Lead Opinion
We address in this appeal whether a subcontractor’s amendment of its original complaint to enforce a mechanic’s lien constituted timely commencement of its action to enforce a bond pursuant to G. L. c. 254, § 14, as amended through St. 2002, c. 400, § 2 (§ 14), which sets forth procedures for execution and enforcement of bonds to dissolve mechanic’s liens. The plaintiff, NES Rentals, Inc. (NES Rentals), filed an action
After NES Rentals filed the amended complaint with leave of court, a judge in the Superior Court denied Maine Drilling’s motion to dismiss the amended complaint, explaining that although NES Rentals had not filed the amended complaint within ninety days of receipt of notice of the bond, service of the motion on the defendants within that ninety-day period provided the defendants with actual notice of the action to enforce the bond, and satisfied the § 14 requirement that a claimant have “commenced” a civil action within that period in order to enforce the bond. The defendants sought leave to appeal, which was allowed, and we transferred the case to this court on our own motion.
We affirm the order denying the defendant’s motion to dismiss, but for reasons different from those relied on by the judge. We conclude that the term “commenced” as used in § 14 contemplates the filing of an action in court in accordance with Mass. R. Civ. P. 3, as amended,
1. Background and prior proceedings. NES Rentals alleges that McManus Excavating, Inc., contracted with it to rent equipment for construction use on property owned by Berkshire Wind.
On April 29, 2011, Maine Drilling
On November 2, 2011, a judge of the Superior Court allowed both the motion of NES Rentals to amend the complaint and Berkshire Wind’s cross motion to dismiss the underlying complaint against it; NES Rentals then filed its amended complaint with the court. Thereafter, Maine Drilling filed a motion to dismiss the amended complaint on the ground that it was not timely filed in accordance with the terms of § 14, because the amended complaint, which constituted the action to enforce the bond, was not filed within ninety days after NES Rentals received notice of recording of the bond, that is, by September 11, 2011.
The judge denied Maine Drilling’s motion to dismiss the amended complaint. He explained that “even though the amended complaint was actually not ‘filed’ within the 90 day period, the defendants had actual notice of it well within that period,” where NES Rentals had served the motion to amend on Maine Drilling and Berkley within that time, and that, therefore, “the purpose of the statute, i.e., notice to the issuer of the bond within 90 days, was satisfied.”* ***
In this case we consider whether amendment of a complaint, originally brought as an action to enforce a lien, by adding a claim to enforce a lien dissolution bond constitutes timely commencement of an action to enforce the bond within the meaning of § 14. We begin our discussion of the applicable provisions of G. L. c. 254 (mechanic’s lien statute) with the observation that it is the primary purpose of the mechanic’s lien statute “to provide security to contractors, subcontractors, laborers, and suppliers for the value of their services and goods provided for improving the owner’s real estate” through perfection of a mechanic’s lien on the owner’s real estate. Hammill-McCormick Assocs., Inc. v. New England Tel. & Tel. Co.,
“At the same time, the statute contains filing and notice requirements to protect the owner and others with an interest in the property.” Id. at 543, and cases cited. The mechanic’s lien statute is “designed to ensure that a person searching the land records in a registry of deeds can determine with certainty whether or not title to a particular parcel of land is encumbered by a mechanic’s lien.” National Lumber Co. v. LeFrancois Constr. Corp.,
We look to the specific provisions governing creation and perfection of a mechanic’s lien, and the procedures for enforcement of a lien dissolution bond, to decide whether NES Rentals has fulfilled the requirements for enforcement of the bond by timely commencing a civil action. Under § 4 of the mechanic’s lien statute, a subcontractor furnishing rental equipment for use on land may record a lien on that property, but under G. L. c. 254, § 11, as amended through St. 1996, c. 364, § 11 (§ 11), “[t]he lien shall be dissolved unless a civil action to enforce it is commenced within ninety days after the filing of the statement required by section eight,” and thereafter “filed in the registry of deeds and recorded.” G. L. c. 254, § 5 (delineating procedures for lien enforcement action). There is no question that NES Rentals recorded its lien and timely commenced and recorded a civil action to enforce it in the Superior Court, after recording a § 8 statement setting forth the amount due for the rental equipment it had furnished.
Section 14 dictates how such a perfected lien may be dissolved by the posting of a bond, and what a subcontractor must do to maintain his security. “Any person in interest may dissolve a lien ... by recording ... a bond ... in a penal sum
“Because a mechanic’s lien is purely a creation of statute, we have consistently required exact compliance with the statute in order to create, perfect, and enforce such a lien.” Golden v. General Bldrs. Supply,
According to Maine Drilling, NES Rentals did not “commence []” an action on the bond within ninety days from the date on which it received notice of the recording of the bond, because NES Rentals did not file its amended complaint until November 2, 2011, or even file its motion to amend until October 3, 2011, well beyond ninety days after NES Rentals was served with notice of the bond on June 13, 2011.
The mechanic’s lien statute does not define the phrase “civil action commenced,” but its meaning may be discerned from the legislative history of the statute. See Commonwealth v. Hamil
We adopted the Massachusetts rules of civil procedure earlier that year, see National Lumber I, 430 Mass, at 670-671; Introduction to Mass. R. Civ. & Mass. R. App. R,
As provided by Rule 3 of the Massachusetts Rules of Civil Procedure, “A civil action is commenced by (1) mailing to the clerk of the proper court... a complaint and an entry fee . . . or (2) filing such complaint and an entry fee with such clerk.” Mass. R. Civ. P. 3, as amended,
However, this conclusion does not end our inquiry. When Maine Drilling and Berkley recorded the lien dissolution bond and provided notice of the bond to NES Rentals, NES Rentals had already commenced a civil action to enforce its lien against Berkshire Wind, in accordance with the provisions of §§ 5 and ll.
Our adherence to principles of strict statutory construction applicable to the mechanic’s lien statute, “and our insistence on precise compliance with those statutory terms, do[] not mean that the rules of civil procedure are inapplicable to proceedings concerning mechanic’s liens .... Absent some incompatibility between a specific procedural rule and the provisions of the [mechanic’s lien] statute, we will apply and enforce both.” Golden, supra at 655, citing National Lumber I, supra at 670-672.
Under ordinary application of the Massachusetts rules of civil
The language of rule 15 (c) has remained unchanged since the enactment of the Massachusetts rales of civil procedure in 1973, which prompted the amendment of the mechanic’s lien statute to conform to the newly adopted rules. See Mass. R. Civ. P. 15 (c),
In National Lumber I, supra at 671-672, we held that a plaintiff who had timely commenced an action to enforce a § 4 lien against a former property owner could amend the complaint to add the present property owner, even after the statutory period for bringing an enforcement action under § 11 had expired. As we explained in that case, under rule 15 (c), the action relates back to the date of the commencement of the complaint, and § 11 does not bar application of rule 15 (c) because § 11 is not a statute of repose blocking later claims against successive property owners. Id.
By comparison, in Golden, supra, we held that a counterclaim to enforce a hen, filed after the § 11 deadline to commence an action on that lien, does not relate back to the date of the complaint filed by the property owner, id. at 661, because “allowing for reinstatement of a dissolved lien by later filing of a counterclaim ‘would effectively give the contractor a period greater than that intended by the Legislature’ in which to enforce the lien.” Id. at 659, quoting Tremont Tower Condominium, LLC v. George B.H. Macomber Co.,
The text and purpose of § 14 and the mechanic’s hen statute support ordinary application of the relation back provisions of rule 15 (c) to the circumstances of this case. Section 14 states in general terms that “[t]he claimant may enforce the bond by a civil action commenced within ninety days after the later of the filing of the statement required by [§] 8 or receipt of notice of recording of the bond.” First, as discussed above, the phrase “civil action commenced,” read in hght of the circumstances of its addition to the statute, permits relation back of an amended complaint to the date of a timely filed original complaint. Moreover, the language “commenced within ninety days after” does not bar commencement of an action before the ninety-day period, as would result from application of the relation back rules in this case. See Mullen Lumber Co. v. Lore,
Additionally, nothing in the language of § 14 requires that
Moreover, application of the relation back provisions of rule 15 (c) in this context is consistent with, rather than repugnant to, the objectives of the mechanic’s lien statute.
Permitting bond enforcement actions to relate back to the date of a timely-filed lien enforcement action does not frustrate the statutory objective of ensuring a reliable recording system. See National Lumber I, supra at 668, citing Pratt & Forrest Co. v. Strand Realty Co.,
We therefore conclude that the ordinary relation back provisions of rule 15 (c) apply to § 14 bond enforcement actions, and that a claimant may, in accordance with rule 15, amend a timely filed complaint seeking enforcement of a lien to add a claim to enforce a lien dissolution bond against the holder of the bond after the ninety-day period set forth in § 14.
Judgment affirmed.
Notes
A judge allowed a motion of Berkshire Wind Power Cooperative Corporation (Berkshire Wind) to dismiss.
General Laws c. 254, § 4, as amended through St. 1996, c. 364, § 5 (§ 4), provides, in relevant part:
“Whoever. . . furnishes rental equipment, appliances or tools, under a written contract with a contractor, or with a subcontractor of such contractor, may file or record in the registry of deeds for the county or district where such land lies a notice of his contract.... Upon filing or recording a notice, as hereinbefore provided, and giving actual notice to the owner of such filing, the subcontractor shall have a hen upon such real property, land, building, structure or improvement owned by the party who entered into the original contract as appears of record at the time of such filing, to secure the payment of all labor and material and rental equipment, appliances or tools which he is to furnish or has furnished for the building or structure or other improvements. . . .”
GeneraI Laws c. 254, § 8, as amended by St. 1996, c. 364, § 9, provides:
“Liens under section[]. . . four shall be dissolved unless the contractor, subcontractor, or some person claiming by, through, or under them, shall[, within a specified time frame,] file or record in the registry of deeds in the county or district where the land lies a statement, giving a just and true account of the amount due or to become due him . . . .”
Maine Drilling states that it is another subcontractor on the Berkshire Wind property. The record is silent on the point, but Maine Drilling’s role as a subcontractor is not material to our decision in this case.
General Laws c. 254, § 14, as amended through St. 2002, c. 400, § 2 (§ 14), provides, in relevant part:
“Any person in interest may dissolve a lien under this chapter by recording ... a bond ... in a penal sum equal to the amount of the lien sought to be dissolved conditioned for the payment of any sum which the claimant may recover on his claim for labor or labor andmaterials. . . . The claimant may enforce the bond by a civil action commenced within ninety days after the later of the filing of [the G. L. c. 254, § 8, statement of account] ... or receipt of notice of recording of the bond. . . .”
As an additional ground for denying the motion on the basis of notice, the judge stated that Maine Drilling and Berkley were represented by the same counsel as Berkshire Wind, the defendant in the original action. Maine Drilling and Berkley assert that this was a factually incorrect assumption based solely on the fact that counsel in the two firms share a surname. Nothing in the record supports the statement that the firms, or the attorneys, are “the same.” Our disposition of the matter, however, does not depend on a resolution of this issue.
NES Rentals made no claim in the Superior Court that Maine Drilling is
Maine Drilling does not argue that an amended complaint to enforce a bond could not, if filed in the Superior Court by September 11, 2011, have qualified as a timely filed “civil action” within the meaning of § 14.
The relevant language of rule 3 has not changed since its original adoption. Compare Mass. R. Civ. R 3, as amended,
We are not concerned here with a situation in which a bond preceded and thus precluded attachment of a lien, governed by G. L. c. 254, § 12, as amended through St. 2002, c. 400, § 1 (§ 12), or where, at the time that the bond was recorded, a lien claimant already had perfected a lien but had not yet commenced an action to enforce it. In accordance with §§ 12 and 14, both of those situations require a claimant to commence a new action to enforce the bond.
An amended complaint is a pleading that qualifies as a civil action within the meaning of § 14. See Mass. R. Civ. R 15 (a),
The amendment of a complaint to enforce a lien, by adding a claim seeking enforcement of a lien dissolution bond against a person who executed the bond, complies with the threshold requirement of Mass. R. Civ. R 15 (c),
Because a lienholder has ninety days to file a complaint under § 11, and thirty days to record the complaint thereafter under § 5, the lienholder has a maximum of 120 days within which to commence and provide record notice of a claim to enforce a lien.
This interpretation is consistent with the legislative history of § 14. The 2002 amendments to § 14 added “the later of the filing of the statement required by section 8 or” to the statute, see St. 2002, c. 400, § 2, which previously had required only that a civil action be commenced “after the receipt of notice of recording of the bond.” Compare G. L. c. 254, § 14, as amended through St. 1996, c. 364, § 14, with G. L. c. 254, § 14, set forth in note 6, supra. A December, 2002, memorandum to then Governor Jane M. Swift from the Director of Legislative Research regarding 2002 Senate Doc. No. 931, the bill that was enacted as St. 2002, c. 400, §§ 1-2, explained that, under this bill, “the final deadline for either type of bond [under § 12 or § 14] will be [ninety] days after the claimant files a ‘Statement of Claim,’ in accordance with c. 254, § 8 ... . The effect of the change is to afford contractors who rely on bonds the same amount of time to commence an action on that claim as contractors who rely on liens currently have to file an action to enforce the lien.” See also R.V. Lizza, Massachusetts Mechanic’s Lien Law § 5.5, at 5.5.1 (Mass. Cont. Legal Educ. 2006) (“The 2002 Amendment also addressed a procedural ‘trap for the unwary’ ” under which claimants bringing actions to enforce bonds under §§ 12 and 14 may have “a shorter period of time than would be available for making a normal lien claim”). It thus appears that, in adding more detail to the § 14 timeline, the Legislature was concerned with
General Laws c. 254, § 5, provides, in pertinent part: “All other parties in interest may appear and have their rights determined in such action, and at any time before entry of final judgment, upon the suggestion of any party in interest that any other person is or may be interested in the action, or of its own motion, the court may summon such person to appear in such cause on or before a day certain or be forever barred from any rights thereunder. The court may in its discretion provide for notice to absent parties in interest.”
Compare § 5 (“The terms ‘party in interest’ and ‘person in interest,’ as used in this chapter, shall include mortgage[e]s and attaching creditors” [emphasis added]), with § 12 (“The bond may be enforced by a civil action in the superior court or district court brought by any party in interest” [emphasis added]), and § 14 (“Any person in interest may dissolve a lien under this chapter by recording ... a bond” [emphasis added]).
Cf. Nett v. Bellucci,
The dissent, post at 870, 873, expresses concern that application of the ordinary rules of relation back in the context of § 14 would introduce uncertainty into the mechanic’s lien statute. However, concerns about uncertainty appears to relate primarily to reliability of title. See Golden, supra at 660 & n.8 (discussing interest in certainty of recording system). As described above, once a bond is posted, the lien encumbering the property is dissolved, and any uncertainty of title arising from the lien disappears. Moreover, the principal on the bond — the party with a continuing interest in certainty — would be on record notice of any pending lien enforcement actions, back to which an amendment could relate, when undertaking to post a bond in the first place. See G. L. c. 254, § 5 (requiring recording of copy of complaint seeking enforcement of lien).
Although the rule provides that “leave shall be freely given when justice so requires,” see Mass. R. Civ. R 15 (a),
A claimant is of course not precluded from filing a separate, timely complaint to enforce a bond under § 14. See National Lumber II, supra at 725; LaCentra v. Jackson,
NES Rentals argues that Maine Drilling and Berkley did not properly give service of notice of the bond to NES. We do not address this argument, which was not raised below and therefore has been waived. See Mass. R. A. R 16 (a) (4), as amended,
Dissenting Opinion
(dissenting). I write separately because I believe that the court’s decision strays from both clear statutory language and well-established precedent. In so doing, the court unnecessarily introduces a level of unpredictability into the requirements for compliance with the mechanic’s lien statute, an area of law in which those affected rely on the certainty that the statute is designed to provide. See Golden v. General Bldrs. Supply,
As the court recognizes, an amendment to the complaint that the claimant originally brought to enforce the then undissolved lien may constitute the “civil action” contemplated in § 14; the parties agree that an entirely new case need not be brought by a claimant in order to enforce the lien dissolution bond. Ante at note 9. The issue, then, is not — as the court’s statutory analysis, ante at 867-869, would suggest — whether an amended complaint will suffice, but when the amended complaint must be filed. In reliance upon the relation-back provisions of rule 15 (c), the court concludes that it need not be filed within the ninety-day period mandated by § 14. To the extent that the court justifies this result by suggesting that it permits claimants to recover on a lien dissolution bond “without having to initiate an entirely new case,” ante at 869, it answers a question that has not really been asked.
The question that is before us is whether the claimant’s amended complaint must be “commenced,” i.e., filed with the court, see Nett v. Bellucci,
The upshot of the court’s decision is to render the ninety-day period set forth in the statute largely superfluous, a result that is ordinarily to be avoided. See Trace Constr, Inc. v. Dana Barros Sports Complex, LLC,
It is hard to imagine that this is what the Legislature intended in a statute otherwise replete with precise statutory deadlines with which we have routinely required exact compliance. See Gale v. Blaikie,
Strict compliance with the express language of the mechanic’s lien statute promotes certainty, uniformity of application, and predictability for all whose interests are affected by it; the vagueness, imprecision and uncertainty introduced by the court’s novel and relaxed approach does those interests no favors. Given
“The claimant may enforce the bond by a civil action commenced within ninety days after the later of the filing of the statement required by section 8 or receipt of notice of recording of the bond.” G. L. c. 254, § 14, as amended through St. 2000, c. 400, § 2 (§ 14).
I agree with the court that the mere service of a motion to amend a complaint on an opposing party does not constitute commencement of an action within the meaning of § 14. Ante at 864.
If the amended complaint is not itself filed with the court within the ninety-day period, the filing with the court in that ninety-day window of the motion to amend the complaint should be deemed to commence the § 14 civil action. See Nett v. Bellucci,
Since the statute requires claimants seeking to enforce a mechanic’s lien to commence a civil action within a narrow timeframe lest the lien be dissolved, G. L. c. 254, § 11, as amended through St. 1996, c. 364, § 11, most claimants later seeking to enforce a lien dissolution bond, G. L. c. 254, § 14, will already have brought a civil action and will likely seek to amend that original complaint.
