188 Mo. App. 467 | Mo. Ct. App. | 1915
This is a suit against the sureties alone on a builder’s bond, for damages accrued through a breach of the building contract. Plaintiffs recovered and defendants prosecute the appeal.
Plaintiff Ladislaus Neuwirth is the pastor and his coplaintiffs are trustees of the Roman Catholic Slovak Church of the Holy Trinity in, St. Louis, and defendants,- Moydell and Piskulic, are sureties on the contractor’s bond. It appears that the church, desiring to erect a parish school building on the south side of
Among other things, the building contract makes the plans and specifications for the building parcel thereof, and the bond is conditioned for the faithful performance of the contract. Defendants, in their answer, set forth numerous changes and alterations in the construction of the building, which were made without regard to the provisions of the contract and at variance from' the specifications, without their knowledge or consent, and assert that they are discharged as sureties because of these. It is entirely clear that,' while all of the matters and things set forth in the answer as changes going to destroy the identity of the contract may not be regarded as such, others do so. All of those changes are detailed in,plaintiff’s evidence and stand conceded in the case, in that the parish priest, Reverend Ladislaus Neuwirth, who, it appears, was the active agent of plaintiffs, frankly testified to each.
The building contemplated is a two-story-and-basement brick school building, and the contract includes, too, the repair of certain sidewalks about it. It appears that, while the building was in course of construction, a city inspector interposed an objection to the sufficiency of one of the walls. Because of this, plaintiff entered into a new and independent contract with Harik, the builder, to erect a fire wall adjacent
Then, too, the plans and specifications called for plastered ceilings in the school building, and it appears the contractor put in two of the classrooms downstairs corrugated iron ceilings instead. However, he did this voluntarily and without any agreement or request from plaintiffs to do so.
The plans and specifications required the builder, Harik, to repair the old sidewalk and such was parcel of the contract; but, instead, after the work was in progress, plaintiffs entered into a new agreement with Harik, whereby a concrete sidewalk was substituted, at the agreed price of $125', which was paid. Touching this matter, Father Neuwirth testified: “Instead of having the sidewalk repaired, I had the brick sidewalk torn up and had a granitoid sidewalk made.”
Another change in the terms of the original contract, made by agreement between plaintiffs and the builder, pertains to the lathing of a partition on the first floor of the building. Concerning this the parish priest testifies as follows: “On the north side of that hall between it and the classrooms is a partition. This partition was made fireproof with metal lath and studding. . According tp the specifications that was to be ordinary wooden studding and plastering and wooden laths. Mr. Harik didn’t pay for the change in that partition; I paid for it. The money was received by one of the old-time parishioners who did the work; Harik’s plasterers did the plastering and Harik’s car-' penters put in the partition and lath. The metal lath and metal studding for that partition were furnished by John Nitka, a parishioner. I paid seventy-five dollars for the metal laths and studding.” It appears from this that plaintiffs substituted the metal lath and studding at an expense of seventy-five dollars, with the
On the second floor of the building a partition was changed—that is, moved eastward about three feet— and thus-varied from the specifications, in order to make the room on the second floor at the head of the stairs larger. In this connection, also, a double door called for in the specifications between a large room called a hall and a room at the head of the stairs was changed to a single door of the same shape as the small doors downstairs. These changes plaintiffs says were done by agreement with the builder and at a cost of five dollars.
In the original plans a door was designed on the first floor, opening into the back of the church, but when the fire wall was constructed, a change was made with respect to this. However, no charge was made for this change.
Father Neuwirth also testifies that two doors were put in, one upstairs and one downstairs, different from those mentioned in the specifications, and “ Harik charged eight dollars for changing or constructing each of these doors. I paid him for it. . . . One of these doors is entering from a room to the classroom. The other door opened from the lower classroom to the yard on the east side of the building, so that in case the fire would come, that the children could go out fast enough to save their lives.”
The building contract provided in substance that the superintendent shall be at liberty to make any deviations from or alteration in the plan and construction of the building; but this provision is limited by another in the bond executed by the sureties.
The condition of the bond is as follows:
“The condition of the above obligation is such, that, whereas, the said Stephen Harik has on the day of the date of these presents executed and entered into a certain contract for the erection of certain build*476 ings in said contract described, which contract is hereto annexed. Now, if the said Stephen tlarik shall well and trnely perform and fulfill all and every the covenants, conditions, stipulations and agreements in said contract mentioned to be performed and fulfilled, and any alterations and additions in said contract, provided such alterations and additions, if any such be made, shall not exceed in extra costs the sum of eight and 00-100 dollars ($8).
“We, the said sureties, hereby expressly waiving all rights to be notified of, or by any further act to give our assent to, such alterations and additions and acknowledging ourselves to be bound unconditionally for the faithful performance of said contract price and of such alterations and additions within limit of said contract price and of such extra costs aforesaid, and shall keep the said Rev. Ladislaus Neuwirth, pastor, and John Palubiak, Andró Spavor and J. P. Gabries, trustees, of the Roman Catholic Slovak Church of the Holy Trinity, harmless and indemnified from and against all and every claim, demand, judgments, liens and mechanics ’ liens, costs, etc. ’ ’
The case concedes that defendants’ sureties on the bond were in nowise notified with respect to the several changes and variations from the original specifications and plans of construction detailed in the contract and that such changes were made between the original parties to the building contract without their knowledge or consent. Because of this, it is urged the sureties are discharged, and it is entirely clear that this argument must prevail. It is undoubted that there is no implied obligation on the part of the surety that he has undertaken more or other than that expressed in his contract, for it is only to the extent and in the manner and under the circumstances pointed out in the contract to which he has become a party that he is bound, and not further. Therefore, if the original parties to the contract make changes or alterations
Bhit the principle is without avail in so far as the fire wall above referred to it concerned. The fire wall that was built at the instance of the'city inspector is to be put aside entirely, because it stands on the ground of a separate, independent contract subsequently made, which in nowise varied the terms or tended to destroy the identity of the original contract for which the sureties stood sponsor. The original contract between the parties did not contemplate nor refer in any manner to the fire wall. There was no variation from the plans or specifications in so far as this matter is concerned. The city authorities required an additional wall to be installed adjacent to the old church building and plaintiffs contracted with the builder to erect it for the price of fifty-six dollars. This was a new and independent contract subsequently made, though it was between the same parties and on the same property. As said in Beers v. Wolf, 116 Mo. 179, 187, 22 S. W. 620, “A subsequent independent agreement of the principal, to do other and different work for the same person, would not discharge the surety; because in such case the contract of the surety would remain the same. ’ ’ In other
Touching the matter of the installation of the two corrugated iron ceilings in the first-story rooms of the school building, it is to be said, too, that no discharge of the sureties may be predicated on this. There was no variation of the original contract by any act of plaintiff in so far as this subject-matter was concerned. It is true the original contract and specifications call for plastered ceilings, but plaintiff was in nowise instrumental in varying that term or in substituting something other therefor. The contractor, of his own volition installed the corrugated iron ceilings instead, without a request therefor or an agreement on the part of plaintiff and made no extra charge concerning the same. "While this obviously reveals a breach of the contract on the part of the contractor for which plaintiffs might pursue him and the sureties, too, at law, if they chose to do so, it in nowise operates a change of the original contract through the co-operation as by agreement of the parties. [See Snoqualmi Realty Co. v. Moynihan, 179 Mo. 629, 647, 78 S. W. 1014.]
It is entirely clear that these changes, though they were paid for at the time as extras, destroyed the identiy of the contract and thereby discharged the sureties. Each of these changes last enumerated substituted something different and distinct for that stipulated for between the parties in the contract and in this the contract was so changed as to destroy its identity, and this, too, without the consent of the sureties, for they consented to such changes only as should be made not exceeding $8 in cost. Under the established rule of decision which obtains in this State in similar cases, the sureties on the bond are discharged because of these changes, for, as the Supreme Court says in Beers v. Wolf, 116 Mo. 179, 187, 188, 22 S. W. 620, “These changes destroy the identity of the contract, and that is sufficient to discharge the sureties.” [See, also, to the same effect, Reissaus v. Whites, 128 Mo. App. 135, 106 S. W. 603; School District v. Green, 134 Mo. App. 421, 427, 114 S. W. 578.] This being true, plaintiffs are not entitled to recover against the sureties and the judgment should, therefore, be reversed. It is so ordered.