Respondent initially instituted the present action to foreclose a mechanic’s and materialman’s lien for labor and materials furnished in remodeling appellants’ home. The trial court found that although there were instances of defective construction, the contract had been substantially performed, and the court entered judgment in favor of respondent.
Upon appeal, in disposition of the first appeal,
Upon remand to the district court, the case was submitted upon the record and exhibits already on file, no additional evidence having been introduced. The district court entered findings to the effect that respondent was entitled to recover $5,090.86 for labor and materials, less $1,997.51 which appellants had paid on the contract. The trial court then awarded appellants damages for the cost of repairing defective construction in the amount of $2,494.50 allowed as a set-off from respondent’s award, and entered judgment in favor of respondent for $598.85 with interest and costs.
The trial court under the remittitur was instructed “to assess the damages sustained by appellants and entered judgment accordingly, and to that end, take any additional evidence as may be deemed requisite.” Nelson v. Hazel, supra. The trial court followed such instruction by allowing appellants’ damages by way of a set-off, in the amount of the estimated cost of repairs to restore their home to good and workmanlike condition, from the contractor’s total charges for labor and material of $5,090.86.
In an action for breach of contract, only such damages will be allowed as fairly compensate the injured party for his loss. Jones v. Better Homes,
Appellants contend on the basis of the earlier ruling in this case that a person may not enforce collection under a contract which has not been substantially performed. Nelson v. Hazel, supra. However, building contracts constitute an exception to the usual contract rule that a defaulting party in a contract action can
*852
not recover damages. Such exception is based on the reasoning that unjust enrichment would result were the homeowner to retain the value of improvements in excess of that caused by the contractor’s breach. Amtorg Trading Corp. v. Miehle Printing Press & Mfg. Co., 2 Cir.,
If the defective performance, though less than substantial, has conferred benefits on the homeowner in excess of his injury, he is under a quasi-contractual duty to pay that excess. Corbin on Contracts, vol. 3A, p. 310 (1960). See Restatement, Contracts, § 357, Comment e. See Hixen v. Allphin,
Appellants contend that they have reaped no benefit from the building transaction, because the installations by the contractor will still require large remedial expenditures. The estimates by appellants’ expert witnesses (adduced in evidence prior to the first appeal) make allowance ’ for those expenditures. The trial court chose the higher of those estimates in allowing appellants the set-off of $2,300.00 for general costs of repair, and included the item of $194.50 expended for restoration of the chimney, totaling $2,494.50.
Judgment affirmed. Cost? . to respondent. : •
