Opinion
In this action under the California Environmental Quality Act (Pub. Resources Code, § 21000 et seq.; CEQA),
Petitioners filed a petition for writ of mandate seeking to set aside County’s determinations and approvals on the ground that the failure to review the entire project—including the mining operations—violated CEQA and constituted an abuse of discretion. The trial court disagreed with petitioners’ analysis, concluded that County did not err in limiting its consideration to the reclamation plan, and entered a judgment denying the petition. Petitioners appealed. We conclude petitioners are correct in their fundamental claim on appeal: County’s role as lead agency under CEQA, in conjunction with its responsibilities under SMARA, required it to evaluate the environmental effects of the whole surface mining project even though that project was on federally owned land.
FACTS AND PROCEDURAL HISTORY
The remote Jawbone Canyon area in the Southern Sierra Nevada foothills contains significant mineral deposits of what BLM describes as “an uncommon variety” of calcite marble. The purity and other characteristics of the calcite marble found in this location make it a valuable resource for production of high-quality or special-use calcium carbonate and calcite that have a number of beneficial commercial and industrial applications. Approximately 8.3 acres of the Jawbone Canyon area were previously surface mined and that site was (and is) commonly known as the Monarch Calcite Quarry. As a result of the prior mining operations, several exposed, open-face side-hill cuts remain at the site of the former mine.
In the present case, Carlton proposed to restart surface mining of calcite marble at the Monarch Calcite Quarry and thereafter to expand such mining
Concurrent Applications to County and BLM
Although this dispute concerns Carlton’s mining and reclamation plans, and in particular the sufficiency of County’s environmental review thereof, the initial applications to both County and BLM were made by Carlton’s predecessors in interest, including Alpha Minerals & Chemicals LLC (Alpha Minerals) and Tri-Western Resources, LLC (Tri-Western). Therefore, as we summarize the background facts at this point in our discussion, we track the steps taken in the approval process by reference to these predecessor entities of Carlton.
On February 28, 2005, Alpha Minerals filed an “APPLICATION FOR SURFACE MINING PERMIT AND/OR RECLAMATION PLAN” with County’s planning department. The project described therein included a plan to surface mine calcite marble at the site of the former Monarch Calcite Quarry for a period of 30 years and a reclamation plan related thereto. This document appears to be an early or preliminary version of the subsequently proposed mining and reclamation plan and encompassed only the 8.3-acre site of the original Monarch Calcite Quarry.
Subsequently, on March 14, 2005, Tri-Western filed a proposed mine plan of operations with BLM, which was revised on April 6, 2005, and August 22, 2005. The proposed plan and revisions thereto were submitted to BLM in order to obtain a lease or permit from BLM for conducting mining operations on federal land. The second revision thereto, entitled “REVISED MINE PLAN OF OPERATIONS AND RECLAMATION PLAN FOR U.S. BUREAU OF LAND MANAGEMENT AND KERN COUNTY, CA . . . ,” was filed in response to comments received from BLM and County and clearly specified that the mining plan covered a total of 40 acres on BLM land. It also referred to the filing of a SMARA plan with County. The proposed plan (as revised) was presented by Tri-Western “on the Kern County SMARA form” in order to represent both “a Plan of Operations ... for the BLM and a Reclamation Plan for Kern County, California under [SMARA].”
The same mining and reclamation plans were proposed or submitted to County. Tri-Western submitted an “APPLICATION FOR SURFACE MINING PERMIT AND/OR RECLAMATION PLAN” to County’s planning
The above submission to County included a document executed by Tri-Westem on June 15, 2005, entitled “STATEMENT OF RESPONSIBILITY,” in which Tri-Westem confirmed in writing that it would perform all provisions and conditions imposed by County pursuant to “the Ordinance Code of Kem County (Chapter 19.100).” The referenced County ordinance explicitly addresses “SURFACE MINING OPERATIONS” and was adopted by County for the express purpose of regulating surface mining within County in a manner consistent with the requirements of laws such as SMARA. (County Zoning Ord., § 19.100.010.) Among other things, the ordinance provides: “[N]o surface mining operations may be undertaken anywhere in unincorporated Kem County unless a surface mining permit and a reclamation plan has been submitted to and approved by the Planning Commission in accordance with the procedures set out in Sеctions 19.102.130 through 19.102.180 of this title.” (County Zoning Ord., § 19.100.020.)
Additionally, Tri-Westem’s documentation filed with County included an “ENVIRONMENTAL INFORMATION FORM” to assist County in its CEQA review process. The form was signed on June 15, 2005, and was filed with County’s planning commission on October 17, 2005. In said environmental information form, Tri-Westem described the “project for which this form is filed” as a “Surface Mine (Quarry)” (Italics added.)
To summarize the above referenced submissions by Tri-Westem (as Carlton’s predecessor) regarding surface mining and reclamation plans, it appears that applications were made to both County and ELM for governmental approvals,
BLM Completes NEPA Assessment and Approves Mining Application
BLM acted first. As the proposed mining was to occur on federal land, BLM, as the responsible federal agency, proceeded to conduct an environmental review thereof in compliance with NEPA standards. BLM completed its “Environmental Assessment” of the planned mining operations and, based on that assessment, adopted a finding under NEPA that said mining operations would have no significant effect on the environment (referred to as a “Finding of No Significant Impact” or a FONSI). Accordingly, the proposed mining operations were approved by BLM from a federal law standpoint. BLM’s approval and its written statement of findings (FONSI) were transmitted to Tri-Western by letter dated November 18, 2005.
County Limits Its Review to the Reclamation Plan
Sometime after BLM’s adoption of the FONSI and resulting approval of mining operations, County proceeded to separately consider whether to approve the reclamation plan. In February of 2006, an “INITIAL STUDY REVIEW” (the Initial Study) of potential environmental impacts (including an “ENVIRONMENTAL CHECKLIST FORM” and attachments) was completed by County’s planning commission. The “[p]roject” under review in the Initial Study was described therein as follows: “A Conditional Use Permit to allow a mining reclamation only plan in accordance with the Surface Mining and Reclamation Act (SMARA) . . . .” (Italics added.) The Initial Study further emphasized the limited scope of the matter being reviewed: “The applicant is seeking the approval of ... a reclamation plan only on federally administered property in accordance with [SMARA]. Kern County is limited to the reclamation of the mined site, and [BLM] is responsible for the mining activity. The applicant has received approval from the BLM to mine the 40-acre project site for calcite marble over a period of 30 years.” (Italics added.)
A staff report by County’s planning department similarly explained that County’s environmental review and approval was limited to the reclamation plan only: “The applicant is seeking approval of a conditional use permit to approve a reclamation plan. Because this property is located on federally owned land, the BLM is the actual permitting agency for mining operations.
The MOU referred to by County staff is an agreement between the State of California, the United States Forest Service (the Forest Service) and BLM, entered with the objective of establishing procedures and guidelines to coordinate environmental review, facilitate compliance with state and federal environmental laws and avoid unnecessary duplication in situations where surface mining activities are proposed on federal land. We shall consider the MOU in greater detail at a later point in our discussion. At this juncture, we simply note that County’s planning department staff believed the MOU supported their conclusion that County was required to review the reclamation plan only.
County’s planning department staff analyzed the environmental effects of the reclamation plan only and identified certain mitigation measures that were necessary to keep the environmental impacts of the reclamation plan at a level that was less than significant. A staff report set forth the opinion that “the proposed reclamation plan, as conditioned, is adequate to ensure that the site will be successfully reclaimed in a manner that complies with local and State requirements.” The planning depаrtment recommended in the staff report that a mitigated negative declaration be adopted and that the reclamation plan be approved.
On April 27, 2006, County’s planning commission held a public hearing relating to the proposed reclamation plan. The hearing culminated in the commission’s adoption of resolution No. 84-06, approving Carlton’s (Tri-Westem’s) conditional use permit for the reclamation plan and certifying the mitigated negative declaration in conjunction with the reclamation plan.
An adjacent property owner, Leroy Cass, appealed the commission’s decision to County’s board of supervisors (the Board), arguing that a complete study of environmental impacts of mining operations should have been conducted by County. The appeal was initially scheduled for June 27, 2006, but the Board continued the hearing several times to allow further consideration of various issues and comments, including the issues raised by petitioners’ counsel. Prior to each scheduled hearing, staff reports prepared by County’s planning department reiterated the department’s firm position that the matter before the Board for its review was “a mining reclamation only plan,” not a plan for mining operations. (Italics added.)
Petitioners disagreed, arguing in letters and oral argument to the Board that it was improper under CEQA for County to segregate the reclamation plan
At the public hearing on October 9, 2007, after considering the recommendations of the planning department and the arguments presented by petitioners and others, the Board denied the appeal, approved the conditional use permit for the reclamation plan and adopted the mitigated negative declaration concerning the reclamation plan. At that point, as far as Carlton and County were concerned, no further approval was needed for Carlton to begin surface mining.
The Petition and the Trial Court’s Ruling
On November 14, 2007, petitioners filed their petition for writ of administrative mandate.
On July 17, 2009, a hearing on the merits of the petition was held in the trial court. On September 11, 2009, after considering the briefing and oral argument presented by the parties, the trial court issued its “Order Denying Petition for Writ of Administrative Mandamus and Judgment in Favor of Respondent County of Kern.” (Some capitalization omitted.) In its order, the trial court reasoned that County was correct in limiting its review to the reclamation plan because (1) BLM had sole authority over the approval of the mining operation under the terms of the MOU, (2) the mine would be on federal land, and (3) BLM granted approval of the mining operation before County acted on the reclamation plan. The trial court concluded that the situation was analogous to two appellate cases that allowed reclamation plans to be reviewed separately from preexisting mining operations that operated pursuant to vested rights. Those two cases were El Dorado County Taxpayers for Quality Growth v. County of El Dorado (2004)
DISCUSSION
I. Standard of Review
In our consideration of petitioners’ CEQA challenge, we independently review the administrative record to determine whether County proceeded in a manner consistent with the requirements of CEQA. (El Dorado County, supra,
In applying this standard of review, we begin with a brief overview of an agency’s basic obligations under CEQA. “A governmental agency must
“Generally, an agency will prepare an initial threshold study to gather information necessary to determine whether to prepare an EIR or a negative declaration. The initial study must include a description of the project.” (City of Redlands, supra, 96 Cal.App.4th at pp. 405-406, fns. omitted.) “Where an agency fails to provide an accurate project description, or fails to gather information and undertake an adequate environmental analysis in its initial study, a negative declaration is inappropriate. [Citation.] An accurate and complete project description is necessary to fully evaluate the project’s potential environmental effects. [Citations.]” (El Dorado County, supra,
“The scope of the environmental review conducted for the initial study must include the entire project.” (Tuolumne County Citizens for Responsible Growth, Inc. v. City of Sonora (2007)
II. County Erred by Limiting Its Environmental Review to the Reclamation Plan
Petitioners contend that County was required to review the entirety of the surface mining project, including mining operations, based on (1) County’s lead agency responsibilities under SMARA and CEQA, and (2) a correct definition of what constitutes a CEQA project. We agree. Furthermore, we conclude that County’s reliance on the MOU and the mining cases of El Dorado County, supra,
A. County’s Responsibility as Lead Agency Under SMARA and CEQA
The question of whether County had a responsibility to review Carlton’s surface mining operations (and not merely the reclamation plan) must be considered in light of the requirements of SMARA and the local
To facilitate the enforcement of SMARA, section 2774 states that “[e]very lead agency shall adopt ordinances in accordance with state policy that establish procedures for the review and approval of reclamation plans and financial assurances and the issuance of a permit to conduct surface mining operations . . ..” (§ 2774, subd. (a).) In the present case, County adopted such an ordinance, entitled “SURFACE MINING OPERATIONS,” which was enacted for the express purpose of regulating surface mining within County in a manner consistent with the requirements of SMARA. (County Zoning Ord., § 19.100.010.) The ordinance provides: “[N]o surface mining operations may be undertaken anywhere in unincorporated Kern County unless a surface mining permit and a reclamation plan has been submitted to and approved by the Planning Commission in accordance with the procedures set out in Sections 19.102.130 through 19.102.180 of this title.” (County Zoning Ord., § 19.100.020.)
Local рublic agencies, such as cities or counties, are given the responsibility to enforce SMARA.
Based on the above provisions, it is clear that County, as lead agency, was responsible under SMARA and the local ordinance to evaluate Carlton’s entire proposal and to determine both whether to issue a permit
The same result is obtained when we consider the issue in the larger framework of the environmental review required under CEQA, and in particular CEQA’s conception of (1) lead agency responsibility and (2) the nature and scope of a project. CEQA defines a “[l]ead agency” as “the public agency which has the principal responsibility for carrying out or approving a project which may have a significant effect upon the environment.” (§ 21067.) The first part of that definition is that the lead agency must be a public agency, which under CEQA means a state agency. (§ 21063; CEQA Guidelines, § 15379 [the term public agency “does not include agencies of the federal government”].) In view of County’s responsibility regarding approval of the surface mining project under SMARA and the fact that a federal agency cannot be a CEQA lead agency (since it is not a state public agency), we conclude that County was the lead agency under CEQA. Moreover, even if other agencies also had responsibility for approvals, CEQA mandates there be only one lead agency that will be ultimately responsible
As lead agency, County’s significant responsibilities under CEQA included conducting an initial study to evaluate the potential environmental effects of the proposed mining project and determining, in response to the information provided in the initial study, whether to prepare an EIR or adopt a negative declaration. (El Dorado County, supra,
Because County, as lead agency, was required by CEQA to consider and evaluate the potential environmental effects of the entire project, we now discuss the definition of a project under CEQA and the consequences of that definition in the present context. As will be seen, CEQA’s notion of what constitutes a project confirms that Carlton’s proposed mining operations and reclamation plan together constituted a single project in this case. Accordingly, both had to be reviewed by County.
B. The Scope of the Project as Defined by CEQA
CEQA defines a “[p]roject” as “an activity which may cause either a direct physical change in the environment, or a reasonably foreseeable indirect physical change in the environment, and .. .[][]... [f] .. . that involves the issuance to a person of a lease, permit, license, certificate, or other entitlement for use by one or more public agencies.” (§ 21065.) The CEQA Guidelines augment the statutory definition by specifying that a
As is readily apparent from the above definitions, CEQA’s conception of a project is broad (see Friends of the Sierra Railroad v. Tuolumne Park & Recreation Dist. (2007)
CEQA Guidelines further clarify that the term “project” refers to “the activity which is being approved and which may be subject to several discretionary approvals by governmental agencies. The term ‘project’ does not mean each separate governmental approval.” (CEQA Guidelines, § 15378, subd. (c), italics added.) This important elaboration is meant to “ensure that a project proponent does not file separate environmental reports for the same project to different agencies thereby preventing ‘consideration of the cumulative impact on the environment . . . .’ [Citation.]” (Azusa Land Reclamation Co. v. Main San Gabriel Basin Watermaster (1997)
Based on the foregoing, we conclude that the entire CEQA project that had to be reviewed by County included both the mining operations and the reclamatiоn plan. Both aspects were integrally related and constituted the whole of the action or the entire activity for which approvals were being sought. Indeed, the reclamation plan was simply the final phase of the overall usage of the land proposed by Carlton, by means of which the land will be (or was intended to be) significantly restored. Also, the two aspects are closely related by the fact that a reclamation plan was legally required in any proposal to engage in surface mining operations in California (§ 2770, subd. (a)). For these reasons, the mining and reclamation activities proposed by Carlton constituted a single CEQA project. (See Tuolumne County Citizens, supra, 155 Cal.App.4th at pp. 1225-1231 [where distinct actions are closely related to same overall objective, or if success of the overall objective depends on the inclusion of certain action, the distinct actions are viewed as parts of a larger whole—the same project].) Therefore, in accordance with our discussion above, CEQA required County to engage in an environmental review of both the mining operations and the reclamation plan—the entire project.
Since County’s analysis of potential environmental impacts in its initial study was limited to the reclamation plan and did not extend to Carlton’s mining operations, County failed to review the entire project as required by CEQA and thereby abused its discretion. To put it another way, when County focused on the reclamation plan alone, it committed the “fallacy of division” whereby a larger, whole project was improperly divided into component parts for piecemeal consideration. That was error, and the error was clearly prejudicial because County decision makers and the public were thereby deprived of the essential information and environmental analysis that CEQA mandates. (See Citizens Assn. for Sensible Development of Bishop Area v. County of Inyo (1985)
“An accurate and complete project description is necessary for an intelligent evaluation of the potential environmental impacts of the agency’s action.” (City of Redlands, supra,
C. The Two Mining Cases Relied on by County and the Trial Court
We briefly address the two mining cases that were relied on by County planning staff and by the trial court in its judgment below: namely, El Dorado County, supra,
We begin with the older of the two cases, City of Ukiah. In that case, Ford Gravel Company, Inc. (Ford), had conducted gravel excavation (a form of surface mining) at a location on the Russian River in Mendocino County since 1946. In the 1960’s, after a local ordinance was passed requiring a use permit for “ ‘the establishment’ ” of such commercial mining activities, Ford рroceeded to obtain the appropriate use permits for its operations. (City of Ukiah, supra,
In the appeal in City of Ukiah, it was argued that “both the board and the trial court failed to consider the cumulative impact of Ford’s gravel extraction activities in combination with other gravel mining operations on the river.” (City of Ukiah, supra,
A similar situation existed in the case of El Dorado County, supra,
On appeal, it was argued that the county failed to review the entire project, which the appellants defined as including both the mining operations and the updated reclamation plan. The Court of Appeal in El Dorado County disagreed. It held that the only project the county had to review under CEQA was the updated reclamation plan because (1) the existing mining operations were already “allowed as a vested mining right,” and (2) the addition of 16 acres of reclamation was merely an adjunct of the updated reclamation plan itself, not a request for any additional mining activities. (El Dorado County, supra,
In light of the unique factual setting in both of the above mining cases—the existence of pre-SMARA surface mining that was still being conducted under vested mining rights—we believe those cases are distinguishable from the one presently before us. Here, although Carlton’s plan would utilize a previously mined area (the Monarch Calcite Quarry), there was no preexisting and ongoing surface mining operation by Carlton on the 40-acre site pursuant to vested rights. Instead, Carlton submitted what amounted to an entirely new mining and reclamation plan, and the whole project described therein could not proceed without first obtaining necessary governmental approvals. (§ 2770, subd. (a).) Thus, unlike the two mining cases discussed above, here both aspects of the proposed mining plans— mining operations and reclamation—were at once on the table and had to be reviewed and approved for the first time by the appropriate governmental agencies.
In summary, even though BLM may have completed its environmental study and granted federal “approval” before County completed its own CEQA and SMARA state law proceedings, we do not believe the present case is analogous to a situation in which there was long-standing mining activity under vested mining rights. Rather, Carlton’s surface mining and reclamation proposal constituted a new project concerning which environmental review by County of the whole of the action was necessary. For these reasons, we conclude that the El Dorado County and City of Ukiah cases are distinguishable.
D. The MOU
Contrary to the conclusions of County planning staff and the trial court, the MOU did not authorize or require County to avoid environmental review of Carlton’s mining operations.
The MOU was a written agreement between the State of California, the Forest Service and BLM entered into in 1992 for the purpose of establishing procedures or guidelines to (a) coordinate environmental review, (b) facilitate compliance with state and federal environmental laws, and (c) avoid unnecessary duplication in situations where (as here) surface mining activities are proposed on federal land.
For example, in its substantive provisions, the MOU requires lead agencies and the Forest Service and/or BLM to “work cooperatively” to ensure that conditions or measures required of mine operators to mitigаte adverse environmental impacts “conform to all applicable local, State, and Federal regulations.” (Italics added.) Further, while the MOU allows lead agencies to “accept as functionally equivalent documents” for purposes of SMARA, any reclamation plans, operational plans or environmental studies submitted pursuant to federal regulations, a lead agency may do so only if such plans and studies “meet or exceed lead agency requirements as included in the lead agency’s State-certified surface mining and reclamation ordinance and any other applicable laws and regulations . . . .” Similarly, lead agencies may “accept as functionally equivalent, documents prepared under NEPA . . . that meet the requirements of CEQA.” As these provisions make clear, the MOU does not seek to avoid state law requirements, but to uphold them. It provides for cooperation and allows lead agencies to accept environmental documents prepared by a federal agency pursuant to NEPA, but only to the extent such documents comply with SMARA and CEQA.
The MOU specifies in further detail the level of cooperation that should be pursued when a surface mining project is proposed on federal land. At paragraph 8, the MOU states: “For mining operations requiring a Plan of Operations for projects solely on Federal land, that are not exempt from SMARA, BLM and the Forest Service will provide lead agencies notiсe and the opportunity for early participation, consultation, and submission of information and recommendations for the development of environmental documents and reclamation plans.” Paragraph 9 of the MOU indicates that after receipt of such notification, lead agencies should promptly provide comments or recommendations to the Forest Service and/or BLM “so that they may be considered and incorporated, as appropriate, as part of the environmental review and proposed Forest Service and/or BLM decision.” Paragraph 10 provides that public hearings for compliance with SMARA and the local SMARA ordinance should be coordinated with the Forest Service and/or BLM. Nothing in the above provisions suggests that the lead agency is expected to desist from its responsibilities under SMARA and/or CEQA.
We conclude the MOU is not reasonably susceptible to an interpretation that County was relieved of its resрonsibilities under SMARA and CEQA to perform an environmental review of the mining operations. Therefore, the MOU does not even arguably support County’s decision to engage in an environmental review of the reclamation plan only. In addition, we note in passing that County apparently failed to avail itself of the cooperation provisions of the MOU. Nothing in the record reflects that County assisted in the preparation of the federal environmental documents or otherwise undertook to assess the contents of the federal environmental documents to decide whether they were compliant with SMARA and CEQA and therefore, potentially, a functional equivalent to what SMARA and CEQA would require.
III. CEQA and NEPA Both Applied to the Project
An assumption underlying the approach taken by County and the trial court was that BLM’s federal review of the mining operations under NEPA somehow precluded or barred County from fully undertaking state law environmental review under CEQA. Contrary to that assumption, however, CEQA contemplates there will be projects in which both CEQA and NEPA apply and it specifically provides for such occasions by setting forth various means of cooperation while at the same time ensuring that CEQA’s standards are satisfied. (See, e.g., §§ 21083.5-21083.7; CEQA Guidelines, §§ 15220-15229, 15063, subd. (a)(2), 15361.)
For example, a separate article of the CEQA Guidelines, which includes sections 15220 through 15229, specifically covers the subject of “PROJECTS ALSO SUBJECT TO [NEPA].” CEQA Guidelines, section 15220 unequivocally states: “This article applies to projects that are subject to both CEQA and NEPA. NEPA applies to projects which are carried out, financed, or approved in whole or in part by federal agencies. Accordingly, this article applies to projects which involve one or more state or local agencies and one or more federal agencies.” (Italics added.) Thus, the CEQA Guidelines plainly contemplate overlapping state and federal jurisdiction in the sense that certain projects may be subject to both CEQA and NEPA and hence may involve review and approvals by both state or local and federal agencies.
Similarly, regarding notice and circulation requirements where the lead agency elects to rely on a federal agency’s environmental document, the CEQA Guidelines provide as follows: “(a) Where the federal agency circulated the EIS or [FONSI] for public review as broadly as state or local law may require and gave notice meeting the standards in Section 15072(a) or 15087(a), the lead agency under CEQA may use the federal document in the place of an EIR or negative declaration without recirculating the federal document for public review. One review and comment period is enough. Prior to using the federal document in this situation, the lead agency shall give notice that it will use the federal document in the place of an EIR or
To recapitulate, CEQA expressly recognizes there will be projects in which both CEQA and NEPA apply. In such cases, CEQA provides means of cooperation to avoid unnecessary duplication. However, the state or local lead agency must still ensure that CEQA is fully complied with, including in those instances where the environmental documents are jointly produced or are produced by the federal agency and subsequently accepted by the state or local lead agency in lieu of an EIR or negative declaration. We believe that CEQA’s approach to the issue of conсurrent applicability of CEQA and NEPA, as outlined herein, supports our conclusion in the present case that when BLM completed its environmental review under NEPA and made its findings, County was still required to comply with CEQA (and SMARA) with respect to the entire project.
An analogous case decided by the United States Supreme Court is helpful in understanding that a state agency may have authority to enforce state law environmental regulations (such as CEQA) in regard to projects on federal land. In California Coastal Comm’n v. Granite Rock Co. (1987)
Here, similarly, BLM’s own regulations specifically provide for compliance with state environmental laws. (See, e.g., 43 C.F.R. §§ 2920.7(b)(4), 3802.3-2, 3809.3, 3591.1(c) (2010); see also 36 C.F.R. § 228.46 (2010).) Although no preemption claim was made in this case, and thus we do not reach that particular issue, we do make the following general observation: Based on the analysis set forth in California Coastal Comm’n v. Granite Rock Co., supra,
Petitioners further argue that County must be ordered to prepare an EIR based on CEQA’s fair argument test. “With certain limited exceptions, a public agency must prepare an EIR whenever substantial evidence supports a fair argument that a proposed project ‘may have a significant effect on the environment.’ [Citations.]” (Laurel Heights Improvement Assn. v. Regеnts of University of California (1993)
“The determination by an appellate court under the fair argument test involves a question of law decided independent of any ruling by the superior court. [Citation.]” (County Sanitation Dist. No. 2 v. County of Kern, supra,
We note some important definitions. First, the term “substantial evidence” is defined by the CEQA Guidelines to mean “enough relevant information and reasonable inferences from this information that a fair argument can be made to support a conclusion, even though other conclusions might also be reached.” (CEQA Guidelines, § 15384, subd. (a).) Substantial evidence includes “facts, reasonable assumptions predicated upon facts, and expert opinion supported by facts,” but does not include “[argument, speculation, unsubstantiated opinion or narrative, [or] evidence which is clearly erroneous or inaccuratе.” (Id., subds. (b), (a); see § 21080, subd. (e)(1) & (2).) Second, the term “ ‘Significant effect on the environment’ means a substantial, or potentially substantial, adverse change in the environment.” (§ 21068.) As elaborated in the CEQA Guidelines, a significant effect on the environment is “a substantial, or potentially substantial, adverse change in any of the physical conditions within the area affected by the project[,] including land, air, water, minerals, flora, fauna, ambient noise, and objects of historic or aesthetic significance.” (CEQA Guidelines, § 15382.)
We begin with the issue of potential impacts on air quality. County’s Initial Study looked at the reclamation plan only and concluded that emissions or pollutants generated from reclamation activities would have less than a significant impact. A letter from Kern County Air Pollution Control District (the Distriсt), dated October 4, 2007, agreed with that conclusion based on its review of Carlton’s study of air quality impacts of the reclamation plan, but the District emphasized it was not referring to the “full project” but only the reclamation plan. The District noted that it had received “an air quality impact analysis in September of 2007 from the project proponents for only the reclamation portion of the project. The study does not address the cumulative impacts created hy the full project.” (Italics added.) It is clear that County did not attempt to evaluate the air quality impacts of the entire mining project.
To appreciate the potential impact of the mining activity on air quality, a basic description of that activity is necessary. At the public hearing before the Board, Carlton’s manager stated that calcite material from the surface mine would be hauled in 40-ton trucks to an undisclosed site near the mine, off a dirt road, where it would be partially processed (crushed to 1.5 inches in size), then loaded into smaller trucks
We believe that regardless of which estimate of total truck trips is more accurate, the bottom line is that there will be extensive and daily use of heavy-duty diesel trucks, at a rate of at least 40 truckloads per day, hauling
We also point out that there existed information supporting a fair argument that the project may result in significant impacts to the environment regarding issues of water resources and biology. County staff acknowledged that one of the dirt roads for truck access to the excavation site is “basically in the river bottom” or “creek bottom. ... It washes out continuously.” The California Regional Water Quality Control Board reviewed the site plan for the project and identified in an April 13, 2006, comment letter to County the existence of a channel that appeared to be “a blue line stream,” and emphasized it was environmentally important that daily mining activity not be permitted to alter such a channel’s course, or impact its water quality or habitat. Along the same lines, a January 5, 2006, comment letter regarding the project from California’s Department of Fish and Game noted, among other things, the following potential impacts: “The proposed Project has the potential to substantially impact blue oak woodland, native and non-native grassland, intermittent streams, and the species dependent upon these resources. Wetland seeps may occur in the vicinity of limestone deposits and could be impacted by mining activities. The Project site is located within the known distribution range for the State-listed threatened Tehachapi slender salamander .... Traffic flow generated by the Project could result in take of the State and Federally-listed threatened desert tortoise . . . and the State-listed threatened Mohave ground squirrel due to vehicle strikes.”
As this brief summary indicates, there was information before County from agencies with expertise in the areas described that the project could significantly impact water resources and plant and animal life in the area. County largely ignored this information (along with air quality impacts of mining operations) because it was convinced that it was only responsible to consider the impacts of the reclamation plan alone. We conclude from the information
DISPOSITION
The judgment is reversed. The matter is remanded to the trial court with directions to vacate its order denying the petition for writ of mandate and to enter a new order that grants the writ of mandate and directs County to (1) set aside the adoption of the mitigated negative declaration concerning the reclamation plan, (2) set aside the approval of the conditional use permit for the reclamation plan, (3) comply with SMARA by requiring a permit for Cárlton’s proposed surface mining operations as well as the approval of a reclamation plan and any other requirements of SMARA, (4) comply with CEQA by undertaking, prior to the issuance of any such permit or approval, environmental review of the entire project, including mining operations, by means of preparation and certification of a legally sufficient EIR regarding the entire project. Costs on appeal are awarded to petitioners.
Hill, Acting P. J., and Detjen, J., concurred.
Notes
Unless otherwise indicated, all further statutory references are to the Public Resources Code. There are also regulations that supplement or clarify the statutory law of CEQA. These regulations are found at California Code of Regulations, title 14, section 15000 et seq., and are referred to herein as CEQA Guidelines.
The applications were actually made through Carlton’s predecessor entities, as clarified herein below.
SMARA requires reclamation plans for surface mining operations in California after 1975 (§§ 2710, 2711, 2712, 2770, 2776) and provides, among other things, that “no person shall conduct surface mining operations unless a permit is obtained from, a reclamation plan has
Not only was the reclamation plan itself considered separately, but County’s environmental review was not aided by the federal environmental study. That is, County did not adopt, rely on or consult BLM’s environmental documents.
Aside from this brief summary of the initial application and approval process, we shall otherwise refer herein to the project proponent solely as Carlton.
Carlton’s position is that the only approval it was seeking from County was for the reclamation plan. Even if that were the case, under the circumstances of this case, County was required to comply with its obligation to review the entire project, as we proceed to explain.
At the final hearing, Kern County Planning Director Ted James advised the Board that all that was before it was the reclamation plan, not the mining operations. He stated that issues related to mining operations were, or should have been, addressed through the federal NEPA process conducted by BLM. He did not say that County ever incorporated, relied on, or even considered the environmental information generated by BLM’s NEPA process. In fact, another planning department staff person stated, “I don’t think we even knew it was happening.” The trial court rightly concluded that BLM’s Environmental Assessment was not used by County as a joint or surrogate CEQA document.
Leroy Cass, who is not a party to this appeal, was at that time one of the petitioners.
This is true even when a project takes place on federal land. (See pt. HI., post.)
In an amendment to section 2728 that took effect on January 1, 2007, the definition of a “lead agency” was shortened to the following: “ ‘Lead agency’ means the city, county ... or the board which has the principal responsibility for approving a reclamation plan pursuant to this chapter.” (Stats. 2006, ch. 869, § 18.) The amended definition does not alter the conclusion that County is the lead agency.
A permit is defined under SMARA as “any authorization from, or approval by, a lead agency, the absence of which would preclude surface mining operations.” (§ 2732.5.)
As we explain herein post, we distinguish the situation in which an owner of a preexisting and ongoing mining operation (with a vested right to mine) is seeking approval of a reclamation plan only.
So much importance is attached to the lead agency role, CEQA prohibits delegation of that role to another agency. (Planning & Conservation League v. Department of Water Resources, supra,
In the instant case, unlike the El Dorado County case, no further environmental review of the mining operation was going to take place after County approved Carlton’s application relating to a reclamation plan only.
As we noted earlier in our background factual summary, Carlton’s applications were made to County and BLM for governmental approvals, both applications described the mining operations and the reclamation plan, were submitted within the same general time period in 2005 and were (briefly) pending concurrently.
Since the MOU did not do this, we need not resolve the question of whether such an agreement could permissibly do so without violating requirements of California law as set forth in SMARA and CEQA. Without deciding the issue, we note that we know of no legal basis for County to contractually abdicate its responsibilities under these statutes.
The purposes of the MOU are stated therein as follows: “(1) [Assuring the application of adequate and appropriate reclamation throughout the State of California; (2) simplifying the administration of surface mining and reclamation practice requirements on Federal lands and on a combination of Federal and private lands; (3) achieving coordination of activity governing reclamation; and (4) eliminating duplication among the . . . agencies and counties serving as lead agencies (‘lead agencies’ pursuant to [SMARA]) in implementing State and Federal requirements.”
It comes as no surprise that the federal government would want to maintain the right to approve mining oрerations on its own land. That federal approval, however, does not by itself absolve County of its obligations under SMARA and CEQA.
The MOU is in essence the same as the CEQA provisions that state how to proceed when both NEPA and CEQA apply to the same project, which provisions are discussed herein below.
CEQA Guidelines, section 15221, subdivision (b), adds: “Because NEPA does not require separate discussion of mitigation measures or growth inducing impacts, these points of analysis will need to be added, supplemented, or identified before the EIS can be used as an EIR.”
The California Coastal Act of 1976 provides for environmental regulation of projects in certain coastal regions and is certified as a regulatory program that is in compliance with CEQA. (See CEQA Guidelines, § 15251, subd. (c).)
We reiterate that no conflict with any federal law has been argued or shown in this case.
Apparently, the smaller trucks had a 25-ton capacity.
Although this calculation was disputed, it was never shown to be in error.
The use of the heavy tracks at a rate of 40 trips per day would also cause a significant impact (i.e., inordinate wear and tear) on County roads that are used by the tracks. Interestingly, on this point, County stepped in and sought to mitigate an impact of the mining operations by requiring Carlton to either (1) “provide a 0.20-foot asphalt concrete overlay on Jawbone Canyon Road from Highway 14 to a point at the end of the existing pavement approximately four miles to the west,” or (2) contribute a specified amount of funds to the road resurfacing. On the record before us, we have insufficient information to decide whether this mitigation measure would likely reduce the impact on County roads to a level that would be less than significant.
