53 Conn. App. 771 | Conn. App. Ct. | 1999
Opinion
The defendants, Empire Paving, Inc. (Empire), and its bonding company, American Insurance Company, doing business as Fireman’s Fund Insurance Company (Fireman’s Fund), appeal from the judgment of the trial court awarding damages to the named plaintiff, New England Rock Services, Inc. (Rock Services),
The following facts are relevant to the disposition of this appeal. On October 26,1995, Empire entered into a contract with Rock Services under which Rock Services would provide drilling and blasting services as a subcontractor on the Niles Hill Road sewer project on which Empire was the general contractor and the city of New London was the owner.
On October 31, 1995, Rock Services commenced work on the project. From the beginning, Rock Services experienced a number of problems with the project. The primary obstacle was the presence of a heavy concentration of water on the site. The water problem hindered Rock Services’ ability to complete its work as anticipated. The trial court found that it was the custom and practice in the industry for the general contractor to control the water on the site and that, on this particular job, Empire failed to control the water on the site properly. In an effort to mitigate the water problem, Rock Services attempted to “load behind the drill,” a process that allows a blaster to load the drilled hole with a charge immediately after the hole is drilled, before water has the opportunity to seep into the hole. The city fire marshal, however, refused to allow Rock Services to employ this method of drilling. See Regs., Conn. State Agencies § 29-349-238.
In late November, 1995, Rock Services advised Empire that it would be unable to complete the work as anticipated because of the conditions at the site and
Upon completion of the work, Empire refused to pay Rock Services for the remaining balance due on the time and materials agreement in the amount of $58,686.63,
On appeal, Empire claims that the trial court improperly found that the later purchase order was a valid and enforceable modification of the earlier contract. Specifically, Empire claims that the later agreement
“As an appellate court, our review of trial court decisions is limited to determining whether their legal conclusions are legally and logically correct, [and] supported by facts set out in the memorandum of decision. Pandolphe’s Auto Parts, Inc. v. Manchester, 181 Conn. 217, 221-22, 435 A.2d 24 (1980).”Harris Calorific Sales Co. v. Manifold Systems, Inc., 18 Conn. App. 559, 563, 559 A.2d 241 (1989). Whether a contract or a subsequent modification exists is a question of fact for the court to determine. Id.; see also Three S. Development Co. v. Santore, 193 Conn. 174, 177-78, 474 A.2d 795 (1984); Randolph Construction Co. v. Kings East Carp., 165 Conn. 269, 277, 334 A.2d 464 (1973); Thermoglaze, Inc. v. Morningside Gardens Co., 23 Conn. App. 741, 745, 583 A.2d 1331, cert. denied, 217 Conn. 811, 587 A.2d 153 (1991). “If the factual basis of the court’s decision is challenged, our review includes determining whether the facts set out in the memorandum of decision are supported by the evidence or whether, in light of the evidence and the pleadings in the whole record, those facts are clearly erroneous.” (Internal quotation marks omitted.) Harris Calorific Sales Co. v. Manifold Systems, Inc., supra, 563.
In concluding that the modification was valid and enforceable, the trial court determined that the later agreement was supported by sufficient consideration. The trial court relied on Harris Calorific Sales Co. v. Manifold Systems, Inc., supra, 18 Conn. App. 564, to support its determination that the parties’ mutual promises were sufficient consideration to bind them to the
“The doctrine of consideration is fundamental in the law of contracts, the general rule being that in the absence of consideration an executory promise is unenforceable.” State National Bank v. Dick, 164 Conn. 523, 529, 325 A.2d 235 (1973). While mutual promises may be sufficient consideration to bind parties to a modification; Harris Calorific Sales Co. v. Manifold Systems, Inc., supra, 18 Conn. App. 564-65; Gordon v. Indusco Management Corp., 164 Conn. 262, 267-68, 320 A.2d 811 (1973); Taft Realty Corp. v. Yorkhaven Enterprises, Inc., 146 Conn. 338, 342, 150 A.2d 597 (1959); a promise to do that which one is already bound by his contract to do is not sufficient consideration to support an additional promise by the other party to the contract. Thermoglaze, Inc. v. Morningside Gardens Co., supra, 23 Conn. App. 744-46.
“A modification of an agreement must be supported by valid consideration and requires a party to do, or promise to do, something further than, or different from, that which he is already bound to do. [State National Bank v. Dick, supra, 164 Conn. 529]; Dahl v. Edwin Moss & Son, Inc., 136 Conn. 147, 155, 69 A.2d 562 (1949); Simone v. Kirschner, 100 Conn. 427, 429, 124 A. 20 (1924). It is an accepted principle of law in this state that when a party agrees to perform an obligation for another to whom that obligation is already owed, although for lesser remuneration, the second agreement does not constitute a valid, binding
Our Supreme Court in Blakeslee v. Board of Water Commissioners, supra, 106 Conn. 656, however, articulated an exception to the preexisting duty rule: “ ‘[W]here a contract must be performed under burdensome conditions not anticipated, and not within the contemplation of the parties at the time when the contract was made, and the promisee measures up to the right standard of honesty and fair dealing, and agrees, in view of the changed conditions, to pay what is then reasonable, just, and fair, such new contract is not without consideration within the meaning of that term, either in law or in equity.’ ” As to the test to be applied in such a situation, our Supreme Court in Blakeslee quoted with approval the Supreme Court of Minnesota in King v. Duluth, Missabe & Northern Ry. Co., 61 Minn. 482, 488, 63 N.W. 1105 (1895): “ ‘What unforeseen difficulties and burdens will make a party’s refusal to go forward with his contract equitable, so as to take the case out of the general rule and bring it within the exception, must depend upon the facts of each particular case. They must be substantial, unforeseen,
Empire argues strenuously that the water conditions on the site cannot qualify as a new circumstance that was not anticipated at the time the original contract was signed. To support its contention, Empire points to the contract documents prepared for the city of New London, which contained all the job specifications. Empire asserts that those job specifications were incorporated by reference into Rock Services’ subcontract agreement. Empire claims that the job specifications “set out all the known site conditions” and “included specific information that the rock ledge that [Rock Services] was to drill and blast existed below the known water table.” Empire claims, therefore, that Rock Services was not confronted with any new circumstances not specifically contemplated when their contract was made.
Empire’s argument, however, is misplaced. Rock Services does not argue that it was unaware of the water conditions on the site but, rather, that Empire’s failure to control or remove the water on the site constituted the new or changed circumstance. Rock Services argues
In its memorandum of decision, the trial court found that Empire had a duty to control or remove the water from the job site according to the custom and practice in the industry and project specifications.
Empire is correct to point out that the language of the contract is silent and by itself does not give rise to
In addition to finding that Empire had a duty to control or remove the water from the job site, the trial court found further that Empire’s failure to control or remove the water from the site made Rock Services’ working conditions sufficiently burdensome to prevent Rock Services from completing the work as anticipated, forcing Rock Services to attempt to use a different method of drilling and ultimately compelling Rock Services to use the more costly and time consuming method of casing the blasting hole. The trial court further found that Empire’s failure to control or remove the water on the site constituted a new circumstance not anticipated by the parties at the time the original contract was signed. In addition, the trial court also found that Rock Services’ request for the modification was not wrongful but, rather, was justified under the circumstances and did not constitute duress as a matter of law.
Upon our review of the record, we conclude that the trial court’s findings of fact are supported by the record and are not clearly erroneous. On the basis of the trial court’s findings, as supported by the record, we conclude that the later purchase order was a valid and enforceable modification to the earlier contract.
The judgment is affirmed.
In this opinion the other judges concurred.
Western Mass. Blasting Corporation, a subcontractor of Rock Services on the project and an original plaintiff in this case, withdrew its claims prior to trial.
Fireman’s Fund executed a labor and materials bond in connection with the Niles Hill Road project, pursuant to which Fireman’s Fund was obligated to pay all contractors and subcontractors who performed work on, or pro
Section 29-349-238 of the Regulations of Connecticut State Agencies provides: “No loading operation shall be conducted within 25 feet of a drilling operation.”
Empire did pay Rock Services a portion of the balance invoiced by calculating the amount of rock removed from the site at $29 per cubic yard and deducting various setoffs.
Alternatively, the trial court concluded that Rock Services had also proven its claim of promissory estoppel, finding that Rock Services had completed the project in reliance on Empire’s promise to pay on a time and materials basis.
Because it found that Rock Services had satisfied the procedural prerequisites for a valid bond claim, including notice to the surety, the trial court also concluded that Fireman’s Fund breached its obligation to pay on the bond pursuant to General Statutes § 49-41 et seq.
Because we conclude that the later agreement was a valid and enforceable modification, we need not reach Empire’s other claim that the trial court improperly concluded that Rock Services had also proven its claim of promissory estoppel.
The trial court heard testimony from John Gilman, a representative of Rock Services with over thirty years experience in the blasting trade, that it was the custom and practice in the industry for the general contractor to control the water on the job site, and that water could almost always be controlled by the general contractor through the use of pumps, sumps and well points. Representatives from Empire testified conversely that Empire had never been obligated to remove water from a job site for a predrilling operation. “Where there is conflicting evidence ... we do not retry the facts or pass upon the credibility of the witnesses.” (Internal quotation marks omitted.) Emhart Industries, Inc. v. Amalgamated Local Union 376, U.A.W, 190 Conn. 371, 404, 461 A.2d 422 (1983). The probative force of conflicting evidence is for the trier to determine. Bowman v. 1477 Central Avenue Apartments, Inc., 203 Conn. 246, 257, 524 A.2d 610 (1987). “In a case tried before a court,, the trial judge is the sole arbiter of the credibility of the witnesses and the weight, to be given specific testimony.” (Internal quotation marks omitted.) Steiger v. J. S. Builders, Inc., 39 Conn. App. 32, 34-35, 663 A.2d 432 (1995). “The trier is free to accept or reject, in whole or in part, the testimony offered by either party.” Smith v. Smith, 183 Conn. 121, 123, 438 A.2d 842 (1981).
Section 222 of the Restatement (Second), Contracts (1981), provides in relevant part: “(1) A usage of trade is a usage having such regularity of observance in a place, vocation, or trade as to justify an expectation that it will be observed with respect to a particular agreement. ... (2) The existence and scope of a usage of trade are to be determined as questions of fact. ... (3) Unless otherwise agreed, a usage of trade in the vocation or trade in which the parties are engaged or a usage of trade of which they know or have reason to know gives meaning to or supplements or qualifies their agreement.”