipated loss of claims in cases yet to be subjected to the specific factual record that this case has. In Devins v. Borough of Bogota, 124 N.J. 570, 592 A.2d 199 (1991), we applied our ruling to the plaintiffs and made it prospective to all others. But that reflects the special nature of such claims of land title. In the case of adverse possession of land, the limitation period serves as well to confirm the rightness of the underlying claim as it does to avoid suits. 3 American Law of Property § 15.2 (1952). That same sense of the rightness of the claim of one in possession of land for twenty or thirty years does not extend to the underlying controversy here.
Hence, we believe that the fairest course to all is to adhere to the principles of decision that this Court established in Willis and P T & L Construction Co. The doctrine of nullum tempus is abrogated with respect to the State or its agencies insofar as it would preclude the aрplication of general statutes of limitations to the State. This decision shall not be effective or applicable to claims made by the State or its agencies prior to December 31, 1991. As for all claims made thereafter, the doctrine of nullum tempus shall not serve to excuse the Statе from compliance with statutes of limitations on such contractual claims, except to the extent otherwise provided by statute. In all other respects, the judgment of the Appellate Division is affirmed. Our ruling is subject in all aspects to any action of the Legislature.
*77 For affirmance in part and reversal in part — Chief Justice WILENTZ, and Justices CLIFFORD, HANDLER, POLLOCK, O’HERN, GARIBALDI and STEIN — 7.
Opposed — None.
